what are the basic step to design and use the work breakdown structured (WBS)
Project management
Answer-
The following seven steps explain the design and use of the Work
Breakdown Structure.
Step 1: A list of the task breakdown in successively finer levels
of detail is created using information from the action plan. This
process is continued until all meaningful tasks or work packages
have been identified and controlled.
Step 2: Data relevant to the Work Breakdown Structure is identified
for each such work package. The personnel and organizations
responsible for each task are listed. A linear responsibility chart
will be helpful to show who is responsible for what. This chart
will also show the critical interfaces between units that may
require special managerial coordination. The Project Manager can
keep track of who must approve what and who must report to whom
using this list.
Step 3: All the work package information should be reviewed with
the individuals or organizations who have responsibility for doing
or supporting the work in order to verify the Work Breakdown
Structure's accuracy. Next, the resource requirements, schedules,
and subtask relationships can be aggregated to form the next higher
level of the Work Breakdown Structure and continued on to each
succeeding level of the hierarchy. At the uppermost level, there
should be a summary of the project, its budget, and an estimate of
the duration of each work element.
Step 4: For the purpose of pricing a proposal, or determining
profit and loss, the total project budget should consist of four
elements:
(i) Direct budgets from each task as just described
(ii) An indirect cost budget for the project which includes general
and administrative overhead costs, marketing costs, potential
penalty charges, and other expenses not attributable to particular
tasks.
(iii) A project contingency reserve for unexpected
emergencies
(iv) Any residual which includes the profit derived from the
project and which may on occasion be intentionally negative.
Step 5: Schedule information and milestone (significant) events
should be aggregated into a projected baseline schedule. The
projected baseline schedule integrates the many different schedules
relevant to the various parts of the project. It is comprehensive
and may include contractual commitments, key interfaces and
sequencing, milestone events, and progress reports. In addition, a
time contingency reserve for unforeseeable delays might be
included.
Step 6: As the project is carried out step by step, the Project
Manager can continually examine actual resource use, work element,
work package, task, and so on up to the full project level. By
comparing actual against planned resource usage at a given time,
the Project Manager can identify problems, harden the estimates of
the final cost, and make sure that relevant corrective actions have
been designed and are ready to be implemented if necessary. It is
necessary to examine resource usage in relation to results achieved
because, while the project may be over budget, the results may be
farther along than expected. Similarly, the expenses may be exactly
as planned or even lower, but actual progress may be much less than
planned. Control charts showing these earned values can be
developed.
Step 7: Finally, the project schedule may be subjected to the same
comparisons as the project budget. Actual progress is compared to
scheduled progress work by work element, package, task, and
complete project, to identify problems and take corrective action.
Additional resources may be brought to those tasks behind schedule
to expedite them. These added funds may come out of the budget
reserve or from other tasks that are ahead of schedule.