Question

1. A company has two warehouses A and B, and three retail outlets 1, 2 and...

1. A company has two warehouses A and B, and three retail outlets 1, 2 and 3. The warehouse capacities, retail outlet demands, and per-unit shipping costs ($) are shown in the table below. Formulate a linear programming (LP) model of this transportation problem with the objective of minimizing total shipping cost.

                   Retail Outlets

Warehouses

   1  

    2

    3

Total Supply

     A   

$5

$8

$3

500

    B

$7

$4

$6

250

            Total Demand

300

400

250

   

2. A department head has four managers, and three projects (A, B, C) to be executed. The managers differ in efficiency, and the projects differ in their intrinsic complexity. The estimate of the times each manager would take to complete each project is given in the matrix below. Formulate a linear programming (LP) model for determining how the projects should be assigned, to a manager, so as to minimize the total project completion time. No manager should be assigned more than one project.

                   Manager

Project

1

2

3

4

A

8

14

12

11

B

6

9

10

8

C

7

10

9

11

Please input answers into a Word Document, if possible.

Homework Answers

Answer #1

Problem 1:

Let, xij = units shipped from warehouse ‘i’ to retail outlet j

Where, i = a, b for two warehouses

j = 1, 2, 3 for three retail outlets

Thus, there will be 2 x 3 = 6 decision variables in the LPP.

Objective Function:

Objective is to minimize the total shipping cost:

Let Cij = per unit-shipping cost time from warehouse i to outlet j

Min. Z = (Cij x Xij)

Min. z = $5xa1 + $8xa2 + $3xa3 + $7xb1 + $4xb2 + $6xb3

Subject To:

The constraint of problem are:

Warehouse cannot ship more than supply capacity

Demand of outlet has to be satisfied

Supply constraint of warehouses: Since the total supply capacity is less than total demand, all the capacity will be utilized.

Warehouse A: xa1 + xa2 + xa3 = 500

Warehouse B: xb1 + xb2 + xb3 = 250

Demand constraint of retail: Since demand is more than supply capacity, not all demand will be satisfied

Retail 1: xa1 + xb1 <= 300

Retail 2: xa2 + xb2 <= 400

Retail 1: xa3 + xb3 <= 250

Nonnegative Constraint: all Xij >= 0

Problem 2:

Let, xij = 1 if the manager ‘i’ is assigned to project j otherwise Xij = 0

Where, i = 1, 2,…4 for four managers

j = a, b, c for three projects

Thus, there will be 4 x 3 = 12 decision variables in the LPP.

Objective Function:

Objective is to minimize the total project completion time:

Let Cij = time required by manager i to complete project j

Min. Z = (Cij x Xij)

Min. z = 8x1a + 6x1b + 7x1c + 14x2a + 9x2b + 10x2c + 12x3a + 10x3b + 9x3c + 11x4a + 8x4b + 11x4c

Subject To:

The constraint of problem is to assign one manager to one project.

Assignment of Managers: Since the number of manager is more than number of projects, one of the manager will remained unassigned.

Manager 1: x1a + x1b + x1c <= 1

Manager 2: x2a + x2b + x2c <= 1

Manager 3: x3a + x3b + x3c <= 1

Manager 4: x4a + x4b + x4C <= 1

Assignment of Projects

Project A: x1a + x2a + x3a + x4a = 1

Project B: x1b + x2b + x3b + x4b = 1

Project C: x1c + x2c + x3c + x4c = 1

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company has two warehouses A and B, and three retail outlets 1, 2 and 3....
A company has two warehouses A and B, and three retail outlets 1, 2 and 3. The warehouse capacities, retail outlet demands, and per-unit shipping costs ($) are shown in the table below. Formulate a linear programming (LP) model of this transportation problem with the objective of minimizing total shipping cost.                    Retail Outlets Warehouses    1       2     3 Total Supply      A    $5 $8 $3 500     B $7 $4 $6 250             Total Demand 300 400...
Ryan Electronics has production facilities in Denver and Atlanta, warehouses in Kansas City and Louisville, and...
Ryan Electronics has production facilities in Denver and Atlanta, warehouses in Kansas City and Louisville, and retail outlets in Detroit, Miami, and Dallas. Each production facility can deliver to each warehouse and each warehouse can deliver to each retail outlet. The shipping costs per unit appear in the table below: From To Cost ($/unit) Denver Kansas City 4 Denver Louisville 3 Atlanta Kansas City 2 Atlanta Louisville 1 Kansas City Detroit 2 Kansas City Miami 3 Kansas City Dallas 4...
A company has three factories at A, B and C, which supply warehouses at D, E,...
A company has three factories at A, B and C, which supply warehouses at D, E, F and G respectively. Monthly product capacities of these factories are 250, 300 and 400 units respectively. The current warehouse requirements are 200, 275 and 300 units respectively. Unit transportation costs from factories to warehouses are given below. To D E F G A 11 13 17 14 B 16 18 14 10 C 21 24 13 10 Determine the optimum distribution to minimize...
1. Four workers are available to perform tasks 1-4. However, worker 1 can't do tasks 2,...
1. Four workers are available to perform tasks 1-4. However, worker 1 can't do tasks 2, 3, or 4. Also, worker 2 can't do tasks 3 or 4 and worker 3 can't do tasks 1, 3, or 4. Worker 4 can do any task. Each worker can do at most one task, and each task should be performed at most once. a) Draw the network for the maximum flow problem that can be used to determine whether all tasks can...
In a portfolio problem, the investor has up to $50,000 to invest in stocks 1, 2,...
In a portfolio problem, the investor has up to $50,000 to invest in stocks 1, 2, and 3, which have selling prices of $15/share, $47.25/share, and $110/share, respectively. The investor can purchase multiple shares of multiple stocks. The expected returns on investment of the three stocks are 6%, 8%, and 11%. The stockbroker suggests limiting the investments so that no more than $10,000 is invested in stock 2, and the total number of shares of stocks 2 and 3 does...
Company ABC is considering opening warehouses in four cities in Canada: Ottawa, Toronto, Calgary and Winnipeg....
Company ABC is considering opening warehouses in four cities in Canada: Ottawa, Toronto, Calgary and Winnipeg. Each warehouse can ship 100 units per day. The daily fixed cost of keeping each warehouse open is $400 for Ottawa, $500 for Toronto, $300 for Calgary and $350 for Winnipeg. Region 1 of the country requires 80 units per day, region 2 requires 70 units per day and region 3 requires 40 per day. The costs (including production and shipping costs) of sending...
Young and Associate, Inc. is an accounting firm that has three new clients. Project leaders will...
Young and Associate, Inc. is an accounting firm that has three new clients. Project leaders will be assigned to the three clients. Based on the different backgrounds and experiences of the leaders, the various leader-client assignments differ in terms of projected completion times. The possible assignments and the estimate completion times in days are as follows: Client Project Leaders 1 2 3 Johnson 12 15 30 Gilbert 15 22 35 Henderson 23 25 36 a. Develop a network representation of...
Muzi Corporation produces three products at two different plants. The cost of producing a unit at...
Muzi Corporation produces three products at two different plants. The cost of producing a unit at each plant is given in the following table. Product 1 Product 2 Product 3 Plant A R5 R6 R8 Plant B R8 R7 R10 Each plant has the capacity to produce a total of 10 000 units. Demand for at least 6 000 units of product 1, at least 8 000 units of product 2 and at least 5 000 units of product 3...
Consider a small Oil production firm with 5 competing oil production projects, A - E. The...
Consider a small Oil production firm with 5 competing oil production projects, A - E. The table below shows the estimated long-term profit (Net Present Value) for each project as well as the amount of investment capital required to start the project. You have been contacted to help select the best combination of projects to maximize the Net Present Value subject to the capital investment limit of $32 million. Production Project A B C D E Estimated Profit (millions) 25...
A company produces a certain product and has the capacity to produce 100 units per month...
A company produces a certain product and has the capacity to produce 100 units per month in regular time, and an additional 15 units per month in overtime. The production cost of the product varies by month due to changes in the material costs over time. The quantities of the product to be delivered over the next six months have already been set. The delivery requirements and production costs are given in the following table: Month 1 2 3 4...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT