Question

An assembly component A uses 2 units of another component B. Component A has the planned...

An assembly component A uses 2 units of another component B. Component A has the planned order release of 36 and 62 units at week 3 and week 4 respectively. The company expects an on hand inventory of 96 units of B at the end of week 2 and a scheduled receipt of 12 units of B from an outside supplier at the start of week 3. What will be the net requirement of component B at week 4?

Homework Answers

Answer #1

Since each component of A requires 2 units of B, taking into account planned order release of component A , we can say :

Planned order release for component B at week 3 = 36 x 2 = 72

Planned order release for component B at week 4 = 62 x 2 = 124

Expected inventory of B at week 3

= 96 ( on hand inventory ) + 12 ( scheduled receipts)

= 108

108 units fully cater to 72 units requirement at week 3 and left with = 108 – 72 = 36 units for week 4

However gross requirement for week 4 = 124

Net requirement for week 4 for component B = 124 – 36 = 88

NET REQUIREMENT OF COMPONENT B AT WEEK 4 = 88

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
TASK:   Complete the MRP record for component C as it would appear at the beginning of...
TASK:   Complete the MRP record for component C as it would appear at the beginning of week 2. MRP record for component C as it would appear at the beginning of week 1. Week 1 2 3 4 5 6 Gross Requirements 15 30 25 25 10 20 Scheduled Receipts 40 0 0 0 0 0 Projected Available Balance 50 20 35 10 0 20 Planned Order Receipts 0 0 40 0 0 40 Planned Order Releases 40 0 0...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 2 C's and 3 F’s. F needs 3 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 400 0 300 On hand inventory for all items is 200 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 2 C's and 3 F’s. F needs 3 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 400 0 300 On hand inventory for all items is 200 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 4 C's, 2 F’s and 5 G’s. F needs 4 C’s and G needs 2 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 0 100 900 On hand inventory for all items is 300 and lead time for A is 1 period, and LT for all other...
Problem 12:9 Assume that you are the manager of a shop that assembles power tools. You...
Problem 12:9 Assume that you are the manager of a shop that assembles power tools. You have just received an order for 57 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30   ...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 4 C's, 2 F’s and 5 G’s. F needs 4 C’s and G needs 2 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 0 100 900 On hand inventory for all items is 300 and lead time for A is 1 period, and LT for all other...
Problem 5 Eighty units of end item E are needed at the beginning of week 6....
Problem 5 Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case) of J have been ordered and one case is scheduled to arrive in week 3, one in week 4, and one in week 5. Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 units of B and 20 units of J now on hand. Lead times...
The demand for subassembly S is 120 units in week 7. Each unit of S requires2...
The demand for subassembly S is 120 units in week 7. Each unit of S requires2 units of T and 1 unit of U. Each unit of T requires 1 unit of​ V,1unit of​ W, and1 unit of X.​ Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make​ S,1week to make​ T, 2 weeks to make​ U, 2 weeks to make​ V, 3...
Rapid Industries has multiple divisions. One division, Iron Products, makes a component that another division, Austin,...
Rapid Industries has multiple divisions. One division, Iron Products, makes a component that another division, Austin, is currently purchasing on the open market. Iron Products currently has a capacity to produce 515,000 components at a variable cost of $7.00 and a full cost of $9.00. Iron Products has outside sales of 477,000 components at a price of $13.00 per unit. Austin currently purchases 50,000 units from an outside supplier at a price of $11.00 per unit. Assume that Austin desires...
Product Y is made from one component P, three components Q, and one 2 components R.  P...
Product Y is made from one component P, three components Q, and one 2 components R.  P is made from two parts S, Q is made from one S, and R is made from two part S and three part T.  Other data includes: Part                 Lead time             Lot size                   On hand                 Scheduled receipts         Safety Stock Y                         1                                 lot-for-lot               30                                              none                                          5 P                        2                                   40                              15                                              none                                          none Q                        2                                 100                               8                                               none                                          8 R                        3                                 120                             30                                              none                                          none S                         2                                 500                             20                                              500, week 1                          20 T                         2                                 600                           370                                             none                                          50 a.    Draw the BOM for product Y. b. Complete the MRP explosion for product Y.  Identify any problems, and discuss possible solutions Master Production Schedule Finished...