Set up the system of equations and then solve it by using an
inverse matrix.
A manufacturer of table saws has three models (Deluxe, Premium, and
Ultimate) that must be painted, assembled, and packaged for
shipping. The table gives the number of hours required for each of
these operations for each type of table saw.
Deluxe | Premium | Ultimate | |
---|---|---|---|
Painting | 1.6 | 2 | 2.4 |
Assembly | 2 | 3 | 4 |
Packaging | 0.5 | 0.5 | 1 |
(a) If the manufacturer has 96 hours available per day for painting, 154 hours for assembly, and 37 hours for packaging, how many of each type of saw can be produced each day?
Deluxe | saws |
Premium | saws |
Ultimate | saws |
(b) If 8 more hours of painting time become available, find the new
production strategy.
Deluxe | saws |
Premium | saws |
Ultimate | saws |