Question

You are managing a project to film 5 promotional videos to be posted on youtube. Your...

You are managing a project to film 5 promotional videos to be posted on youtube. Your project has a BAC of $12,000. One of the tasks on the critcal path is to arrange filming locations. The task has a BAC of $2,000. You have confirmed 4 of the 10 locations. The task is scheduled to take 2 weeks (10 days), and it is the end of day 2. You have spent $300 so far.

A) identify the tasks BAC, AC, EV, and PV

B) Calculate SPI CPI

C) What do the results tell you about the task's schedule and budget?

Homework Answers

Answer #1

Here the value of CPI is greater than 1 it means the project is performing well against the budget. Thus tasks are running well on budget. SPI schedule performance Index describes the close actual work is being finished as compared to the schedule.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT