Question

Using constant workforce and varying inventory and stockout, what would be the constant workforce? Production required...

Using constant workforce and varying inventory and stockout, what would be the constant workforce? Production required in periods 1,2 and 3 respectively are 1200, 1500 and 900 units. One worker during the panning horizoncan produce two units in one day. Number of work days are 22 in period 17 in period 2 and 21 in period 3. Assume that the beginning inventory and the edniong inventory required are 300 units each. What is the number of workers required during the planning horizon of three periods?

Homework Answers

Answer #1

Total number of units to be produced in 3 periods

= 1200 + 1500 + 900

= 3600 units

It has been mentioned that starting and ending inventory both are 300 units each. Thus net numbers of units to be produced = 3600 units. Had beginning and ending inventory been different, the net requirement would have been different than 3600 units

Total number of working days in three periods

= 22 + 17 + 21

= 60 days

Number of units which can be produced by a worker per day = 2 units

Therefore, total units one worker can produce in three weeks

= 2 x60 units

= 120 units

Since we need a constant workforce,

Number of workers required in three periods

= 3600 / 120

= 30 persons

Hence, the number of workers required will be 30 persons

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Develop a production schedule to produce the exact production requirements by varying the workforce size for...
Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem. The monthly forecasts for Product X for January, February, and March are 950, 1,510, and 1,220, respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February, and 21 in March. Beginning inventory is 550 units. Storage cost is $4 per unit per month...
In order to effectively address the seasonal variation appearing in the annual demand of its products,a...
In order to effectively address the seasonal variation appearing in the annual demand of its products,a bicycle manufacturer starts an aggregate planning.A planning hori- zon of 6 months is used. The (aggregate) demand forecast for the next six months along the number of working days are given below: Month Demand Forcast Number of Working Days Jan 1800 22 Feb 1500 19 Mar 1100 21 apr 900 21 may 1100 22 june 1600 20 If the manufacturer operates 300 days a...
QUESTION 2: Kafue Steel has recorded the monthly forecast for one of its products, mild steel...
QUESTION 2: Kafue Steel has recorded the monthly forecast for one of its products, mild steel grade AISI 1023 rods, for January, February, March and April as 1000, 1500, 1200, and 1400, respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February, 21 in March and 21 in April. Beginning inventory is 500 units. Manufacturing cost is K1,000,000 per unit, storage cost...
Capacity data Beginning workforce 210 employees 210 employees Beginning inventory 400 units 400 units Labor standard...
Capacity data Beginning workforce 210 employees 210 employees Beginning inventory 400 units 400 units Labor standard per unit 6 hours 6 hours Regular time available per period 160 hours 160 hours Overtime available per period 32 hours 32 hours Subcontracting maximum per period 1000 units 1000 units Subcontracting minimum per period 500 units 500 units Demand data Period 1 6000 units Period 2 4800 units Period 3 7840 units Period 4 5200 units Period 5 6500 units Period 6 3600...
A manager is attempting to put together an aggregate plan for the coming nine months. She...
A manager is attempting to put together an aggregate plan for the coming nine months. She has obtained a forecast of expected demand for the planning horizon. The plan must deal with highly seasonal demand; demand is relatively high in periods 3 and 4 and again in period 8, as can be seen from the following forecasts:     Period 1 2 3 4 5 6 7 8 9 Total   Forecast 190 230 260 280 210 170 160 260 180 1,940 The...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Question 4: Aggregate Planning Plan production for a four month period: June through to September. For...
Question 4: Aggregate Planning Plan production for a four month period: June through to September. For June and July you should produce to exact demand forecast. For August and September you should use overtime and inventory with a stable workforce. Stable means the number of workers needed for July will be held constant through September. However the Ministry of Labour regulations put a maximum of 5000 hours of overtime labour per month in August and September (Zero overtime in June...
The? S&OP team at Kansas? Furniture, has received estimates of demand requirements as shown in the...
The? S&OP team at Kansas? Furniture, has received estimates of demand requirements as shown in the table. Assuming? one-time stockout costs for lost sales of ?$125 per? unit, inventory carrying costs of ?$20 per unit per? month, and zero beginning and ending? inventory, evaluate these two plans on an incremental cost? basis: Plan? A: Produce at a steady rate? (equal to minimum? requirements) of 1 comma 000 units per month and subcontract additional units at a ?$70 per unit premium...