Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits.
Times Taken for Different Activities (hours) |
||
Suit |
Cut and Sew |
Deliver |
1 |
4 |
2 |
2 |
7 |
7 |
3 |
6 |
5 |
Assume that orders for suits have been listed in the above table in the order in which they were received.
a. Using the FCFS rule for scheduling, the sequence is: 1-2-3
b. For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) = ____hours (enter your response as a whole number).
c. Using Johnson's rule for 2-machine scheduling, the sequence is 1-3-2 OR 3-1-2 OR 2-3-1 OR 3-2-1 OR 1-2-3 OR 2-1-3?
d) For the schedule developed using the Johnson's rule, the total length of time taken to complete the three suits (including delivery) = _________hours(enter your response as a wholenumber)
e) Of the two developed schedules, Johnson's OR the FCFS rule gets the schedule finished sooner?
.