Total prevention costs: 1,500
Total appraisal cost : 9,100
Total internal failure costs= 2,055
Total external failure costs= 3,345
Prepare a Pareto Chart and copy
Give two suggestions to improve quality for Kennedy Bank
Particular | Cost | Percentage of total cost |
Total prevention costs | 1500 | (1500/16000)*100 =9.4 |
Total appraisal cost | 9100 | (9100/16000)*100 = 56.88 |
Total internal failure costs | 2055 | (2055/16000)*100 =12.84 |
Total external failure costs | 3345 | (3345/16000)*100 =20.9 |
Total Cost | 16000 |
The chart is as below:-
Two suggestions are as below:-
Prevention costs are relatively low thus company should invest more in the defect and waste prevention
The company is incurring a lot of cost in appraisal, in fact, the focus should be more on finding effective ways of productivity improvement a