16. Using a level production plan and the data below, calculate total ending inventory and total...

16.

Using a level production plan and the data below, calculate total ending inventory and total backorders, respectively.

Week 1 = 230

Week 2 = 250

Week 3 = 180

Week 4 = 170

Week 5 =200

Week 6 = 223

Week 7 = 224

Beginning inventory = 0

8 and 270

270 and 8

52 and 104

30 and 223

8 and 220

17.

Which of the following variable is estimated in linear regression?

Smoothing coefficient

Dependent variable

Independent variable

Total number of employees

Slope

Homework Answers

Answer #1

Answer 16 ) Total Demand = (230 + 250 + 180 + 170 + 200 + 223 + 224) = 1477

By level production plan, estimated production for each week = (1477 / 7) = 211

Beginning Inventory = 0

Weeks 1 2 3 4 5 6 7
Production 211 211 211 211 211 211 211
Demand 230 250 180 170 200 223 224
Ending Inventory 0 0 0 14 25 13 0
Backorder 19 58 27 0 0 0 0

Total Ending Inventory = (14 + 25 + 13) = 52

Total Backorder = (19 + 58 +27) = 104

Answer 17) The value of a dependent variable is estimated via linear regression method. A linear equation is formed out of the trend values which includes the slope and intercept values. The value of the dependent variable is then calculated corresponding to the value of the independent variable as there exists a relation between the two variables.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Matthew and Mark work for AMG, and want to do some aggregate planning using "Level Production...
Matthew and Mark work for AMG, and want to do some aggregate planning using "Level Production without Backorders" for the manufacturing of brake calipers for Mercedes Benz S63 sedans. They figure the front brake calipers take 9 hours to forge and assemble while the rear calipers take 7 hours to forge and assemble. They pay their people $24.00 per hour and it costs them $900.00 to hire and $1,300 to fire each employee. They currently employ 6 people and have...
A manager is attempting to put together an aggregate plan for the coming nine months. She...
A manager is attempting to put together an aggregate plan for the coming nine months. She has obtained a forecast of expected demand for the planning horizon. The plan must deal with highly seasonal demand; demand is relatively high in periods 3 and 4 and again in period 8, as can be seen from the following forecasts:     Period 1 2 3 4 5 6 7 8 9 Total   Forecast 190 230 260 280 210 170 160 260 180 1,940 The...
Pat.# Before After 1 195 125 To the left is 2 datasets measured for a sample...
Pat.# Before After 1 195 125 To the left is 2 datasets measured for a sample of 107 patients with the high cholesterol level before and after taking medication. Obtain the following for both sets: 2 208 164 3 254 152 1- the mean, mode and median 4 226 144 5 290 212 2- the variance and standard deviation 6 239 171 7 216 164 3- First, second and third quartiles 8 286 200 9 243 190 10 217 130...
A loan made on March 14 is due September 13 of the following year. Find the...
A loan made on March 14 is due September 13 of the following year. Find the exact time for the loan in a​ non-leap year and a leap year. days. The exact time in a​ non-leap year is ? days The exact time in a leap year is ? days. Data Table Sequential Numbers for Dates of the Year Day of Month Jan. Feb. Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec. 1 1 32 60 91 121...
Bivariate Data & Probability After completing the calculation by hand in Q1 you can use Excel...
Bivariate Data & Probability After completing the calculation by hand in Q1 you can use Excel to check your answers before submitting. Q2 assesses your general understanding of probability and linear associations using Excel to analyse a large dataset. Question 1       Covariance and Correlation The table below shows a set of sample bivariate data. Calculate the covariance and correlation coefficient by completing the below table. Show all working. X Y (X - ) (Y - ) (X - )(Y -...
Researchers in a 2015 study by Flannery et al. sought to estimate the effectiveness of the...
Researchers in a 2015 study by Flannery et al. sought to estimate the effectiveness of the seasonal influenza vaccine in preventing acute respiratory infection (ARI). A total of 507 subjects from Texas who showed symptoms of ARI were recruited for this study. The data provided show the result of each subject's test for influenza. Click to download the data in your preferred format.    CrunchIt!    CSV    Excel    JMP    Mac-Text    Minitab    PC-Text    R   ...
Your firm works in construction and buys ASTM A325M8S bolts in very large numbers. You are...
Your firm works in construction and buys ASTM A325M8S bolts in very large numbers. You are interested in purchasing bolts from different suppliers and have obtained and tested samples of 200 bolts from three suppliers: Allnutt, Boltzman, Coachers.You have tested these in your new bolt testing machine, purchased after you had discovered your old bolt testing machine was performing erratically. (For the purposes of this question, you are safe to assume that the new machine works perfectly and that its...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT