Question

Matthew and Mark work for AMG, and want to do some aggregate planning using "Level Production...

Matthew and Mark work for AMG, and want to do some aggregate planning using "Level Production without Backorders" for the manufacturing of brake calipers for Mercedes Benz S63 sedans. They figure the front brake calipers take 9 hours to forge and assemble while the rear calipers take 7 hours to forge and assemble. They pay their people $24.00 per hour and it costs them $900.00 to hire and $1,300 to fire each employee. They currently employ 6 people and have 129 front calipers in inventory and 113 rear calipers in inventory. Inventory carrying costs are $7.00 per labor hour. Assume 40 hours per week and 4 weeks per month. Please disregard rounding errors and select the closest answer.

The following is the 6 month demand forecast in units:

Month

1

2

3

4

5

6

Front Calipers

200

750

330

550

240

180

Rear Calipers

230

730

340

500

250

220

You will need to first figure what the level production amount will be using the following information over 6 periods:

                                                  1                2                  3                  4                 5                    6       

Cumulative Demand

Beginning Inventory (Constant using the inventory levels given)

Total Cumulative Production

Monthly Production

Use the following model to construct your analysis:

                               1              2                  3                 4               5                  6

Beginning Inventory

Demand

Production

Ending Inventory

Hire Costs

Fire Costs

Wage Costs

Inventory Costs

Total Costs

1. What is the cumulative demand for all periods in labor hours?

A. 28,970

B. 36,140

C. 27,080

D. 29,350

2. What is the level production amount in labor hours?

A. 5,089

B. 4,667

C. 5,511

D. 6,780

3. How many employees will they need to hire (or fire)?

A. Hire 37

B. Hire 32

C. Hire 26

D. Fire 2

4. What is the hiring (or firing) cost in Period 1?

A. $21,600

B. $33,300

C. $23,400

D. $26,100

5. What is the total cost for implementing this plan?

A. $917,672

B. $760,599

C. $1,125,689

D. $777,862

Homework Answers

Answer #1

Solving this LP, we will get the following solution -

Month Forecast Workers Hire Fire Ending Inventory Production Hours Hours Prod - (E.I - B.I) Inventory
Front Rear Front Rear Front Rear Consumed Available Front Rear labor hrs.
3 129 113
1 200 230 32 28.81 0 507 0 578 117 5089 5089 200 230 4053
2 750 730 32 0 0 28 0 271 730 5089 5089 750 730 222
3 330 340 32 0 0 164 0 466 340 5089 5089 330 340 1311
4 550 500 32 0 0 0 0 386 500 5089 5089 550 500 0
5 240 250 32 0 0 271 0 511 250 5089 5089 240 250 2169
6 180 220 32 0 0 617 0 526 220 5089 5089 180 220 4938
Cost Estimates
Month Prod Hire Fire Inventory Total
1 111958 25926 0 28371 166255
2 111958 0 0 1554 113512
3 111958 0 0 9177 121135
4 111958 0 0 0 111958
5 111958 0 0 15183 127141
6 111958 0 0 34566 146524
Totals 671748 25926 0 88851 786525

Note that hiring 28.81 labor is impossible. So, keeping all other things same, we change this number to 29 and get the following result which we consider final result -

Month Forecast Workers Hire Fire Ending Inventory Production Hours Hours Prod - (E.I - B.I) Inventory
Front Rear Front Rear Front Rear Consumed Available Front Rear labor hrs.
3 129 113
1 200 230 32 29 0 507 0 578 117 5089 5120 200 230 4053
2 750 730 32 0 0 28 0 271 730 5089 5120 750 730 222
3 330 340 32 0 0 164 0 466 340 5089 5120 330 340 1311
4 550 500 32 0 0 0 0 386 500 5089 5120 550 500 0
5 240 250 32 0 0 271 0 511 250 5089 5120 240 250 2169
6 180 220 32 0 0 617 0 526 220 5089 5120 180 220 4938
Cost Estimates
Month Prod Hire Fire Inventory Total
1 111958 26100 0 28371 166429
2 111958 0 0 1554 113512
3 111958 0 0 9177 121135
4 111958 0 0 0 111958
5 111958 0 0 15183 127141
6 111958 0 0 34566 146524
Totals 671748 26100 0 88851 786699

Answers -

1. 27,080
2. 5,089
3. Hire 29
4. $26,100
5. $786,699

----------------------------------------

Part 1: Cumulative demand for labor hours

Month 1 2 3 4 5 6
Front Calipers 200 750 330 550 240 180
Rear Calipers 230 730 340 500 250 220
Labor hours 2520 8920 4000 6400 2920 2320
Cumulative 2520 11440 15440 21840 24760 27080

O I J K L Production Hours Hours F ront Rear Consumed Available MN Prod - (E.I-B.1) Front Rear Inventory labor hrs. M EF G H 1 Month Forecast Workers Hire Fire Ending Inventory Front Rear Front Rear 129 113 200 230 =D3+E4-F4 29 506.625 O 750 730 =D4+E5-F5 27.750 330 340 =D5+E6-F6 163.8750 550 500 =D6+E7-F7 250 =D7+E8-F8 271.125 JO 180 220 =D8+E9-F9 617.250 Cost Estimates 11 Month Prod Hire Fire Inventory Total 12 1 =K4*22 =E49900 =F4*1300 =7*04 =SUM(B12:E12) 13 2 =K5*22 =E5*900 =F5*1300 =7*05 =SUM(B13:E13) 14 3 =K6*22 =E6*900 =F6*1300 =7*06 =SUM(B14:E14) =K7*22 =E7*900 =F7*1300 =7*07 =SUM(B15:E15) 16 5 =K8 22 =E8.900 =F8*1300 =7*08 =SUM(B16:E16) =K9*22 =E9 900 =F9*1300 =7*09 =SUM(B17:E17) 18 Totals =SUM(B12:B17) =SUM(C12:017) =SUM(D12:017) -SUM(E12:E17) =SUM(F12:F17) 577.625 271.125 466.125 386.125 511.125 526.125 117 730 340 500 250 220 =8*14+4* J4 =160*D4 =14-(G4-G3) =14-(H4-H3) =G4*8+H4*4 =8*15+4*5 =160*D5 =15-(G5-G4) =)5-(H5-H4) =G5*8+H5*4 =8*16+4*6 =160*D6 =16-(G6-G5) =J6-(H6-H5) =G6*8+H6*4 =8*17+47 =160*D7 =17-(G7-G6) =J7-(H7-H6) =G7*8+H7*4 =8*18+4*J8 =160*D8 =18-(G8-G7) =38-(H8-H7) =G8*8+H8*4 =8*19+4*19 =160*D9 =19-(G9-G8) = 39-(H9-H8) =G9*8+H9*4 240 15 4

Set Objective: SF518 To: O Max Min O Value Of: By Changing Variable Cells: SE$4:$J$9 Subject to the Constraints: SE$5:SF59 = 0 SK$4:$K$9 = $L$4:$L$9 SM$4:SNS9 = $B$4:$C$9 Add Change Delete Reset All Load/Save Make Unconstrained variables Non-Negative Select a Solving Method: Simplex LP Options Solving Method Select the GRG Nonlinear engine for Solver Problems that are smooth nonlinear. Select the LP Simplex engine for linear Solver Problems, and select the Evolutionary engine for Solver problems that are non-smooth.

2 6 A B C D E 1 Month 3 5 2 Front Calipers 200 750 330 550 240 180 3 Rear Calipers 230 730 340 500 250 220 4 Labor hours =B2*8+B3*4 =C2*8+C3*4 =D2*8+D3*4 =E2*8+E3*4 =F2*8+F3*4 =G2*8+G3*4 5 Cumulative =SUM($B$4:B4) =SUM($B$4:04) =SUM($B$4:04) =SUM($B$4:14) =SUM($B$4:F4) =SUM($B$4:04)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
In aggregate production planning, a demand-chasing production plan a. Maximize both inventory-related costs and labor-related costs...
In aggregate production planning, a demand-chasing production plan a. Maximize both inventory-related costs and labor-related costs b. Minimize Inventory-related costs and maximize labor-related costs c. Minimize both inventory-related costs and labor-related costs d. Not enough information given to answer this question
The following information is available pertaining to the Production Division of Clarkson Enterprises: Assembly Dept.      ...
The following information is available pertaining to the Production Division of Clarkson Enterprises: Assembly Dept.       Finishing Dept.        Total Overhead costs                 $10,000        $30,000               $40,000 Direct labor hours 8,000           2,000                    10,000 Machine hours                 3,000           5,000                      8,000 Production information pertaining to Job 4X5: Assembly Dept.       Finishing Dept.        Total Prime costs           $2,380                    $-0-                        $2,380 Direct labor hours    280                         -0-                          280 Machine...
Question 4: Aggregate Planning Plan production for a four month period: June through to September. For...
Question 4: Aggregate Planning Plan production for a four month period: June through to September. For June and July you should produce to exact demand forecast. For August and September you should use overtime and inventory with a stable workforce. Stable means the number of workers needed for July will be held constant through September. However the Ministry of Labour regulations put a maximum of 5000 hours of overtime labour per month in August and September (Zero overtime in June...
Aggregate Planning A key hospital supplier, IVs Plus (IVP) located in Salina, KS sells IV tubing...
Aggregate Planning A key hospital supplier, IVs Plus (IVP) located in Salina, KS sells IV tubing and stands to hospitals and clinics. Sales have picked up ever since they introduced their newest “Squeaky Clean” IV stand, which eliminates all oils and germs left behind by users. Though IVP sells these stands all year long, they sell the most during the summer months, when end-of-fiscal year purchases are at a peak. The demand over the next 12 months is shown in...
Consider the quarterly demand of 3500, 2600, 5500, 4400, for quarters 1,2,3,4, respectively, with a beginning...
Consider the quarterly demand of 3500, 2600, 5500, 4400, for quarters 1,2,3,4, respectively, with a beginning annual inventory of 500 and an ending annual inventory of 500. Let the production standard be 250 items/quarter. Let the carrying cost be $5/item/quarter. Question 6. For the aggregate planning strategies listed, what are the correct quarterly hire and fire FTES for the quarters listed? Select One Answer Aggregate Planning Strategy Quarter Quarterly Hire FTEs Quarterly Fire FTEs A Level Capacity 1 0 3.6...
Trexoid Inc. makes a popular video game console. Demand varies each month, with highest demand coming...
Trexoid Inc. makes a popular video game console. Demand varies each month, with highest demand coming in the last quarter of the year. Regular production costs are $250 per unit and inventory carrying cost is $3 per unit per quarter. Overtime production cost is $280 per unit. Assume that the 20 current Trexoid employees can produce a total of 30,000 units per quarter in regular production and can work enough overtime hours to produce the amount required if a chase...
1. Teller Co. is planning to sell 900 boxes of ceramic tile, with production estimated at...
1. Teller Co. is planning to sell 900 boxes of ceramic tile, with production estimated at 870 boxes during May. Each box of tile requires 44 pounds of clay mix and a quarter hour of direct labor. Clay mix costs $0.40 per pound and employees of the company are paid $12.00 per hour. Manufacturing overhead is applied at a rate of 110% of direct labor costs. Teller has 3,900 pounds of clay mix in beginning inventory and wants to have...
The? S&OP team at Kansas? Furniture, has received estimates of demand requirements as shown in the...
The? S&OP team at Kansas? Furniture, has received estimates of demand requirements as shown in the table. Assuming? one-time stockout costs for lost sales of ?$125 per? unit, inventory carrying costs of ?$30 per unit per? month, and zero beginning and ending? inventory, evaluate these two plans on an incremental cost? basis: Plan? A: Produce at a steady rate? (equal to minimum? requirements) of 1,000 units per month and subcontract additional units at a ?$65 per unit premium cost. Subcontracting...
The production report for Glenway Company for February contained the following information: Work in process, beginning...
The production report for Glenway Company for February contained the following information: Work in process, beginning of the month - 3,500 units; 1 / 5 completed Units completed and transferred to finished goods - 25,000 Work in process, end of month - 4,000 units; 1 / 4 completed Production costs for the month were: materials - $25,325; labor - $20,175; overhead - $38,950. Costs in beginning work in process were $5,250. What is the cost per equivalent unit? a. $3.45...
Bay Company had actual production of 220 units in the month of April. Budgeted standard fixed...
Bay Company had actual production of 220 units in the month of April. Budgeted standard fixed overhead costs were $20,000, based on normal capacity of 800 direct labor hours per month. The time standard was 4 direct labor hours per unit. The fixed overhead volume variance for April was a. $3,600 F b. $3,600 U c. $2,000 F d. $2,000 U