Question

What are the Activity Duration Estimates, Gantt Chart, and Activity Network Diagram used for project schedule?

What are the Activity Duration Estimates, Gantt Chart, and Activity Network Diagram used for project schedule?

Homework Answers

Answer #1

Activity duration estimates is the process of estimating the number of work period needed to complete individual activities with estimated resources. it is used in the project schedule is taht it provide the amount of time each activity will take to complete , it help to develop the schedule process.

Gantt chart is a graphical representation of a project schedule. gantt chart is used during the project schedule is that it shows the start and finish date of several element of a project that include resource, milestone, task and depedencies.

The activity network digram used in the project schedule , as it is tool used in project management, it is used to identify the project critical path. that is the expected completion time of the project.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1.Make a Gantt Chart for a Resource Scheduling Diagram that illustrates a possible issue with limited...
1.Make a Gantt Chart for a Resource Scheduling Diagram that illustrates a possible issue with limited resources that are not available? 2. Make up an example “what if”- some of the project team get the flu at the same time, for instance? 3. Your diagram should illustrate how much of the resource is needed over a short period of time, that there is not enough of the resource, and possible options to keep the project as close to schedule or...
What is a GANTT chart?
What is a GANTT chart?
CPM a. is a network technique that allows three time estimates for each activity in a...
CPM a. is a network technique that allows three time estimates for each activity in a project. b. assumes we do not know ahead of time what activities must be completed. c. assumes that activity time estimates follow the normal probability distribution. d. is a deterministic network technique that allows for project crashing.
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site Selection and Preparation B D Drilling, Engineering and other Works B, C E Installation of other Equipment, Testing, and Analysis D F Project Commission and Handing over to the community E G Demonstrate safety usage and practices E, F H Preclosure safety analysis F, G 1. create an activity precedence diagram showing the network logic for each project activity you have identified; 2.    prepare...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
The critical path for the network activities shown below is ________ with duration ________. Activity Duration...
The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 --- B 2 A C 7 -- D 4 A E 5 B,C,D
What is the crashing techniques used for? a. Activity sequencing b. Cost reduction c. Network diagramming...
What is the crashing techniques used for? a. Activity sequencing b. Cost reduction c. Network diagramming d. Duration compression
2 All _______ activities have been _______ when a new activity is started in a project....
2 All _______ activities have been _______ when a new activity is started in a project. Multiple Choice successor, started successor, completed predecessor, started predecessor, completed 17 A ________ organization is one with ________ of reporting relationships. Multiple Choice dedicated, multiple lines dedicated, a single line matrix, multiple lines matrix, a single line 20 Which of the following is NOT a project management tool for project planning? Multiple Choice Dependency matrix Activity network Gantt chart Flow chart COURSE : OPERATIONS...
Use the table below to answer the questions Activity Optimistic duration Pessimistic duration Most Likely duration...
Use the table below to answer the questions Activity Optimistic duration Pessimistic duration Most Likely duration Weighted duration Immediate Predecessor P 15 27 21 - Q 18 36 24 P R 26 40 24 P S 21 39 27 Q T 27 33 24 Q,R U 16 32 24 S,T V 16 30 26 U 1. Calculate the actual duration of each activity (fill-in the table) 2. Draw an AOA network diagram for the activities (in the space below): 3....
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ___ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)