Question

(UPDATED) Consider a project that requires the completion of 7 tasks, as follows: o Tasks A...

(UPDATED) Consider a project that requires the completion of 7 tasks, as follows:

o Tasks A and B can begin simultaneously at the beginning (“time zero”).

o Task C can only begin after task B is completed.

o Task D can only begin after task A is completed.

o Task E can only begin after task A is completed.

o Task F can only begin after task E is completed.

o Task G can only begin after tasks C and D are completed.

The expected durations (in days) of each task are as follows: A=15; B=20; C=10; D=10; E=30; F=20; G=40.

What is the expected completion of the whole project?

A. 50 days

B. 60 days

C. 70 days

D. 75 days

Consider the project from the previous question with the added complexity that the actual completion time of each task will be:

Task Completion Time
A 15+RANDBETWEEN(-8,8)
B 20+RANDBETWEEN(-8,8)
C 10+RANDBETWEEN(-8,8)
D 10+RANDBETWEEN(-8,8)
E 30+RANDBETWEEN(-8,8)
F 20+RANDBETWEEN(-8,8)
G 40+RANDBETWEEN(-8,8)

Using PERT, what is the expected completion time of the project?

A. 50 days

B. 60 days

C. 70 days

D. 75 days

Homework Answers

Answer #1

First, prepare a chart with the expected duration and precedence order.

Based on this, the duration time is 70 days.

Part 1 : Option C (70 days)

Part 2

This will be based on the estimated task times which include a randbetween function as well. This will lead to different overall estimated time since every time we run the function on excel, a different value will be returned.


Below is a the table based on the values returned when I ran the randbetween function.

Based on this, the value of the expected completion time is 58 days which can be approximated to 60 days (Option B)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity Completion (Days) Immediate Precedence A. Architectural Design 3 - B. Clearing of Land 6 A...
Activity Completion (Days) Immediate Precedence A. Architectural Design 3 - B. Clearing of Land 6 A C. Fencing of project site 7 A D. Digging of foundation 5 A E. Completion of foundation work 13 B,C F. Raising of pillars and block work. 8 C,D G. Roofing 11 D,F H. Furnishing of the cathedral 6 G,E a. Redraw the network diagram for the construction of the National Cathedral by using the above information provided in the table to complete the...
PERT Consider the following table: Activity Prec. Act t0 tml tp te A - 3 4...
PERT Consider the following table: Activity Prec. Act t0 tml tp te A - 3 4 5 4 B - 5 8 11 8 C A 1 2 3 2 D B 2 5 8 5 E B 4 6 8 6 F C,D 1 1 1 1 G E 3 4 5 4 H G,F 2 3 4 3 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the...
Consider the table below, which includes time and activity data for a Small IT Project. All...
Consider the table below, which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform a critical path analysis for this project. Activity Duration (Days) Predecessor A 8 - B 10 A C 18 A D 4 A E 28 B, D F 2 C, E G 32 E H 18 B I 12 F J 2 H, G, I Draw a network diagram representing the project. MS PowerPoint or...
Suppose you are given a set S = {a1,a2,···,an} of tasks, where task ai requires pi...
Suppose you are given a set S = {a1,a2,···,an} of tasks, where task ai requires pi units of processing time to complete, once it has started. You have one computer on which to run these tasks, and the computer can run only one task at a time. Let ci be the completion time of task ai, that is, the time at which task ai completes processing. Your goal is to minimize the average completion time, that is, to minimize n1...
#3) Planned duration of a project is 28 weeks. Budget at completion for the project is...
#3) Planned duration of a project is 28 weeks. Budget at completion for the project is $525,000. The project is in its 25th week. The actual cost (thus far) is $270,000. At this point in the plan, the planned cost was expected to be $261,000. For the work performed to date, the earned value is estimated at $272,000. Compute the following for the project (10 points) a) Cost variance. b) Schedule variance. c) If rest of the project is assumed...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C...
TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C Beans -B 10 sec D Meat -B 10 sec E Salsa -C, D 10 sec F Cheese -E 5 sec G Sour Cream -E 10 sec H Lettuce -E 10 sec I Wrap -F, G, H 15 sec J Bag -I 5 sec K Checkout/pay -J 25 sec Achieving the above cycle time and output, what is the theoretical number of workstations? Assign tasks...
1. Given is a PERT project network diagram as shown below: Activity Start A B C...
1. Given is a PERT project network diagram as shown below: Activity Start A B C D E F G H I J K End Time 0 18 24 21 38 28 34 22 20 34 34 16 0    a) The Project Completion time =   b) The Earliest Start time, ES, of Activity F =   c) The Earliest Start time, ES, of Activity K =   d) The Latest Start time, LS, of Activity E =   e) The non-critical activities...
A landscaping project consists of the activities below. The following information describes the relationships between the...
A landscaping project consists of the activities below. The following information describes the relationships between the activities that need to be completed for this project.                         Immediate Activity      Predecessors                A      -                B      A                C      A                D      C                E       B, D Using the data above, develop a network for this project. The following are estimates of optimistic, most likely, and pessimistic times. Activity      Optimistic time Most Likely Time Pessimistic Time                A      3                                   4                                  ...
A project is represented by the activity durations (in days, estimated at 90% likelihood of completion)...
A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many project buffers are needed if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length A -- 18 E C, D 13 B -- 16 F C 9 C A 22 G E, F 15 D B 14 ​ ​ ​ options: 0 1 2 3
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT