Question

Lulwa WLL produces a component that is subsequently used in the aluminum industry. The component consists...

Lulwa WLL produces a component that is subsequently used in the aluminum industry. The component consists of three parts (A, B, and C) that are purchased from outside and cost 0.40BD, 0.35BD, and 0.15BD per piece, respectively.

· Parts A and B are assembled first on assembly line 1, which produces 140 components per hour.

· Part C undergoes a drilling operation before being finally assembled with the output from assembly line 1.

· There are in total six drilling machines, but at present only three of them are operational.

· Each mixing drilling drills part C at a rate of 50 parts per hour.

· In the final assembly, the output from assembly line 1 is assembled with the drilled part C. The final assembly line produces at a rate of 160 components per hour.

· At present, components are produced eight hours a day and five days a week.

· Management believes that is need arises, it can add a second shift of eight hours for the assembly lines.

Other Costs:

· The cost of assembly labor is 0.30 BD per part for each assembly line;

· The cost of mixing labor is 0.15 BD per part.

· For mixing, the cost of electricity is 1 fills per part.

· The total overhead cost has been calculated as 1,200 BD per week.

· The depreciation cost for equipment has been calculated as 30 BD per week.

a. Determine the process capacity (number of components produced per week) of the entire process.

b. Suppose a second shift of eight hours is run for assembly line 1 and the same is done for the final assembly line. In addition, four of the six drilling machines are made operational. The drilling machines, however, operate for just eight hours a day. What is the new process capacity (number of components produced per week)?

c. Management decides to run a second shift of eight hours for assembly line 1 plus a second shift of only four hours for the final assembly line. Five of the six drilling machines operate for eight hours a day. What is the new capacity?

d. Determine the cost per unit output for questions b and c.

Homework Answers

Answer #1

Answer a:

No. of hours per day = 8; No. of days per week = 5

No. of hours per week = 8 x 5 = 40

Based on the information given in the question, we may represent the given process as mentioned in the below chart:

No. of components Processed in an Hour at assembly line 1 (Parts A and B) = 140 Units / Hr

No. of Components Processed in an Hour at Drilling Machine (Part C) = 50 x 3 drills = 150 Units / Hr

No. of Components Processed in the Final Assembly Line = 160 Units / Hr

So, the Bottleneck Station = Workstation processing the least no. of units/hr = Assembly Line

Therefore, Overall Process Capacity = Capacity of Bottleneck Station = 140 Units / Hr

Hence, Process Capacity Per Week =  140 x 40 = 5600 Units

Answer b:

We can find the new capacity at each of the workstations as mentioned in the below table:

Where Capacity / Week = Product of Col 2 to Col 7

So, the new overall process capacity = Capaacity at bottleneck (i.e., workstation havin the least no. processed of units) statiion = 8000 Components / Week

Answer c:

We will find the new capacity for each of the workstations as mentioned in the below table:

Where,

Col 8 = Total Hrs / Day = (Col 4 x Col 5) + (Col 6 x Col 7)

Col 10 = Capacity / Week = Col 2 x Col 3 x Col 8 x Col 9

So, the new overall process capacity = Capaacity at bottleneck (i.e., workstation havin the least no. processed of units) statiion = 9600 Components / Week

Answer d:

We will Calculate the cost per unit output for answers b and c as mentioned in the below table:

____________________________________________________________________________

Please Please up vote this answer. I worked a lot to write a perfect answer. Your up vote is so valuable to me. Please. Thank you so much.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A small company produces three computer components. Component A requires 2 hours of fabrication and one...
A small company produces three computer components. Component A requires 2 hours of fabrication and one hour of assembly, Component B requires 3 hours of fabrication and one hour of assembly, and Component C requires 2 hours of fabrication and 2 hours of assembly. The company has 1000 hours of fabrication and 800 hours of assembly available every week. Profit of Components A, B, and C are $7, $8, and $10 respectively. Using the simplex method, calculate how many components...
Your company produces electronic connectors, which consist of a metal strip with multiple prongs assembled into...
Your company produces electronic connectors, which consist of a metal strip with multiple prongs assembled into a plastic housing. The manufacturing process is divided into four separate departments: 1) Injection molding, where the small plastic housings are produced; 2) Stamping, where the steel strips are punched out of thin coils of steel; 3) Plating, where the steel strips, after being stamped, are plated with tin or gold; and 4) Assembly, where the plated strips are inserted into the plastic housing....
e Goode Perk Company produces several models of coffee makers. There is little difference in the...
e Goode Perk Company produces several models of coffee makers. There is little difference in the production time required for the various model coffee machines. The plant is designed to produce 160 coffee machines per eight-hour shift, and there are two shifts per working day. However, the plant does not operate for the full eight hours: the employees take two 12-minute breaks in each shift, one in the first four hours and one in the second four hours; two hours...
You are the manager of a manufacturing plant that produces disk drives for personal computers. One...
You are the manager of a manufacturing plant that produces disk drives for personal computers. One of your machines produces a part that is used in the final assembly. The width of this part is important to the disk drive’s operation. The width needs to be 4mm 005mm. If not, the disk drive will not work properly and will need to be repaired at a cost of $10.45. The machine producing the part can be set to produce the part...
Laval produces lamps and home lighting fixtures. Its most popular product is a brushed aluminum desk...
Laval produces lamps and home lighting fixtures. Its most popular product is a brushed aluminum desk lamp. This lamp is made from components shaped in the fabricating department and assembled in the assembly department. Information related to the 36,000 desk lamps produced annually follows. Direct materials $ 260,000 Direct labor Fabricating department (6,500 DLH × $26 per DLH) $ 169,000 Assembly department (15,600 DLH × $25 per DLH) $ 390,000 Machine hours Fabricating department 15,200 MH Assembly department 20,800 MH...
Laval produces lamps and home lighting fixtures. Its most popular product is a brushed aluminum desk...
Laval produces lamps and home lighting fixtures. Its most popular product is a brushed aluminum desk lamp. This lamp is made from components shaped in the fabricating department and assembled in the assembly department. Information related to the 22,000 desk lamps produced annually follows. Direct materials $ 270,000 Direct labor Fabricating department (6,500 DLH × $20 per DLH) $ 130,000 Assembly department (16,200 DLH × $28 per DLH) $ 453,600 Machine hours Fabricating department 14,200 MH Assembly department 21,050 MH...
The Big Manufacturing Company produces a particular product in an assembly line operation. One of the...
The Big Manufacturing Company produces a particular product in an assembly line operation. One of the machines on the line is a drill press that has a single assembly line feeding into it. A partially completed unit arrives at the press to be worked on every 7.5 minutes, on average. The machine operator can process an average of 10 parts per hour. Using the Poisson arrivals and exponential service time model, a-what is the average number of parts waiting to...
A manufacturer produces four parts: XJ201, XM897, TR29, and BR788. The net profit per unit are...
A manufacturer produces four parts: XJ201, XM897, TR29, and BR788. The net profit per unit are $9, $12, $15, and $11 respectively. The products are each processed in the wiring and drilling departments then go to assembly. The final step in the plant is a final inspection. The time in minutes spent at each of the four departments is listed in the following table:                         Wiring             Drilling            Assembly        Inspection XJ201             30                    180                  120                  30 XM897           90                    60                    240                  60 TR29              ...
Suppose a manufacturer produces three models of air-conditioner unit: deluxe, standard, and economy. The deluxe model...
Suppose a manufacturer produces three models of air-conditioner unit: deluxe, standard, and economy. The deluxe model can be assembled in four hours, the standard in three hour, and the economy in two hours. The assembly line has 800 staff hours available each week. (a) If the demands for deluxe, standard, and economy are in the ratio 2:3:4, calculate (i) the total time needed to assemble (2+3+4) 9 units, and (ii) the total number of units produced per week. (b) If...
Complete in Excel: A manufacturer produces four parts: XJ201, XM897, TR29, and BR788. The net profit...
Complete in Excel: A manufacturer produces four parts: XJ201, XM897, TR29, and BR788. The net profit per unit are $9, $12, $15, and $11 respectively. The products are each processed in the wiring and drilling departments then go to assembly. The final step in the plant is a final inspection. The time in minutes spent at each of the four departments is listed in the following table:                         Wiring             Drilling            Assembly        Inspection XJ201             30                    180                  120                  30 XM897           90                    60                   ...