Question

What is the probability that the following project will take more than 10 weeks to complete...

What is the probability that the following project will take more than 10 weeks to complete if the activity means and standard deviations are as shown below? (Round standard deviation to 2 decimal places and final answer to 4 decimal places.)

Use Table B.
Activity Mean Standard
Deviation
1-2 5 1.3
2-3 4 1.0
1-3 8 1.6

Homework Answers

Answer #1

Path 1 = (1-2) + (2-3) = 5+4 = 9

Path 2 = (1-3) - 8

So the critical path is 1

The standard deviation of the critical path = Square root of the variance of the critical path

Square root of (2.56+1.69) = Square root of (4.25) = 2.06

The probability of completing the work in 10 weeks = normal distribution of Z score

Z= (TS-TE) / DS of the critical path

Z = (10-9)/2.06 = 0.48

Normal of Z (0.48) = 0.6844

The probability of completeing the work within 10 weeks would be 68%

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Please answer the questions below and show all work. 1. If 10% of all disk drives...
Please answer the questions below and show all work. 1. If 10% of all disk drives produced on an assembly line are defective, what is the probability that there will be exactly one defect in a random sample of 5 of these? What is the probability that there will be no defects in a random sample of 5? 2. The time to complete a construction project is normally distributed with a mean of 60 weeks and a standard deviation of...
What is the probability that a normal random variable will take a value that is less...
What is the probability that a normal random variable will take a value that is less than 1.05 standard deviations above its mean? In other words, what is P(Z < 1.05)? .8531 .1468 .9332 .0668 What is the probability that a normal random variable will take a value that is between 1.5 standard deviations below the mean and 2.5 standard deviations above the mean? In other words, what is P(-1.5 < Z < 2.5)? .9938 .0668 .9270 .0730 What is...
Do women tend to spend more time on housework than​ men? If​ so, how much​ more?...
Do women tend to spend more time on housework than​ men? If​ so, how much​ more? A study reported the results shown in the table to the right for the number of hours spent on housework per week. Complete parts a through d below. Housework Hours   Gender Sample Size Mean Standard Deviation Women 474 30.5 13.7 Men 493 15.0 12.6 A. Based on this​ study, calculate how many more hours per​ week, on the​ average, women spend on housework than...
6. You have been provided the following probability distribution: Pets P(x) x*P(x) (x-µ)²P(x) 0 0.330 1...
6. You have been provided the following probability distribution: Pets P(x) x*P(x) (x-µ)²P(x) 0 0.330 1 0.270 2 0.300 3 0.050 4 0.025 5 0.020 6 or more 0.005 Let x = the total number of pets in a household a. Complete table b. What is the probability of a household having no pets? c. What is the probability of a household having exactly 3 pets? d. What is the probability of a household having between 1 and 3 pets?...
The population mean and standard deviation are given below. Find the required probability and determine whether...
The population mean and standard deviation are given below. Find the required probability and determine whether the given sample mean would be considered unusual. For a sample of nequals70?, find the probability of a sample mean being greater than 215 if muequals214 and sigmaequals5.8. For a sample of nequals70?, the probability of a sample mean being greater than 215 if mu equals 214 and sigmaequals5.8 is 0.9251. ?(Round to four decimal places as? needed.) Would the given sample mean be...
9. A contractor estimates the probabilities for the number of days required to complete a certain...
9. A contractor estimates the probabilities for the number of days required to complete a certain type of construction project as follows: Table 1: Distribution of days of completion Time (Days) 1 2 3 4 5 Probability 0.05 0.20 0.35 0.30 0.10 (a) What is the probability a randomly chosen project will take less than 3 days to complete? (b) Find the expected time to complete. (c) Find the variance of time required to complete a project. (d) The contractor’s...
The amount of time to complete a physical activity in a PE class is normally distributed...
The amount of time to complete a physical activity in a PE class is normally distributed with a mean of 39.4 seconds and a standard deviation of 5.2 seconds. Round answers to 4 decimal places. a) What is the probability that a randomly chosen student completes the activity in less than 35.3 seconds? b) What is the probability that a randomly chosen student completes the activity in more than 46.1 seconds? c) What proportion of students take between 35.6 and...
Consider the discrete probability distribution to the right. Complete parts a and b below. Outcome Probability...
Consider the discrete probability distribution to the right. Complete parts a and b below. Outcome Probability 1 0.17 2 0.25 3 0.25 4 0.33 Mean of this distribution = 2.74 Calculate the standard deviation of this distribution.
Use the probability distribution to complete parts​ (a) and​ (b) below. The number of defects per...
Use the probability distribution to complete parts​ (a) and​ (b) below. The number of defects per 1000 machine parts inspected Defects 0 1 2 3 4 5 Probability 0.265 0.294 0.243 0.140 0.046 0.012 ​(a) Find the​ mean, variance, and standard deviation of the probability distribution. The mean is ?. ​(Round to one decimal place as​ needed.)
Suppose that for a given computer salesperson, the probability distribution of x = the number of...
Suppose that for a given computer salesperson, the probability distribution of x = the number of systems sold in 1 month is given by the following table. x 1 2 3 4 5 6 7 8 p(x) 0.04 0.10 0.13 0.30 0.30 0.11 0.01 0.01 (a) Find the mean value of x (the mean number of systems sold). Answer= 4.14 (b) Find the variance and standard deviation of x. (Round your standard deviation to four decimal places.) variance = 1.8604...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT