Question

The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...

The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241.

(Job) (Date Job Received) (Due Date Duration (days))

BR-02 225 270 25

CX-01 230 320 35

DE-06 235 360 40

RG-05 231 310 30

SY-11 228 300 15

Using the LPT? (longest processing? time) decision rule for sequencing the? jobs, the order is? (to resolve a? tie, use the order in which the jobs were? received):

The average tardiness? (job lateness) for the sequence developed using the LPT rule? =

The percentage utilization for the sequence developed using the LPT rule? =

The average completion time for the sequence developed using the LPT rule? =

The average number of jobs in the system for the sequence developed using the LPT rule? =

Critical Ratio? (CR) for each job is given by the? relationship:= (Due Date-Date Today) / (Processing Time). what is CR for jobs a-e

.

Using the Critical Ratio? (CR) scheduling rule for sequencing the? jobs, the order? is:

.

Homework Answers

Answer #1

Scheduling as per LPT rule -

Job Date
received
Process
time
Due date Order Flow time End time Lateness
DE-06 235 40 360 1 40 280 0
CX-01 230 35 320 2 75 315 0
RG-05 231 30 310 3 105 345 35
BR-02 225 25 270 4 130 370 100
SY-11 228 15 300 5 145 385 85
TOTAL 145 495 1695 220
AVERAGE 99 339 44

Average tardiness = 44

Utilization = 145/495 = 29.29%

Average completion time = 339

Average jobs in the system = 495/145 = 3.41

Scheduling as per the Critical Ratio -

Job Date
received
Process
time
Due date Critical ratio Order
BR-02 225 25 270 1.16 1
CX-01 230 35 320 2.26 2
RG-05 231 30 310 2.30 3
DE-06 235 40 360 2.98 4
SY-11 228 15 300 3.93 5
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on...
Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2). The processing times are given in the table below. Job Machine 1 Machine 2 L 10 2 M 5 4 N 7 5 O 3 6 P 1 7 ** Please show excel steps so i can see if I did this right** thanks What is the optimal sequence? What is the total...
The owner/operator of the local franchise of Handyman, Inc. has 4 jobs to complete today, shown...
The owner/operator of the local franchise of Handyman, Inc. has 4 jobs to complete today, shown in the order in which they were received. Job Processing Time (hrs) Due (hrs from now) W 4 4 X 3 5 Y 2 2 Z 1 1 If he or she uses the earliest due date first priority rule to schedule these jobs, what will be the average tardiness?
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs in a schedule ABCDE is 1st,2nd,3rd,4th,5th, respectively.] Five jobs arrived to be processed with the processing times and due dates. Present Date= 300 Work Order A B C D E Processing Times (Days) 14 5 40 12 7 Due Date 167 163 195 191 161 . . . Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the...
Five jobs are ready for processing at time zero through a workstation. The details of the...
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 5 11 B 6 16 C 3 19 D 4 10 E 2 9 Using the earliest due date (EDD) rule, the average lateness for the five jobs is:
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job...
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job A, Process time =14 days, and due date November 26 Job B, Process time= 11 days, and due date = November 25 Job C, Process time =7 days, and due date= December 14 Job D, Process time=6 days, and due date= November 29 Job E, Process time= 2 days, and due date= November 20 Schedule the jobs according to SPT. What are the average...
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table....
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard’s schedule. Job Due Date Remaining Time (Days) A 212 6 B 209 3 C 214 10 D 210 8 In what sequence would the jobs be ranked according to the following decision rules: a) FCFS b) SPT c) LPT d) EDD e) Critical ratio Which is best and why? Which has the minimum lateness?
You have the following information on four jobs. Today is the beginning of day 1, so...
You have the following information on four jobs. Today is the beginning of day 1, so you can assume that the Time needed = work remaining and Due (days) = time remaining. Job Time Needed (days) Due (days) P 8 8 Q 10 23 R 3 17 S 6 30 T 4 29 U 7 24 1. If you order these jobs by Shortest Process Time rule, the order will be: 2. If you order these jobs by Earliest Due...
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at...
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to Johnson's rule, a. what is the job processing sequence? b. how much idle time does work center Beta have? Job Alpha Beta R 20 10 S 25 35 T 50 20 U 15 35 V 55 75
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT