Question

You are a project manager for a small construction project. Your project was budgeted for U.S....

You are a project manager for a small construction project. Your project was budgeted for U.S. $82,000 over a six-week period. As of today, you have spent U.S. $32,000. The earned value is U.S. $34,000. According to your schedule, you should have spent U.S. $40,000 by this time. Based on these circumstances, your project could be BEST described as:

A.) Ahead of schedule

B.) Behind schedule

C.) On schedule

D.) Not enough information is provided

Homework Answers

Answer #1

From the given set of data,

Percentage of the project which should have been completed

= Amount should have been spent / Project budget x 100

= 40,000/82,000 x 100

= 48.78 %

Percentage of the project actually completed

= Earned value of the project / Project budget x 100

= 34000/ 82000 x 100

= 41.46%

Therefore, on a given time when 48.78% of the project is expected to be completed, only 41.46% of the project is completed.

Therefore , the project is behind schedule

ANSWER : B ) BEHIND SCHEDULE

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Your project has a total budget of $10,000,000. At the end of week 26 of your...
Your project has a total budget of $10,000,000. At the end of week 26 of your project, you have the following values: Planned Value: $1,000,000 Earned Value: $750,000 Actual Cost: $1,250,000 Questions: What is your schedule variance? Is your project ahead of or behind schedule? What is your cost variance? Is your project over budget or under budget? Provide two estimates of the cost at completion for your project. Be sure to show your calculations.
You are the project manager of a complicated construction project, which involves building highways in the...
You are the project manager of a complicated construction project, which involves building highways in the whole state of North Carolina. You have several groups working with you in the project. To plan resources for this project and determine connection between individuals you should preferably use: Staffing pool description Staffing management plan Responsibility assignment matrix (RAM) Organization matrix You are the project manager of a project team that includes several new recruits. You notice that most of the team members...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
You have been hired as construction manager for a building construction project. Highlight some key aspects...
You have been hired as construction manager for a building construction project. Highlight some key aspects of your anticipated role.
Your firm MS Ankomadu has won a project of €1,785,000 to build a 161kV/33kV sub-station. You...
Your firm MS Ankomadu has won a project of €1,785,000 to build a 161kV/33kV sub-station. You have been selected as the project manager to lead the project team for the successful execution of the project. You are the project manager, there are a total of 8,400 hours of work schedule on the project. You made your checks with the accounting department, and they told you that you have spent a total of €1,144,000. According to the schedule, your team should...
Swimming Pool Installation: You are the project manager working for Mack's Pool Co. Your project consists...
Swimming Pool Installation: You are the project manager working for Mack's Pool Co. Your project consists of installing a new swimming pool at the local country club before Memorial Day weekend (pool opening weekend). You would like to find the minimum cost schedule for your project. There is a $9,000 per week penalty for each week the project is delayed beyond week 9. In addition, your project team determined that indirect costs are $15,000 per week. ACTIVITY Immediate Predecessor (s)...
The project manager of a task force planning the construction of a domed stadium had hoped...
The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. One of your site supervisors makes contact to inform you that a subcontractor suffered serious injuries when a section of rebar fell, during a crane lift, and struck him on his shoulder and back. Describe the immediate actions you would take and outline the main elements of the subsequent incident investigation you would lead,...
As a project manager, you have learned, as of the last audit of your project, the...
As a project manager, you have learned, as of the last audit of your project, the project's SPI was 68%, and the project's CPI was 80%. How would you interpret these two parameters? And what would you be your reaction?
You are the manager of a small U.S. firm that sells nails in a competitive market...
You are the manager of a small U.S. firm that sells nails in a competitive market as there are hundreds of other firms selling this standardized commodity. Stores view your nails as identical as to those available from other firms. You are concerned about two recent events that appeared in the news. First, foreign competitors are existing the market due to increased input prices (labor in their home countries). Second, a rise in global income had led to an increased...