Question

The following cash flows are given for a project C0 = -9000 C1= +9000 C2= +18000...

The following cash flows are given for a project
C0 = -9000 C1= +9000 C2= +18000

The NPV of the project at a discount rate of 50% is:
A.) 18,000 B.) 5,000 C.) 11,000 D.) zero or E.) none of these

The IRR for this project is:
A.) 10% B.) 25% C.) 50% D.) 100% or E.) none of these

The payback period for this project is:
A.) zero years B.) one year C.) two years D.) three years or E.) none of these.

So I’m pretty sure the NPV is B.) 5,000 and the IRR is D.) 100% but I cannot figure out the payback period can someone please help.

Homework Answers

Answer #1
Answer is B. $5000
Net Present value:
Year Cashflows PVF @50% Present values
0 -9000 1 -9000
1 9000 0.666667 6000
2 18000 0.444444 8000
NPV 5000
Answer is D. 100%
Year Cashflows PVF @100% Present values
0 -9000 1 -9000
1 9000 0.5 4500
2 18000 0.25 4500
NPV 0
Hence, IRR is 100%
Answer is B. One year
Payback period:
Year Cashflows Cumulative cash flows
0 -9000 -9000
1 9000 0
2 18000 18000
As, the cumulative cashflows is 0 at Year1.
Therefore,
payback period is 1 year
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given the following Cash flows: C0 = - $6,750 C1 = $4,500 C2 = $18,000 Calculate...
Given the following Cash flows: C0 = - $6,750 C1 = $4,500 C2 = $18,000 Calculate the NPV of the above project for discount rates of 0%, 50%, and 100%. What is the IRR of the project?
Consider the following cash flows: Cash Flows ($) C0 C1 C2 −6,950 4,700 18,400 a. Calculate...
Consider the following cash flows: Cash Flows ($) C0 C1 C2 −6,950 4,700 18,400 a. Calculate the net present value of the above project for discount rates of 0, 50, and 100%. NPV @ 0% $ NPV @ 50% $ NPV @100% $ b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a percent rounded to the nearest whole number.) IRR %
A project has the following forecasted cash flows: Cash Flows Thousands of dollars C0 C1 C2...
A project has the following forecasted cash flows: Cash Flows Thousands of dollars C0 C1 C2 C3 -100 40 60 50 The investor expected rate of return is 10%. The cost of capital is 12%. Required: 1.What will you choose to be the discount rate? Why? 2.Please calculate the payback period (PP) and return on investment (ROI). 3.Please calculate NPV,PVI and IRR.. 4.Make decision based on the above calculation and explain the reasons. 5.David said that the profit is the...
2. A project has the following cash flows             C0                    C1    &n
2. A project has the following cash flows             C0                    C1                    C2                    C3                                       ($1000)             $300                $400                $600 What is the project’s payback period? Year 0 1 2 3 Cash Flow ($1000) $300 $400 $600 Cumulative ($1000) ($700) ($300) 300 a. Calculate the projects NPV at 10%. b. Calculate the project’s PI at 10%. c. Calculate an IRR for the project in question 2 How would you answer a,b, and c in excel? I am getting...
Suppose the cash flows for project are C0 = -2000; C1 = 500; C2 = 1000;...
Suppose the cash flows for project are C0 = -2000; C1 = 500; C2 = 1000; C3 = 4000, C4= 1000, C5= 500. The discounted payback period is ____________________ and profitability index is ___________________ at a discount rate of 10 percent.
Here are the cash flows for a project under consideration: C0 C1 C2 −$8,010 +$5,940 +$20,160...
Here are the cash flows for a project under consideration: C0 C1 C2 −$8,010 +$5,940 +$20,160 a. Calculate the project’s net present value for discount rates of 0, 50%, and 100%. (Round your answers to the nearest whole dollar.) b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a whole percent.)
Here are the cash flows for a project under consideration: C0 C1 C2 −$7,020 +$4,860 +$18,360...
Here are the cash flows for a project under consideration: C0 C1 C2 −$7,020 +$4,860 +$18,360 a. Calculate the project’s net present value for discount rates of 0, 50%, and 100%. (Round your answers to the nearest whole dollar.) b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a whole percent.)
Here are the the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3...
Here are the the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A -21,200 9,328 9,328 9,328 B -21,200 0 0 28,620 what is the IRR of each project? (round answer to 2 decimal places)
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 22,200 +$ 9,768 +$ 9,768 +$ 9,768 B − 22,200 0 0 + 29,970 What is the IRR of each project? (Round your answers to 2 decimal places.)
A project has the following cash flows. C0 C1 C2 C3 ($770) $290 $530 $236 Calculate...
A project has the following cash flows. C0 C1 C2 C3 ($770) $290 $530 $236 Calculate an IRR for the project using an iterative technique. (Hint: Start by guessing 17%.) Do not round intermediate calculations. Round PVF values in intermediate calculations to four decimal places. Round the answer to whole percentage. %
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT