Question

Assuming that the cost of each activity is linearly distributed over its duration, create two budgets...

Assuming that the cost of each activity is linearly distributed over its duration, create two budgets as follows:

  1. The first budget should assume an early-start schedule
  2. The second budget should assume a late-start schedule
  3. Explain why the two budgets are different
Activity Duration (days) Immediate predecessors Cost
A 3 $3,000
B 4  2,000
C 3  6,000
D 2 C  2,000
E 1 B  1,000
F 5 A 10,000
G 2 B  4,000
H 3 B  9,000
I 11 C 11,000
J 3 D, E  3,000
K 1 F, G  1,000
L 4 K  2,000
M 4 J, H  8,000

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3 A Dennis D 3 B Kate E 8 D William F 10 C Sam G 8 F William H 3 E, G Jane 1. Draw the network diagram and indicate the critical path. 2. Draw the network diagram by specifying Early Start, Early Finish, Late Start, Late Finish, and slacks. 3. Indicate all the activities, duration, start and finish dates, predecessors, resources in a...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D...
Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D C 1 5 E B 2 5 F E 8 5 G D 10 5 H B 2 5 I B 3 5 J F,G,I 3 5 K H 2 5 L J,K 3 5 M L 1 5 i.Construct an activity on the arrow network ii. Determine the Duration of the Critical Path; iii. Draw the corresponding Gantt chart iv. Draw the resource...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A -...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Determine the following for each activity: Expected Duration (round to the nearest whole number) Early Start...
Prepare a table in Excel showing the time-phased budget for the project. Assume the budgeted cost...
Prepare a table in Excel showing the time-phased budget for the project. Assume the budgeted cost is linearly distributed over the duration of the activity, e.g., if the budgeted cost of a Task is $100 and the duration of the Task is 2 weeks, then budgeted cost/week=100/2= $50. All calculations should be done within the Excel spreadsheet. Task Predecessor Budget Cost ($) Duration (weeks) A - $              1,500 4 B A $              1,350 2 C A $              1,260 3 D...
AON The table given below contains the activity label, its respective duration (in weeks) and its...
AON The table given below contains the activity label, its respective duration (in weeks) and its precedents. Use critical path method to find the critical path and activities of this project. ACTIVITY DURATION (IN WEEKS) PRECEDENTS A 6 – B 4 – C 3 A D 4 B E 3 B F 10 – G 3 E, F H 2 C, D
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 -...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 - B 4 - C 5 - D 4 - E 6 K F 2 B,C,D G 4 E.F H 6 F Compute slack for each activity. Activity Slack K B C D E F G H
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and find the critical path(s) Activities Predecessor duration A - 2 B - 10 C A 9 D A,B 7 E A,B 9 F B 5 G C 10 H D,E 1 I D,E,F 2 J F 7 K C,H,I 2 L I,J 2 M I 1 N G,K 5
Francisco is planning a vacation to Germany. A variety of activities must be completed before his...
Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities: Immediate Activity Predecessors A - B - C - D A, B E C F D, E G E H F, G I F J I, H Francisco was also able to estimate the activity times as shown in the table below: Activity Time (Days) A 3 B 4 C 5 D 3 E...