Question

LEADERSHIP IMPLICATIONS IN COMPLEX PROJECTS: THE BOEING DREAMLINER AND CEO JIM MCNERNEY In defense of criticism...

LEADERSHIP IMPLICATIONS IN COMPLEX PROJECTS: THE BOEING DREAMLINER AND CEO JIM MCNERNEY

In defense of criticism of Boeing’s 787 production delays, CEO Jim McNerney explained: We are trying to come up with the strongest set of partnerships we can with the people that supply our major systems and structures. In defense, we are trying to respond to the pressures of governments buying fewer things at lower prices, with less favorable contract terms. And that pressure cannot just stop at Boeing. We have to find willing partners to share the burden. And on the commercial side, low-cost carriers and a very flattish global economy leads you to the same conclusion. So the ‘no-fly list’ is people who don’t want to play ball, who only want to hide behind the contractual language of their current programs. We’re going to give those who do want to work with us more business—or we’ll move some things in-house. This is the reality we all face. The majority of suppliers are beginning to have productive discussions with us. We have some holdouts, people who take the position that the pressure should only be absorbed by Boeing, notwithstanding the fact that 65 percent of most of our airplanes are built by suppliers…we both have to demand lots of productivity improvements to offset price pressure. Those that work with us in that way will find more volume. We are the biggest player. My message is, ‘Don’t bet against us.

The Boeing Dreamliner Boeing Corporation was one of the world's largest manufacturers of commercial aircraft, ranking 27th on the Fortune 500 list in 2016. When it announced the delivery of its first 787 Dreamliner transporter to its first customer, All Nippon Airways, in September, 2011, it was almost 40 months later than originally planned, after a long series of unexpected delays. The actual development cost of the project had been estimated at about US$40 billion but came in over twice the original estimate. One year later, a malfunction was discovered in one of the aircraft's lithium batteries, which caught fire after takeoff. These problems led to months of grounding, imposed by the FAA (Federal Aviation Administration), of the entire Dreamliner fleet already in service. The Dreamliner was designed to be a revolutionary project in terms of physical characteristics, technology, management style, financing, design and engineering management, quality assurance, and assembly processes. Many of these initiatives were intentionally taken on to benefit from new developments in aviation technology and to speed up design and development; however, they posed unexpected challenges for both the company and the project team.

A New Organizational Paradigm: Boeing adopted a new organizational paradigm for the development of Dreamliner and decided to outsource an unprecedented portion of the design, engineering, manufacturing, and production to a global network of 700 local and foreign suppliers. With more than 70% foreign development content, this decision turned Boeing's traditional supply chain into a development chain. Tier-1 suppliers became responsible for the detailed design and manufacturing of 11 major subassemblies, while Boeing only did system integration and final assembly.

Furthermore, Boeing came up with a new risk and revenue sharing contract with its suppliers, called the “build-to-performance” model (as differentiated from the more typical “build-to-spec” or “build-to print” models). According to the model, contract suppliers bore the non-recurring R&D cost up-front, owned the intellectual property of their design, and got paid a share of the revenues from future aircraft sales. Under this model, the suppliers’ roles were dramatically changed from mere subcontractors to strategic partners who had a long-term stake in the project. This model created some risks, which caused extensive integration problems and additional delays.

Finally, Boeing employed a new assembly method. Subcontractors were required to integrate their own subsystems and send their preassembled subsystems to a single final assembly site. The goal was to reduce Boeing's integration effort by leveraging subcontractors to do more work compared with previous projects. However, many of these subcontractors were not able to meet their delivery schedules due to lack of experience in subsystem design and integration, as well as insufficient guidelines and training. As a consequence, parts and assemblies, which were sent to Boeing for integration, were missing the appropriate documentation, including instructions for final assembly. Unanticipated Consequences Supply chain and design delays increased, as did Boeing’s financial losses, including penalties for late delivery of the aircraft.

