Question

Your firm MS Ankomadu has won a project of €1,785,000 to build a 161kV/33kV sub-station. You...

Your firm MS Ankomadu has won a project of €1,785,000 to build a 161kV/33kV sub-station. You have been selected as the project manager to lead the project team for the successful execution of the project. You are the project manager, there are a total of 8,400 hours of work schedule on the project. You made your checks with the accounting department, and they told you that you have spent a total of €1,144,000. According to the schedule, your team should have worked 5000 hours, but your foreman says that the team was allowed to work some overtime, and they have actually put in 5000 hours of work.                      

Develop the activities sequence for the project in the CASE STUDY above                                                                       

Homework Answers

Answer #1

Answer:

Activity sequence for the project is given in the table below for building an electric substation of 161kV/33kV:

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are a highly regarded project manager at your company. You have demonstrated the ability to...
You are a highly regarded project manager at your company. You have demonstrated the ability to execute and deliver results. You are working on a critical project that has the attention of the CEO. Your project team consists of 25-30 team members where you meet weekly. During a weekly meeting, you learn a team member, Jeff, is withholding information from other team members. Jeff proceeds to throw a tantrum during the meeting and accuses you of misrepresenting his work and...
Chase Opportunity has selected you as the project manager to oversee their latest project – Chase...
Chase Opportunity has selected you as the project manager to oversee their latest project – Chase Retail Complex. Chase’s vision is to build four (4) 10,000 square foot buildings (see concept drawing below). Within each building, suite sizes may vary per customer rental agreement (estimating five (5) 2,000 square foot areas per building). Chase has the funds to cover the total project costs and they have already purchased the land for construction. Chase wants to start construction January 2, 2007...
You are the supervising manager at an engineering firm. A client has requested your firm work...
You are the supervising manager at an engineering firm. A client has requested your firm work on a project that is handled frequently by your employees. The standard hours for projects of this nature is 36 hours for one engineer. You have decided to hand this incoming project to a brand new hire who just graduated with her engineering degree. What should your expectation be regarding the standard of 36 hours for this particular project? Why?
Your manager has asked you to take on an existing project from a peer PM who...
Your manager has asked you to take on an existing project from a peer PM who is leaving the company. As you hold the knowledge transfer, you learn that your co-worker signed a statement of work (approx. $150,000) with an outside vendor with no involvement from strategic sourcing. Additionally, the business requirements have not yet been finalized internally within your project team nor tied to the statement of work. The contract states the work is expected to start within five...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Sydney was a newly hired project manager at a consulting firm. She has previous experience working...
Sydney was a newly hired project manager at a consulting firm. She has previous experience working on project teams but had never led a project on her own. She has only been with the firm for two weeks and has spent a week of that time in onboarding. Her manager, the head of operations, has just assigned her to a rather large project. The project is to evaluate the current processes in use within the organization specifically focused in two...
You are the project manager for a new multimillion-dollar building renovation for your organization. The company...
You are the project manager for a new multimillion-dollar building renovation for your organization. The company needs to maximize the space that it has, and the best approach is to do a staggered build-out in order to better maximize the space in the existing building. You feel that the best approach was to negotiate with multiple contractors on a fixed-price contract. Different contractors discussed other contracts with you, particularly ones to address the current market fluctuations in the raw materials...