Question

Which of the following groups was the predecessor of TJC?

Which of the following groups was the predecessor of TJC?

Homework Answers

Answer #1

TJC i.e. Joint Commission on Accreditation of Healthcare Organization’s predecessor organization grew from the efforts of Ernest Codman for promoting hospital reform that was based on outcomes management in patient care. The American College of Surgeons Hospital Standardization Program was established by Codman's efforts. By merging the Hospital Standardization Program with similar programs run by the American College of Physicians, the American Hospital Association, the American Medical Association, and the Canadian Medical Association in 1951 the Joint Commission on Accreditation of Hospitals was created.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
What is the purpose of predecessor-successor auditor communications? Which party, the predecessor or successor auditor, has...
What is the purpose of predecessor-successor auditor communications? Which party, the predecessor or successor auditor, has the responsibility for initiating these communications? Briefly summarize the information that a successor auditor should obtain from the predecessor auditor.
Which of the following is true? Quarks appear in groups and leptons appear in groups. Quarks...
Which of the following is true? Quarks appear in groups and leptons appear in groups. Quarks appear in groups and leptons are solitary. Quarks are solitary and leptons appear in groups. Quarks are solitary and leptons are solitary. Which force is responsible for beta decay? The strong force. The electromagnetic force. The weak force. The gravitational force. Which of these quarks is most stable? Top. Strange. Down. Up.
Which of the following groups of people Not regarded as economically inactive?
Which of the following groups of people Not regarded as economically inactive?
In a 2-way between groups ANOVA, which of the following is a source of within groups...
In a 2-way between groups ANOVA, which of the following is a source of within groups variance? Differences between the marginal means and the grand mean. Differences among the marginal means. Differences between individual participant scores and their respective cell means. Differences among the cell means.
Insert the correct predecessor function using Microsoft Project for the following question: "Work may not start...
Insert the correct predecessor function using Microsoft Project for the following question: "Work may not start on basement until work on foundation is 50% complete. Work on basement may not proceed past 70% until work on foundation is 100% complete."
Which is the most important stakeholder of the following groups in terms of sentiments in the...
Which is the most important stakeholder of the following groups in terms of sentiments in the market for the company? Potential new shareholders. Existing shareholders. Current creditors. The CRA. Existing management
1. Which of the following sets in (a) are groups under addition? For each set which...
1. Which of the following sets in (a) are groups under addition? For each set which is not a group under addition, show which group property does not apply by counterexample. a. N; W; Z; Q; R; E; C; P(x, 3); M(2,1,N) .
Which of the following is not true about ‘sclereids’? (a) these are groups of living cells...
Which of the following is not true about ‘sclereids’? (a) these are groups of living cells (b) these are found in nut shells, guava pulp, pear (c) these are also called stone cells (d) these are form of sclerenchyma with fibres.
List the symmetry elements of the following molecules and name the point groups to which they...
List the symmetry elements of the following molecules and name the point groups to which they belong: (a) NO2, (b) N2O, (c) CHCl3, (d) CH2=CH2. ​Show all work for all parts.
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...