Question

A firm must choose between remaining where it is, with current capacity, and building a new...

A firm must choose between remaining where it is, with current capacity, and building a new facility with 50% more capacity. The probability of high demand is estimated to be 75%. The current facility would provide $100,000 profit if there is high demand or $50,000 profit if there is low demand. The replacement facility would provide $160,000,000 profit if there is high demand but would only break even if there is low demand. What is the expected value of each option? (Enter your answer without using a comma separator, e.g. 5275.)
?For replacement facility = $____

For current facility = $____

Homework Answers

Answer #1

Following are to be noted :

Probability of high demand = 0.75

Therefore, probability of low demand = 1- 0.75 = 0.25

Expected value of current facility

= Probability of high demand x Profit under high demand + Probability of low demand x Profit under low demand

= 0.75 x 100,000 + 0.25 x 50,000

= $75,000 + $12500

= $87500

Expected value of replacement facility

= Probability of high demand x Profit under high demand + Probability of low demand x Profit under low demand

= 0.75 x 160,000,000 + 0.25 x 0

= $120,000,000

EXPECTED VALUE OF CURRENT FACILITY = $87500

EXPECTED VALUE OF REPLACEMENT FACILITY = $120000000

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Expando, Inc. is considering the possibility of building an additional factory that would produce a new...
Expando, Inc. is considering the possibility of building an additional factory that would produce a new addition to its product line. The company is currently considering two options. The first is a small facility that it could build at a cost of $6 million. If demand for new products is low, the company expects to receive $10 million in discounted revenues (present value of future revenues) with the small facility. On the other hand, if demand is high, it expects...
Best Buy USA must to decide whether to build a new distribution center in Paramus, New...
Best Buy USA must to decide whether to build a new distribution center in Paramus, New Jersey, to serve its stores in the Northeast region of the United States. The options it has can be simply described as building a small, medium-size, or large facility. The costs and expected returns have been thoroughly estimated but one big question remains: what will be the general level of the demand for the entire range of products that Best Buy USA distributes? Three...
MJ Logistics has decided to build a new warehouse to support its supply chain activities. They...
MJ Logistics has decided to build a new warehouse to support its supply chain activities. They have the option of building either a large warehouse or a small one. Construction costs for the large facility are R8 million versus R5 million for the small facility. The profit (excluding construction cost) depends on the volume of work the company expects to contract for in the future. This is summarized below (in millions of rands): large warehouse - High Volume =35 Low...
A property developer is selling new villas in Spain. The cost of building each villa is...
A property developer is selling new villas in Spain. The cost of building each villa is 100,000 euros. There are two types of potential buyers. Type 1 buyers are willing to pay up to P1 = 250,000 - 10,000M1, where M1 is the number of months that they would have to wait before taking possession of the villa. Type 2 buyers are willing to pay up to P2 = 200,000 - 1,000M2, where M2 is the number of months that...
6. A property developer is selling new villas in Spain. The cost of building each villa...
6. A property developer is selling new villas in Spain. The cost of building each villa is 100,000 euros. There are two types of potential buyers. Type 1 buyers are willing to pay up to P1 = 250,000 – 10,000M1, where M1 is the number of months that they would have to wait before taking possession of the villa. Type 2 buyers are willing to pay up to P2 = 200,000 – 1,000M2, where M2 is the number of months...
Revision Questions 1.     Non-Current Assets Provide the journal entries for the following transaction: Matthew built a...
Revision Questions 1.     Non-Current Assets Provide the journal entries for the following transaction: Matthew built a new building to store supplies for his business. The builder charged $250,000, the electrician cost $10,000 and a painter cost 5,000. A compulsory fire safety inspection was conducted and cost $1,000. Matthew is still worried about the building burning down and has purchased 12 months insurance for $10,000 which covers the value of the building in case of destruction. Matthew calculated that the above...
Cover-to-Cover Company is a manufacturer of shelving for books. The company has compiled the following cost...
Cover-to-Cover Company is a manufacturer of shelving for books. The company has compiled the following cost data, and wants your help in determining the cost behavior. After reviewing the data, complete requirements (1) and (2) that follow. Units Total Total Total Machine Produced Lumber Cost Utilities Cost Depreciation Cost 15,000 shelves $180,000 $18,250 $135,000 30,000 shelves 360,000 35,500 135,000 60,000 shelves 720,000 70,000 135,000 75,000 shelves 900,000 87,250 135,000 2. For each cost, determine the fixed portion of the cost,...
Value-Added and Non-Value-Added Costs, Unused Capacity For Situations 1 through 6, provide the following information: An...
Value-Added and Non-Value-Added Costs, Unused Capacity For Situations 1 through 6, provide the following information: An estimate of the non-value-added cost caused by each activity. If required, round your final answer to the nearest dollar. The root causes of the activity cost (such as plant layout, process design, and product design). The appropriate cost reduction measure: activity elimination, activity reduction, activity sharing, or activity selection. Choose " Multiple" in the Root cause column, wherever there is more than one root...
**This is the full question, but I only need the Contribution Margin, Sales Mix and Target...
**This is the full question, but I only need the Contribution Margin, Sales Mix and Target Profit. Cover-to-Cover Company is a manufacturer of shelving for books. The company has compiled the following cost data, and wants your help in determining the cost behavior. After reviewing the data, complete requirements (1) and (2) that follow. Units Total Total Total Machine Produced Lumber Cost Utilities Cost Depreciation Cost 13,000 shelves $156,000 $15,950 $145,000 26,000 shelves 312,000 30,900 145,000 52,000 shelves 624,000 60,800...
choose correct answer 1)The difference between manufacturer's desire to produce large quantities of a limited variety...
choose correct answer 1)The difference between manufacturer's desire to produce large quantities of a limited variety of items vs. a customer's desire to demand small quantities of numerous items best describes which of the following?        Discrepancy in space        Discrepancy in quantity and assortment        Discrepancy in time        Discrepancy in logistics 2)Developing long-term relationships with key supply chain participants (e.g., consumers, intermediate customers, and suppliers) can be best described as:        Relationship marketing...