LEADERSHIP IMPLICATIONS IN COMPLEX PROJECTS: THE BOEING DREAMLINER AND CEO JIM MCNERNEY In defense of criticism...

LEADERSHIP IMPLICATIONS IN COMPLEX PROJECTS: THE BOEING DREAMLINER AND CEO JIM MCNERNEY

In defense of criticism of Boeing’s 787 production delays, CEO Jim McNerney explained: We are trying to come up with the strongest set of partnerships we can with the people that supply our major systems and structures. In defense, we are trying to respond to the pressures of governments buying fewer things at lower prices, with less favorable contract terms. And that pressure cannot just stop at Boeing. We have to find willing partners to share the burden. And on the commercial side, low-cost carriers and a very flattish global economy leads you to the same conclusion. So the ‘no-fly list’ is people who don’t want to play ball, who only want to hide behind the contractual language of their current programs. We’re going to give those who do want to work with us more business—or we’ll move some things in-house. This is the reality we all face. The majority of suppliers are beginning to have productive discussions with us. We have some holdouts, people who take the position that the pressure should only be absorbed by Boeing, notwithstanding the fact that 65 percent of most of our airplanes are built by suppliers…we both have to demand lots of productivity improvements to offset price pressure. Those that work with us in that way will find more volume. We are the biggest player. My message is, ‘Don’t bet against us.

The Boeing Dreamliner Boeing Corporation was one of the world's largest manufacturers of commercial aircraft, ranking 27th on the Fortune 500 list in 2016. When it announced the delivery of its first 787 Dreamliner transporter to its first customer, All Nippon Airways, in September, 2011, it was almost 40 months later than originally planned, after a long series of unexpected delays. The actual development cost of the project had been estimated at about US$40 billion but came in over twice the original estimate. One year later, a malfunction was discovered in one of the aircraft's lithium batteries, which caught fire after takeoff. These problems led to months of grounding, imposed by the FAA (Federal Aviation Administration), of the entire Dreamliner fleet already in service. The Dreamliner was designed to be a revolutionary project in terms of physical characteristics, technology, management style, financing, design and engineering management, quality assurance, and assembly processes. Many of these initiatives were intentionally taken on to benefit from new developments in aviation technology and to speed up design and development; however, they posed unexpected challenges for both the company and the project team.

A New Organizational Paradigm: Boeing adopted a new organizational paradigm for the development of Dreamliner and decided to outsource an unprecedented portion of the design, engineering, manufacturing, and production to a global network of 700 local and foreign suppliers. With more than 70% foreign development content, this decision turned Boeing's traditional supply chain into a development chain. Tier-1 suppliers became responsible for the detailed design and manufacturing of 11 major subassemblies, while Boeing only did system integration and final assembly.

Furthermore, Boeing came up with a new risk and revenue sharing contract with its suppliers, called the “build-to-performance” model (as differentiated from the more typical “build-to-spec” or “build-to print” models). According to the model, contract suppliers bore the non-recurring R&D cost up-front, owned the intellectual property of their design, and got paid a share of the revenues from future aircraft sales. Under this model, the suppliers’ roles were dramatically changed from mere subcontractors to strategic partners who had a long-term stake in the project. This model created some risks, which caused extensive integration problems and additional delays.

Finally, Boeing employed a new assembly method. Subcontractors were required to integrate their own subsystems and send their preassembled subsystems to a single final assembly site. The goal was to reduce Boeing's integration effort by leveraging subcontractors to do more work compared with previous projects. However, many of these subcontractors were not able to meet their delivery schedules due to lack of experience in subsystem design and integration, as well as insufficient guidelines and training. As a consequence, parts and assemblies, which were sent to Boeing for integration, were missing the appropriate documentation, including instructions for final assembly. Unanticipated Consequences Supply chain and design delays increased, as did Boeing’s financial losses, including penalties for late delivery of the aircraft.

CEO McNerney had to face some hard facts based on earlier decisions. He acknowledged that his new paradigm may have been flawed, “We got a little bit seduced that it would all come together seamlessly and the same design rules would be applied everywhere in the world and corners wouldn’t be cut and financial realities wouldn’t hit certain folks. McNerney’s approach to workers, suppliers, and labor resources was notably off-putting, according to many in Washington State, Boeing’s corporate home. Since 2011 when Boeing opened its non-unionized South Carolina assembly plant where salaries were approximately $10/hour less than those of the unionized workers in Washington State, worker relationships have been troubled. While admirers have touted his efficiency and ability to deliver profits, alienated professionals at every level, along with union members, have described McNerney as “cold-blooded.” One labor specialist stated, “A lot of employees feel top management doesn’t value them, treats them as expendable [creating an atmosphere of] lowered trust, anger and disgruntlement.

According to Richard Aboulafia, noted aerospace specialist, “Management believes if it continues to squeeze suppliers and labor, the problem[s] will be solved. Again, the track record here is not great. Most of the manufacturing world tell a very different story. Whether it’s with cars, aircraft or turbines, productivity improvements often come from the shop floor. That means convincing the people who build things to identify ways to reduce scrap, improve work flow and eliminate defects. To promote the kind of process improvements that happen in the factory, a work force needs incentives such as profit-sharing or other compensation. At the very least, machinists and engineers need to believe their work is valued. Taking away pensions at a time of record sales is simply a bad way to motivate workers to go the extra mile. Boeing right now embodies a strange combination of very good and very bad.

McNerney’s management style created its own problems. He vacillated between maintaining his dispassionate, hands-off general management style with multiple-times per day meetings with executives during the Dreamliner grounding crisis. His revolving door policy for managers in charge of the 787 project (four in as many years) generated a sense of uncertainty at all levels in the company and increased pressure to meet goals quickly. This focus on urgency caused him to reflect, after having resolved the major problems in the Dreamliner, that the plane could have been completed sooner had Boeing listened more to the customer and less to innovative technology. He said, in a rare interview in 2014, “What I would like to have done is pursued 70 percent of the technology that still would have satisfied 95 percent of [customer desire]. It would have gotten to them quicker, and it would have cost us less…You get excited about these projects, and things creep into the design and you lose discipline sometimes. We just need to be reminded about that. As described by an anonymous former Boeing executive, “The sense I always got from him in meetings is that it could have been any business…If we’d been making cameras or autos or doing bond trading, it would have all been the same to him. The net effect is distancing from the people who come to work there every day, who bring their hearts and souls to it and want to make it more than a job.

Required

What can we learn from Boeing’s Dream-liner experience in terms of project management? Apply your understanding and knowledge of the project management course.

Note : Answers should be in word version format written and in details and in your own words

Homework Answers

Answer #1

Ans

From the case it becomes evident that following aspects of Project Management were not followed in the Project Initiation phase:

Extensive Outsourcing Policy: New Assembly method where subcontractors were expected to design, manufacture some components on strategic partnership model. This method did not take into consideration that suppliers lacked the experience needed to handle such critical job. Thus Feasibility testing did not happen properly This led to delays as the parts did not meet the standards and corners were cut to reduce costs at the expense of quality.

In the Project Planning stage Boeing planned for a new assembly method. Subcontractors were required to integrate their own subsystems and send their preassembled subsystems to a single final assembly site. However it did not take into consideration the documentation standards in the Communication Plan to be followed by the suppliers as well as the risk of quality issues arising in Risk Management phase of the project. Project monitoring was

In the Project Execution phase no centralized teams were formed to help the suppliers learn the ropes of meet and manufacturing the components. No tracking systems were set up to track the progress of the component manufacturing with the suppliers which led to delays.

In the Project Monitoring phase no special monitoring system were put in place to monitor and take corrective action design needed.

