Question

You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you...

You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent?

Year Project A Project B
0 -$80,000 -$80,000
1 31,000

0

2 31,000 0
3 31,000 0

A.) accept A at 8.5 percent and B at 13 percent

B.) accept B at 8.5 percent and A at 13 percent

C.) Accept B at 8.5% and neither at 13 percent

D.) accept A at 8.5 percent and neither at 13 percent

Homework Answers

Answer #1

As given Project B has 0 inflows in all three years so it would be rejected at any given discount rate.

Now option d is only valid where we need to identify which at which rate a project should be accepted. Logically NPV will be higher at lesser discount rate so project should be accepted at 8.5%.

Now NPV at both 8.5% and 13% are negative so ideally we should not accept any of the project at any rate however option D is more correct out of all the given option.

Year Cashflow PV at 8.5% PV at 13%
0 -80000 -80000 -80000
1 31000 28571.429 27433.63
2 31000 26333.114 24277.55
3 31000 24270.151 21484.56
NPV -825.3065 -6804.269

Hope this helps, feel free to let us know in case of any questions. Thanks and have a good day.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 9 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -21,000 11,000 31,000 2,000   Project B Cash Flow -31,000 11,000 21,000 51,000 Use the NPV decision rule to evaluate these...
3. A project has an initial cost of $30,000 and a 3-year life. The company uses...
3. A project has an initial cost of $30,000 and a 3-year life. The company uses straight-line depreciation to a book value of zero over the life of the project. The projected average net income from the project is $1,766.67 per year for the next 3 years, respectively. What is the accounting rate of return based on average investment? A. 11.78 percent B. 14.69 percent C. 8.72 percent D. 11.04 percent 4. You are considering two mutually exclusive projects with...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 8 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and three years, respectively. Time 0 1 2 3 Project A Cash Flow ?20,000 10,000 30,000 1,000 Project B Cash Flow ?30,000 10,000 20,000 50,000 Use the MIRR decision rule to evaluate...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -30,000 20,000 40,000 11,000   Project B Cash Flow -40,000 20,000 30,000 60,000 Use the NPV decision rule to evaluate these...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three and a half years, respectively. Time 0 1 2 3 Project A Cash Flow ?1,000 300 400 700 Project B Cash Flow ?500 200 400 300 Use...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three and a half years, respectively. Time 0 1 2 3 Project A Cash Flow ?1,000 300 400 700 Project B Cash Flow ?500 200 400 300 Use...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are 2.5 and 3.5 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -1,000 300 400 700   Project B Cash Flow -500 200 400 300 Use the payback decision rule to evaluate these projects;...
You are considering the following two mutually exclusive projects with the following cash flows:                           &nbsp
You are considering the following two mutually exclusive projects with the following cash flows:                                                                                  Project A                                  Project B                                                             Year    Cash Flow                   Year    Cash Flow                                                             0          -$75,000                         0       -$70,000                                                             1          $19,000                         1       $10,000                                                             2          $48,000                         2       $16,000                                                             3          $12,000                         3       $72,000                        Required rate of return                     10 %                                        13 %                             Calculate the NPV, IRR,...
You are considering two mutually exclusive projects with the following cash flows. Which project would you...
You are considering two mutually exclusive projects with the following cash flows. Which project would you choose? (The following is the only information you have. Don’t ask for more because I don’t have any more information?) Hint: Find the “crossover rate” to answer. PLEASE SHOW & EXPLAIN ALL WORK Year Project A Project B 0 -240,000 -198,000 1 0 110,800 2 0 82,500 3 325,000 45,000
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0 –$ 61,000 –$ 76,000 1 41,000 40,000 2 36,000 49,000 3 31,000 52,000    The cash flows of Project A are expressed in real terms while those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 12 percent and the inflation rate is 3 percent.    Calculate the NPV for each project. (Do not round intermediate calculations and round...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT