AE Manufacturing has 60 machine hours every day. AE Manufacturing two products, A and B. When changing over from producing product B to A, there is no change over time. When changing over from producing product A to B, it takes 8 machine hours. If the previous day ended with producing product B, what is the effective capacity when AE Manufacturing has the following schedule: product A, product B, product A.
56 machine hours per day |
||
60 machine hours per day |
||
44 machine hours per day |
||
52 machine hours per day |
Given values:
Design capacity = 60 machine hours per day
Time taken from product B to A = 0 machine hours
Time taken from product A to B = 8 machine hours
Production schedule = A — B — A
Solution:
Previous day ended with Product B. Since, there is 0 changing over time from B to A, the new day will immediately begin with producing product A.
Beginning = Product A, changeover time = 0
Product A to B, changeover time = 8 machine hours
Product B to A, changeover time = 0 machine hours
Effective capacity = Design capacity — Total Change over time
Effective capacity = 60 — (0 + 8 + 0) = 52
Effective capacity = 52 machine hours per day