CEO McNerney had to face some hard facts based on earlier decisions. He acknowledged that his new paradigm may have been flawed, “We got a little bit seduced that it would all come together seamlessly and the same design rules would be applied everywhere in the world and corners wouldn’t be cut and financial realities wouldn’t hit certain folks. McNerney’s approach to workers, suppliers, and labor resources was notably off-putting, according to many in Washington State, Boeing’s corporate home. Since 2011 when Boeing opened its non-unionized South Carolina assembly plant where salaries were approximately $10/hour less than those of the unionized workers in Washington State, worker relationships have been troubled. While admirers have touted his efficiency and ability to deliver profits, alienated professionals at every level, along with union members, have described McNerney as “cold-blooded.” One labor specialist stated, “A lot of employees feel top management doesn’t value them, treats them as expendable [creating an atmosphere of] lowered trust, anger and disgruntlement.

According to Richard Aboulafia, noted aerospace specialist, “Management believes if it continues to squeeze suppliers and labor, the problem[s] will be solved. Again, the track record here is not great. Most of the manufacturing world tell a very different story. Whether it’s with cars, aircraft or turbines, productivity improvements often come from the shop floor. That means convincing the people who build things to identify ways to reduce scrap, improve work flow and eliminate defects. To promote the kind of process improvements that happen in the factory, a work force needs incentives such as profit-sharing or other compensation. At the very least, machinists and engineers need to believe their work is valued. Taking away pensions at a time of record sales is simply a bad way to motivate workers to go the extra mile. Boeing right now embodies a strange combination of very good and very bad.

McNerney’s management style created its own problems. He vacillated between maintaining his dispassionate, hands-off general management style with multiple-times per day meetings with executives during the Dreamliner grounding crisis. His revolving door policy for managers in charge of the 787 project (four in as many years) generated a sense of uncertainty at all levels in the company and increased pressure to meet goals quickly. This focus on urgency caused him to reflect, after having resolved the major problems in the Dreamliner, that the plane could have been completed sooner had Boeing listened more to the customer and less to innovative technology. He said, in a rare interview in 2014, “What I would like to have done is pursued 70 percent of the technology that still would have satisfied 95 percent of [customer desire]. It would have gotten to them quicker, and it would have cost us less…You get excited about these projects, and things creep into the design and you lose discipline sometimes. We just need to be reminded about that. As described by an anonymous former Boeing executive, “The sense I always got from him in meetings is that it could have been any business…If we’d been making cameras or autos or doing bond trading, it would have all been the same to him. The net effect is distancing from the people who come to work there every day, who bring their hearts and souls to it and want to make it more than a job.

Required

As a project leader how successful is the CEO McNerney in handling the overall project and its workforce? Evaluate his leadership capabilities in the light of a successful project leader.

Note : Answer should be in word version format written please and in your own words and in details

Homework Answers

Answer #1

After going through the given case of The Boeing Dreamliner and the CEO Jim McNerney, it can be identified that McNerney was not an efficient project leader while handling the overall project and its workforce. With so many issues during the project tenure he as a leader could have determined ways of keeping employees motivated. It was observed that employees felt that top management doesn’t value them and it resulted in lowering employees trust, gave rise to anger and dissatisfaction.

Some of the characteristic and capabilities of successful project leader in which McNerney lacked are as follows:

· Critical thinking and problem solving: Successful leaders are capable in critical thinking skills. The CEO Jim McNerney had to face some hard facts because he lacked in critical thinking skills. He emphasised on technology rather than customer needs and demands.

· Decision Making: McNerney did not apply strategic decision making. He decided to outsource design, engineering, manufacturing, and production to a global network of suppliers. But it was determined during integration process that the appropriate documentation was missing along with instructions for final assembly. He failed significantly in strategizing the project.

· Ability to inspire and motivate: McNerney failed terribly to inspire its taskforce. Any successful project leaders can be seen inspiring and motivating employees to work in desired manner to achieve organizational objectives. But in case of Boing under the leadership of the CEO Jim McNerney it can be observed that employees felt dissatisfied and overburdened.

· Setting clear objectives: It can be identified that McNerney failed to set clear objectives for its project team. Any successful tam leader sets clear objectives that a team must achieve before deadlines.

· Planning: Successful project leaders plan projects as per availability of resources including time and finance. But in case of Boing the CEO McNerney did not planned the project appropriately. In-fact no corrective and preventive measures were implemented after the project got delayed.

Therefore, based on the above evaluation, it can be identified that the CEO McNerney was not successful as a project leader.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
LEADERSHIP IMPLICATIONS IN COMPLEX PROJECTS: THE BOEING DREAMLINER AND CEO JIM MCNERNEY In defense of criticism...
LEADERSHIP IMPLICATIONS IN COMPLEX PROJECTS: THE BOEING DREAMLINER AND CEO JIM MCNERNEY In defense of criticism of Boeing’s 787 production delays, CEO Jim McNerney explained: We are trying to come up with the strongest set of partnerships we can with the people that supply our major systems and structures. In defense, we are trying to respond to the pressures of governments buying fewer things at lower prices, with less favorable contract terms. And that pressure cannot just stop at Boeing....
Why would Boeing outsource its electronics production and then bring its manufacture back in-house? In the...
Why would Boeing outsource its electronics production and then bring its manufacture back in-house? In the early 2000s, The Boeing Company (NYSE: BA) outsourced key portions of its aircraft manufacturing and design operations, including electronics and central computers. Beginning in 2007, Boeing’s 787 Dreamliner (a new model for Boeing) was assembled in the U.S., with global subcontractors assigned the work of assembling key sections of the 787. Subcontractors also worked on various software systems and electronics components for the 787....
The Boeing Company, headquartered in Chicago, Illinois, is one of the two major producers of aircraft...
The Boeing Company, headquartered in Chicago, Illinois, is one of the two major producers of aircraft in the global market. The other major producer is European Airbus. Boeing produces three models in Everett, Washington: 747s, 767s, and 777s. The planes are all produced in the same building. At any one time, there may be as many as six planes in various stages of production. Obviously the building has to be fairly large to accommodate such a huge undertaking. In fact,...
The Infusion Pump Roll-Out Jim Altschuler and Mary James were sitting in their conference room on...
The Infusion Pump Roll-Out Jim Altschuler and Mary James were sitting in their conference room on a late Friday in January. They had just received the latest cost projections from the project manager on the new infusion pump system that had been in development for two years. Based on the latest design changes the results were going to result in a major revision to the initial pricing forecasts. While early tests with potential buyers showed great receptivity at an initial...
PM301 ASSESSMENT 2 S118 Case Study: The Case of the Never Ending Scope Creep In 1999,...
PM301 ASSESSMENT 2 S118 Case Study: The Case of the Never Ending Scope Creep In 1999, the XY Department of the Federal Government reviewed its Year 2000 Date Turnover Computer Risks and found that its outdated computer systems for managing public clients needed replacing. A business case was prepared for funding the replacement while at the same time implementing some improvements. The total budget requested was $2.3 million. In view of a shortage of funds around at the time, government...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by 10 percent rather than the target of 25 to 35 percent. Internal resources were reduced by only 5 percent. The reduction in prototype time and cost was 15 percent rather than the expected 30 to 35 percent. Como’s automotive customers were not pleased with the slow progress and relatively immature performance of the company’s’ project management system. Change was taking place, but not fast...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by...
By 1997, Como had achieved partial success in implementing project management. Lead times were reduced by 10 percent rather than the target of 25 to 35 percent. Internal resources were reduced by only 5 percent. The reduction in prototype time and cost was 15 percent rather than the expected 30 to 35 percent. Como’s automotive customers were not pleased with the slow progress and relatively immature performance of the company’s’ project management system. Change was taking place, but not fast...
Jim Watanabe was in his new car, driving down I-5, on his way to work. He...
Jim Watanabe was in his new car, driving down I-5, on his way to work. He dreaded the phone call he knew he was going to have to make. The original go-live date for a pilot implementation of Petrie Electronics’ new customer relationship management (CRM) system was July 31. That was only six weeks away, and Jim knew there was no way they were going to be ready. The XRA CRM they were licensing turned out to be a lot...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...