A plumbing company has 8 crews fielding repair calls. It takes a crew 2 hours to complete one repair call (including travel time and breaks). What is the capacity of the plumbing company over the course of a 10-hour workday?
Number of crews in plumbing company:- 8
Time taken by 1 crew to complete one call(task):- 2 hours
Total working hours in a day:- 10 hours
Total capacity of completing the tasks by 1 crew in 1 day =
10/2
= 5 calls per crew per day
Total capacity of plumbing company which has 8 crews = Capacity
of completing 1 call by 1 crew X Number of crew
= 5 X 8
= 40 calls per day
The total capacity of the plumbing company over the course of a 10-hour workday is = 40 calls per day.