You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent?
Year | Project A | Project B |
0 | -$80,000 | -$80,000 |
1 | 31,000 |
0 |
2 | 31,000 | 0 |
3 | 31,000 | 0 |
A.) accept A at 8.5 percent and B at 13 percent
B.) accept B at 8.5 percent and A at 13 percent
C.) Accept B at 8.5% and neither at 13 percent
D.) accept A at 8.5 percent and neither at 13 percent
As given Project B has 0 inflows in all three years so it would be rejected at any given discount rate.
Now option d is only valid where we need to identify which at which rate a project should be accepted. Logically NPV will be higher at lesser discount rate so project should be accepted at 8.5%.
Now NPV at both 8.5% and 13% are negative so ideally we should not accept any of the project at any rate however option D is more correct out of all the given option.
Year | Cashflow | PV at 8.5% | PV at 13% |
0 | -80000 | -80000 | -80000 |
1 | 31000 | 28571.429 | 27433.63 |
2 | 31000 | 26333.114 | 24277.55 |
3 | 31000 | 24270.151 | 21484.56 |
NPV | -825.3065 | -6804.269 |
Hope this helps, feel free to let us know in case of any questions. Thanks and have a good day.