At the end of week 24, the project with the data presented in the table below has the earned value right on schedule, but the actual expenses are $9,000. What are the CPI, SPI, CR,
ETC, and EAC?
Activity |
Predecessors |
Duration (weeks) |
Budget ($) |
a |
- |
6 |
900 |
b |
- |
6 |
1200 |
c |
a |
6 |
1200 |
d |
a |
12 |
1800 |
e |
b, c |
14 |
1400 |
f |
B,c,d |
10 |
1500 |
g |
D,e |
16 |
800 |