Question

what are the basic step to design and use the work breakdown structured (WBS) Project management

what are the basic step to design and use the work breakdown structured (WBS)

Project management

Homework Answers

Answer #1

Answer-

The following seven steps explain the design and use of the Work Breakdown Structure.
Step 1: A list of the task breakdown in successively finer levels of detail is created using information from the action plan. This process is continued until all meaningful tasks or work packages have been identified and controlled.
Step 2: Data relevant to the Work Breakdown Structure is identified for each such work package. The personnel and organizations responsible for each task are listed. A linear responsibility chart will be helpful to show who is responsible for what. This chart will also show the critical interfaces between units that may require special managerial coordination. The Project Manager can keep track of who must approve what and who must report to whom using this list.
Step 3: All the work package information should be reviewed with the individuals or organizations who have responsibility for doing or supporting the work in order to verify the Work Breakdown Structure's accuracy. Next, the resource requirements, schedules, and subtask relationships can be aggregated to form the next higher level of the Work Breakdown Structure and continued on to each succeeding level of the hierarchy. At the uppermost level, there should be a summary of the project, its budget, and an estimate of the duration of each work element.
Step 4: For the purpose of pricing a proposal, or determining profit and loss, the total project budget should consist of four elements:
(i) Direct budgets from each task as just described
(ii) An indirect cost budget for the project which includes general and administrative overhead costs, marketing costs, potential penalty charges, and other expenses not attributable to particular tasks.
(iii) A project contingency reserve for unexpected emergencies
(iv) Any residual which includes the profit derived from the project and which may on occasion be intentionally negative.
Step 5: Schedule information and milestone (significant) events should be aggregated into a projected baseline schedule. The projected baseline schedule integrates the many different schedules relevant to the various parts of the project. It is comprehensive and may include contractual commitments, key interfaces and sequencing, milestone events, and progress reports. In addition, a time contingency reserve for unforeseeable delays might be included.
Step 6: As the project is carried out step by step, the Project Manager can continually examine actual resource use, work element, work package, task, and so on up to the full project level. By comparing actual against planned resource usage at a given time, the Project Manager can identify problems, harden the estimates of the final cost, and make sure that relevant corrective actions have been designed and are ready to be implemented if necessary. It is necessary to examine resource usage in relation to results achieved because, while the project may be over budget, the results may be farther along than expected. Similarly, the expenses may be exactly as planned or even lower, but actual progress may be much less than planned. Control charts showing these earned values can be developed.
Step 7: Finally, the project schedule may be subjected to the same comparisons as the project budget. Actual progress is compared to scheduled progress work by work element, package, task, and complete project, to identify problems and take corrective action. Additional resources may be brought to those tasks behind schedule to expedite them. These added funds may come out of the budget reserve or from other tasks that are ahead of schedule.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Approaches to Work Breakdown Structure (WBS) The PROJECT MANAGEMENT INSTITUTE (PMI) states that a WBS MUST...
Approaches to Work Breakdown Structure (WBS) The PROJECT MANAGEMENT INSTITUTE (PMI) states that a WBS MUST be product-oriented (planned outcomes, not planned actions). Why do they say this and what would this imply regarding the precedence of the WBS and the requirements engineering effort?
(Project Management) Q1) Create WBS (Work-breakdown structure) for Mobile Application Development Project. Application should be able...
(Project Management) Q1) Create WBS (Work-breakdown structure) for Mobile Application Development Project. Application should be able to allow passengers to have self-check-in at airports. Q2) Create Design Structure Matrix (DSM) using listed tasks created in Q1. Find the activities which are dependent upon each other.
Read the following case carefully. Develop a work breakdown structure (WBS) for the project. The WBS...
Read the following case carefully. Develop a work breakdown structure (WBS) for the project. The WBS should be organized by either “phase” or “project management process groups.” Break down the work to Level 3. The case description is simple. Thus, go beyond the case description and be creative to include additional detailed tasks.    ---------------[Case] ----------------------- Project for building a new, state-of-the-art multimedia classroom for your organization within the next five months and the budget is $200,000. The classroom should...
What is the difference between project task plan and WBS (work breakdown structure)? Please explain in...
What is the difference between project task plan and WBS (work breakdown structure)? Please explain in simple terms. Please do not copy words from other source.
Similarities and differences between task lists or task plan and WBS work breakdown strucure.
Similarities and differences between task lists or task plan and WBS work breakdown strucure.
I need to develop a work breakdown structure (WBS) for building a fence around the backyard
I need to develop a work breakdown structure (WBS) for building a fence around the backyard
I need to develop a work breakdown structure (WBS) for building a fence around the backyard
I need to develop a work breakdown structure (WBS) for building a fence around the backyard
I need to develop a work breakdown structure (WBS) for building a fence around the backyard
I need to develop a work breakdown structure (WBS) for building a fence around the backyard
What is the purpose of a WBS? What is the difference between a WBS, a SWBS,...
What is the purpose of a WBS? What is the difference between a WBS, a SWBS, and a CWBS? How do work packages relate to the WBS? Construct a WBS for a program of your choice. SYSTEM ENGINEERING MANAGEMENT FIFTH EDITION Benjamin S. Blanchard
You have been assigned as a project manager for a project. The work statement of this...
You have been assigned as a project manager for a project. The work statement of this project is design, develop and manage a website for e-Learning. Answer the following: A. Define the proper type of stakeholder that you need. B. Create your team and assign the tasks for each member. C. Create your timeline, assuming that the website SHOULD be online in 6 months. D. Explain: how are you going to creating a work breakdown structure (WBS) for the project.
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT