Question

After the scope has been approved, the next step in the process is determining what is...

After the scope has been approved, the next step in the process is determining what is required to complete the project successfully. This includes evaluating what needs to be procured, human resources needed, allocation of funds, as well as gaining an understanding of the support needed within the organization to deliver the project. This moves the project to the next phase: planning. This typically starts at the define stage and continues through most of the execution phase. The planning stage focuses on development of schedules, budgets, resource requirements—including personnel and funding.

At this point of the project the WBS has been developed and the rest of the project plan and a Gantt chart can be completed. This includes identifying project tasks, task dependencies, milestones, resource assignments, and tasks duration as well as evaluation of the critical path, lag and lead times, slack and float.

Respond to the following topic:

·      Why is it important to ensure the WBS has accurate time and cost estimates?

·      What estimating method, as described in Chapter 5, would you use to estimate the time, cost and resources required to complete each deliverable / task for a new project?

·      In your organization or projects you have seen, which resources types, of the ones described in Chapter 8, are the ones most difficult to schedule accurately and why?

·      Assume your project is about 1/3 complete and due to critical organizational objective changes, the project needs to be completed several weeks sooner. As the Project Manager, what planning options do you have? What estimate variables will be affected by your proposed plan modification?

·      Within the context of the project to create a website or move to a new house, describe the different types of costs you would include and the cost classification they fall under.

Homework Answers

Answer #1

Ans 1

Work BreakDown Structure has project scope broken down into manageable components. These components need to be completed on time and within budget to ensure that the overall project gets completed on time as many components are dependent on each other.

Ans 2.

I would use the wideband Delphi Technique to estimate the time, cost and resources required for the completion of the project.

Ans 3

The most difficult resource to schedule are people. This is because people are working on multiple projects simultaneously and therefore are constrained on time.

Ans 4

To complete the project several weeks earlier I would look at various activities and which of them can be crashed to achieve the required timeline. This would require additional resources in terms of cost and people to finish the work early. I would look at all activities to see how additional cost and resource allocation can reduce the timeline.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Mary Kate is a project manager in the IT department for a university. She has been...
Mary Kate is a project manager in the IT department for a university. She has been asked to manage a project to create a faculty intranet. The university has multiple campuses in various locations, and professors and other faculty need to be able to easily post questions, schedules and other documents to share in a secure environment. Mary Kate performed the following steps to begin the intranet project. She performed a needs analysis. Mary Kate interviewed the university faculty to...
Mary Kate is a project manager in the IT department for a university. She has been...
Mary Kate is a project manager in the IT department for a university. She has been asked to manage a project to create a faculty intranet. The university has multiple campuses in various locations, and professors and other faculty need to be able to easily post questions, schedules and other documents to share in a secure environment. Mary Kate performed the following steps to begin the intranet project. She performed a needs analysis. Mary Kate interviewed the university faculty to...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Case Study Personal Trainer, Inc. owns and operates fitness centers in a dozen Midwestern cities. The...
Case Study Personal Trainer, Inc. owns and operates fitness centers in a dozen Midwestern cities. The centers have done well, and the company is planning an international expansion by opening a new “supercenter” in the Toronto area. Personal Trainer’s president, Cassia Umi, hired an IT consultant, Susan Park, to help develop an information system for the new facility. During the project, Susan will work closely with Gray Lewis, who will manage the new operation. Background You are enjoying your job...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
1) Which of the following is not a valid way that a CRM system can collect...
1) Which of the following is not a valid way that a CRM system can collect information? A. accounting system B. order fulfillment system C. inventory system D. customer’s personal computer 2)Which of the following is a common marketing CRM metric? A. number of new prospective customers B. average number of service calls per day C. average time to resolution D. cost per interaction by marketing campaign 3)Which question below represents a CRM reporting technology example? A. Why did sales...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do several international Camp Noah projects. Last year the French government asked for resources for children in Southeastern France who had been affected by floods; LSS responded within 15 weeks with a French Camp Noah curriculum that met many of the project objectives. The Board of Directors of LSS commended the effort; international expansion was added to this year’s strategic objectives for the LSS organization....
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
You work for Microsoft in their global smart phone group. You have been made project manager...
You work for Microsoft in their global smart phone group. You have been made project manager for the design of a new smart phone. Your supervisors have already scoped the project so you have a list showing the work breakdown structure and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!      You have been given the information in Exhibit 5.13. It includes all the...