Question

At the end of week 24, the project with the data presented in the table below...

At the end of week 24, the project with the data presented in the table below has the earned value right on schedule, but the actual expenses are $9,000. What are the CPI, SPI, CR,

ETC, and EAC?

Activity

Predecessors

Duration (weeks)

Budget ($)

a

-

6

900

b

-

6

1200

c

a

6

1200

d

a

12

1800

e

b, c

14

1400

f

B,c,d

10

1500

g

D,e

16

800

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative completed times for four periods of the project. Completed% Activity ID Activity Predecessors Estimated Duration(Weeks) Budget ($) Actual Spend ($) 1 2 3 4 Crash time Crash cost$ A 7          7,000                       9,000 20 40 100 100 6             8,000 B A 2          5,000                       5,000 20 60 100 100 1             7,000 C A 4          9,000                       6,000 0 40...
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
Problem #5 An IT project requires 6 activities. The table below displays the expected time and...
Problem #5 An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity. Activity Expected time (weeks) Budgeted Cost Immediate Predecessors A 3 $2,000 None B 4 $6,000 None C 2 $7,000 A D 5 $9,000 B E 3 $3,000 C F 6 $8,000 B,D Develop a budget for the 15 weeks of the project using LS times.
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
You have the following investment options as laid out in the table below: Project Cash Flow...
You have the following investment options as laid out in the table below: Project Cash Flow Year A B C D E 0 -$1000 -$1200 -$2000 -$1600 -$1400 1 900 800 950 900 400 2 500 700 950 900 400 3 100 700 950 900 1200 4 50 300 950 900 400 If your MARR is 15%, which of these options should you select? Solve this problem by challenger-defender analysis.
Assuming that the cost of each activity is linearly distributed over its duration, create two budgets...
Assuming that the cost of each activity is linearly distributed over its duration, create two budgets as follows: The first budget should assume an early-start schedule The second budget should assume a late-start schedule Explain why the two budgets are different Activity Duration (days) Immediate predecessors Cost A 3 – $3,000 B 4 –  2,000 C 3 –  6,000 D 2 C  2,000 E 1 B  1,000 F 5 A 10,000 G 2 B  4,000 H 3 B  9,000 I...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
Prepare a table in Excel showing the time-phased budget for the project. Assume the budgeted cost...
Prepare a table in Excel showing the time-phased budget for the project. Assume the budgeted cost is linearly distributed over the duration of the activity, e.g., if the budgeted cost of a Task is $100 and the duration of the Task is 2 weeks, then budgeted cost/week=100/2= $50. All calculations should be done within the Excel spreadsheet. Task Predecessor Budget Cost ($) Duration (weeks) A - $              1,500 4 B A $              1,350 2 C A $              1,260 3 D...
AON The table given below contains the activity label, its respective duration (in weeks) and its...
AON The table given below contains the activity label, its respective duration (in weeks) and its precedents. Use critical path method to find the critical path and activities of this project. ACTIVITY DURATION (IN WEEKS) PRECEDENTS A 6 – B 4 – C 3 A D 4 B E 3 B F 10 – G 3 E, F H 2 C, D
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT