Question

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the...

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels.

Time

(weeks )

Immediate

Time

(weeks )

Immediate

Activity

a

m

b

Predecessor(s)

Activity

a

m

b

Predecessor(s)

A

44

88

1010

long dash—

G

22

33

44

C, E

B

22

99

2424

A

H

22

22

22

F

C

99

1212

1616

A

I

77

77

77

F

D

44

66

99

A

J

44

77

1212

D, G, H

E

11

22

44

B

K

11

11

44

I, J

F

55

88

2121

C, E

a) To find the expected activity time, the beta distribution weights the three time estimates as follows.

Expected Time equals StartFraction left parenthesis a plus 4 m plus b right parenthesis Over 6 EndFractionExpected Time=(a+4m+b)6

Calculate the expected (estimated) time for activity C.

Expected Time =

12.1712.17

weeks (Round your response to two decimal places.)

b) To compute the variance of activity completion time, use the following formula.

Variance equals left parenthesis StartFraction left parenthesis b minus a right parenthesis Over 6 EndFraction right parenthesis squaredVariance=(b?a)62

Calculate the variance for activity C.

Variance =

11

weeks (Round your response to two decimal places.)

Consider the AON network for the project.

font size increased by 1 Upper DD

font size increased by 1 Upper FF

font size increased by 1 Upper GG

font size increased by 1 Upper AA

font size increased by 1 Upper EE

font size increased by 1 Upper CC

font size increased by 1 Upper BB

font size increased by 1 Upper HH

font size increased by 1 Upper II

font size increased by 1 Upper KK

font size increased by 1 Upper JJ

x y graph

c) The length of the path

Upper A minus Upper B minus Upper E minus Upper F minus Upper H minus Upper J minus Upper KA ? B ? E ? F ? H ? J ? K

is

40.6740.67

weeks. (Round your response to two decimal places.)

The length of the path

Upper A minus Upper B minus Upper E minus Upper F minus Upper I minus Upper KA ? B ? E ? F ? I ? K

is

38.3438.34

weeks. (Round your response to two decimal places.)

The length of the path

Upper A minus Upper B minus Upper E minus Upper G minus Upper J minus Upper KA ? B ? E ? G ? J ? K

is

nothing

weeks. (Round your response to two decimal places.)

Homework Answers

Answer #1

(a)

Expected activity time for 'C' = (a + 4m + b)/6 = (9+4*12+16)/6 = 12.167 weeks

(b)

Variance of activity time for 'C' = (b - a)2/36 = ((16 - 9)^2)/36 = 1.36

(c)

Activity a m b te=(a+4m+b)/6
A 4 8 10 7.67
B 2 9 24 10.33
E 1 2 4 2.17
F 5 8 21 9.67
H 2 2 2 2.00
J 4 7 12 7.33
K 1 1 4 1.50
Total 40.67

(d)

Activity a m b te=(a+4m+b)/6
A 4 8 10 7.67
B 2 9 24 10.33
E 1 2 4 2.17
F 5 8 21 9.67
I 7 7 7 7.00
K 1 1 4 1.50
Total 38.33

(e)

Activity a m b te=(a+4m+b)/6
A 4 8 10 7.67
B 2 9 24 10.33
E 1 2 4 2.17
G 2 3 4 3.00
J 4 7 12 7.33
K 1 1 4 1.50
Total 32.00
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are given in the following table. Assume that the activity times are independent Activity Immediate Predecessor Time (Weeks) a m b A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 a) Calculate the expected time and variance for each activity. b) What is the expected completion time of the critical path? What is the...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
Given below are the durations of and the precedence relationships among the activities required to compute...
Given below are the durations of and the precedence relationships among the activities required to compute a project. 1) construct an AOA network of the project 2)what is the critical path? determine the expected duration of the project. 3)compute the standard deviation of the critical path Duration(days) Activity pre-decessor(s) a m b A - 4 7 12 B A 6 9 13 C A 5 7 9 D B,C 3 5 8 E B 7 8 10 F A 2...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity Activity Time​ (weeks) Immediate​ Predecessor(s) A 6 − B 1 − C 9 − D 3 ​A, B E 6 B F 4 ​D, C G 5 ​E, C H 9 ​F, G b. Specify the critical path. The critical path is _____ and the project duration is_____ c. Calculate the slack for activities A and D.
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8 13 B 5 7 9 C 5 12 19 D 2 5 8 E 5 9 19 F 4 8 18 G 9 15 21 H 4 6 14 If required, round your answers to two decimal places. A.) Find the critical path. Activity Expected Time Variance A B C D E F G H Earliest Latest Earliest Latest Critical Activity Start Start Finish...
A market analyst wants to know if the new website he designed is showing increased page...
A market analyst wants to know if the new website he designed is showing increased page views per visit. A customer is randomly sent to one of two different​ websites, offering the same​ products, but with different designs. The accompanying table shows the data from five randomly chosen customers from each website. Test the null hypothesis that the mean number of page visits is the same for the two websites. Assume that the data come from a population that is...
A market analyst wants to know if the new website he designed is showing increased page...
A market analyst wants to know if the new website he designed is showing increased page views per visit. A customer is randomly sent to one of two different​ websites, offering the same​ products, but with different designs. The accompanying table shows the data from five randomly chosen customers from each website. Test the null hypothesis that the mean number of page visits is the same for the two websites. Assume that the data come from a population that is...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT