Question

Explain what you think the role of the Project Manager is in each of the four...

Explain what you think the role of the Project Manager is in each of the four phase categories, Initiating, Planning, Performing, and Closing Steps that the project is going through. Starting with the most difficult and challenging, rank the relative difficulty and challenge each step of the process to the project manager. Must contain a reason for each ranking.

Describe the possible benefits that the project manager might gain from gathering and reviewing information to better organize and prepare future projects. Explain the largest project you have completed / worked on as project manager / project team member. Include the number of people involved and identify the degree of success of the project.

Homework Answers

Answer #1

Role of project manager in different phases

Initiating

The project manager is responsible to develop a project charter that should include goals, objectives and mission of project. In this stage, the project manager needs to define outcomes of project clearly to approve the project. The project manager is also responsible to identify and manage the stakeholders

Planning phase

Project manager is responsible to develop plan for project management, to define the scope of project, and to create a structure of WBS. He or she is responsible to plan and define schedule of project, and activities to complete project. He or she is also required to estimate needed resources. In this phase, the project manager is required to create a budget and manage quality. Requirements of project members are also required. A better communication is also desired from the project manager. Risk management planning as well as planning for procurement of materials is also required from project manager

Performing

In this phase, the project manager is responsible to direct and manage project related activities. He needs to ensure quality level in the project and to select required human resource. He or she also needs to communicate progress of projects to team members and stakeholders. Stakeholder management as well as procurement management is also required.

Controlling phase

Project manager is required to monitor the project work and take proactive approach to introduce necessary changes. Scope management activities are also required as project manager needs to ascertain project scope must be clearly defined. Costs and time management activities are also responsibilities of project manager during controlling phase. Quality maintenance of project, good communication and procurement management activities need to be implemented by project manager. Stakeholder management in this phase is also required.

Ranking of challenging phases of project

Planning

It is the most difficult phase of the project. During planning phase, challenges such as poorly defined scope of project, and schedule to complete the project often creates project failure, therefore, a detailed planning is required by the project managers. If the risk management, and work break down structure are not well planned, they also lead to project failure. Therefore, this phase is most challenging.

Executing phase

The second most difficult phase is execution phase where project manager faces problems such as scope creep, and lack of skills of project team workers. Lack of teamwork can also cause a great challenge for project manager during implementation of project.

Poor quality, and overrun costs due to poor scope definition in planning phase are other significant challenges faced by project manager in this phase.

Initiating phase

In this phase the challenges such as no support initially by stakeholder, lack of consensus regarding outcomes of project, unavailability of resources and lack of a clear business strategy make project manager task more challenging.

Controlling

There are certain issues such as lack of change control initiatives, issues in implementing control procedures, inability of project manager and staff to measure progress, posing challenges for a project. These challenges need to be addressed by project manager with proper skills and as these challenges are controllable by skill improvement, this phase is ranked four in risk category.

Possible benefits by gathering and reviewing information

Information availability assists to complete a project within time and budget. Information availability ensures that the project manager can deploy proactive strategies to ward off project challenges. Availability of information ensures that scope management of project is done correctly. Correct and timely information and its review assist project manager and team to understand roles and responsibilities clearly. Review of project charter and status report assists the project manager to make justified scope of project and budget. Information availability and review can help project manager to manage costs, and time to complete a project. Therefore, in the future projects, a project manager having access to relevant information can mitigate several challenges of projects.

Project completed

The project is solar project that installed PV system in homes. A local area was chosen to install the project. Solar technicians installing the solar projects inside homes were part of the team. There were 10 people working in the team. The outcome of the project is a moderate success because initial upfront cost and lack of staffs to review the installed system in homes resulted in less solar system installation in homes during given time. The project duration was six months and target was to install 100 solar systems but the project installed 75 solar systems.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
(Use the case of “Global Treps”) You have been selected as the project manager for the...
(Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Please read through the article below and answer the question at the end of the article....
Please read through the article below and answer the question at the end of the article. High-Performing Teams Need Psychological Safety. Here’s How to Create It “There’s no team without trust,” says Paul Santagata, Head of Industry at Google. He knows the results of the tech giant’s massive two-year study on team performance, which revealed that the highest-performing teams have one thing in common: psychological safety, the belief that you won’t be punished when you make a mistake. Studies show...
Using the model proposed by Lafley and Charan, analyze how Apigee was able to drive innovation....
Using the model proposed by Lafley and Charan, analyze how Apigee was able to drive innovation. case:    W17400 APIGEE: PEOPLE MANAGEMENT PRACTICES AND THE CHALLENGE OF GROWTH Ranjeet Nambudiri, S. Ramnarayan, and Catherine Xavier wrote this case solely to provide material for class discussion. The authors do not intend to illustrate either effective or ineffective handling of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality. This publication may not be...
Team 5 answer the questions What are 4 key things you learned about the topic from...
Team 5 answer the questions What are 4 key things you learned about the topic from reading their paper? How does the topic relate to you and your current or past job? Critique the paper in terms of the organization and quality. Incentive Systems             In this paper, we will focus primarily on financial rewards that companies use to attract, retain and motivate the brightest and most talented candidates in the labor market. By providing a reward system that...
2. SECURING THE WORKFORCE Diversity management in X-tech, a Japanese organisation This case is intended to...
2. SECURING THE WORKFORCE Diversity management in X-tech, a Japanese organisation This case is intended to be used as a basis for class discussion rather than as an illustration of the effective or ineffective handling of an administrative situation. The name of the company is disguised. INTRODUCTION In light of demographic concerns, in 2012, the Japanese government initiated an effort to change the work environment in order to secure the workforce of the future. Japan is world renowned for its...
Please read the article and answear about questions. Determining the Value of the Business After you...
Please read the article and answear about questions. Determining the Value of the Business After you have completed a thorough and exacting investigation, you need to analyze all the infor- mation you have gathered. This is the time to consult with your business, financial, and legal advis- ers to arrive at an estimate of the value of the business. Outside advisers are impartial and are more likely to see the bad things about the business than are you. You should...
QUESTION 1 1. Brianna is trying to increase her chances of being promoted to vice president...
QUESTION 1 1. Brianna is trying to increase her chances of being promoted to vice president by working to build good work relationships with other managers outside her own department. Brianna's behavior should be viewed as dysfunctional politics. functional politics. coercive power. functional influence. 2 points QUESTION 2 1. The Gingerbread Factory has a separate unit that makes their chocolate crunch cookies and another unit that is completely responsible for all operations in producing their ginger snap cookies. The Gingerbread...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...