In the project closure phase the learnings from the delay and over budgeting was not documented to prevent such occurrence in future.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
LEADERSHIP IMPLICATIONS IN COMPLEX PROJECTS: THE BOEING DREAMLINER AND CEO JIM MCNERNEY In defense of criticism...
LEADERSHIP IMPLICATIONS IN COMPLEX PROJECTS: THE BOEING DREAMLINER AND CEO JIM MCNERNEY In defense of criticism of Boeing’s 787 production delays, CEO Jim McNerney explained: We are trying to come up with the strongest set of partnerships we can with the people that supply our major systems and structures. In defense, we are trying to respond to the pressures of governments buying fewer things at lower prices, with less favorable contract terms. And that pressure cannot just stop at Boeing....
The Boeing Company, headquartered in Chicago, Illinois, is one of the two major producers of aircraft...
The Boeing Company, headquartered in Chicago, Illinois, is one of the two major producers of aircraft in the global market. The other major producer is European Airbus. Boeing produces three models in Everett, Washington: 747s, 767s, and 777s. The planes are all produced in the same building. At any one time, there may be as many as six planes in various stages of production. Obviously the building has to be fairly large to accommodate such a huge undertaking. In fact,...
Please read this scenario and job description carefully. You are involved in the prestigious but often...
Please read this scenario and job description carefully. You are involved in the prestigious but often challenging Google recruitment process. As part of this process you are required to respond to several questions and activities. All your answers must address the context of this scenario and the information given in the individual questions. Job description - Software development professional at Google There's no such thing as “a normal day" at Google. We work to create and maintain the safest operating...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
The Business Case for Agility “The battle is not always to the strongest, nor the race...
The Business Case for Agility “The battle is not always to the strongest, nor the race to the swiftest, but that’s the way to bet ’em!”  —C. Morgan Cofer In This Chapter This chapter discusses the business case for Agility, presenting six benefits for teams and the enterprise. It also describes a financial model that shows why incremental development works. Takeaways Agility is not just about the team. There are product-management, project-management, and technical issues beyond the team’s control. Lean-Agile provides...
Professor Edwards’s “Fundamentals of Supervision” class was in the fifth week, and the class was discussing...
Professor Edwards’s “Fundamentals of Supervision” class was in the fifth week, and the class was discussing servant leadership. Professor Edwards identified three things for the students to consider. “Leaders need to create a vision for their team that will create a future for the organization based on resilience. Leaders need to use the talents and skills of their team members to get the best results. Leaders need to find ways to engage their followers to be the best they can...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by 10 percent rather than the target of 25 to 35 percent. Internal resources were reduced by only 5 percent. The reduction in prototype time and cost was 15 percent rather than the expected 30 to 35 percent. Como’s automotive customers were not pleased with the slow progress and relatively immature performance of the company’s’ project management system. Change was taking place, but not fast...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by 10 percent rather than the target of 25 to 35 percent. Internal resources were reduced by only 5 percent. The reduction in prototype time and cost was 15 percent rather than the expected 30 to 35 percent. Como’s automotive customers were not pleased with the slow progress and relatively immature performance of the company’s’ project management system. Change was taking place, but not fast...
Jim Watanabe was in his new car, driving down I-5, on his way to work. He...
Jim Watanabe was in his new car, driving down I-5, on his way to work. He dreaded the phone call he knew he was going to have to make. The original go-live date for a pilot implementation of Petrie Electronics’ new customer relationship management (CRM) system was July 31. That was only six weeks away, and Jim knew there was no way they were going to be ready. The XRA CRM they were licensing turned out to be a lot...
Read the Who makes the Apple iPhone? case study and answer the question which follows. In...
Read the Who makes the Apple iPhone? case study and answer the question which follows. In answering the question, relate your discussion to the facts presented within the case. Who makes the Apple iPhone? In its early days, US-Based Apple usually didn’t look beyond its own backyard to manufacture its devices. By 2004, however, Apple had largely turned to foreign manufacturing. The shift to offshore manufacturing reached its peak with the iconic iPhone, which Apple first introduced in 2007. All...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT