In the following situation, should one machine be purchased and operated 24 hours a day, or should three machines be bought and operated 8 hours?
We will calculate the total cost in 10 years.
Option 1. 24 hour operation with one machine
Initial Cost : $120000
Per day labour cost =12+14+16.5 = $42.5
Adding the inefficiency factor the per day labour cost = $42.5/.95=44.73
Let us assume a total of 3650 days machine will operate in 10 years.
Then total labour cost = 3650*44.73=$163264
Total Cost = 120000+163264= 283264
Option 2. 8 hour each machine with three machine
Initial machine cost = 360000
Labour cost = $12 per day * 3 labour = $36
Labour cost for 10 year=3650*36=131400
Total Cost = 360000+131400=$ 491400
Therefore, it is far cheaper to have one machine and operate it for 24 hours even if it is 95% efficient as the labor cost is low and the machine cost is very high. Therefore one machine option is more suitable.