Question

Project S requires an initial outlay at t = 0 of $10,000, and its expected cash...

Project S requires an initial outlay at t = 0 of $10,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $50,000, and its expected cash flows would be $13,750 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Project S, since the NPVS > NPVL. c. Neither Project S nor L, since each project's NPV < 0. d. Both Projects S and L, since both projects have NPV's > 0. e. Both Projects S and L, since both projects have IRR's > 0.

Homework Answers

Answer #1

S:

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=6500/1.16+6500/1.16^2+6500/1.16^3+6500/1.16^4+6500/1.16^5

=21282.91

NPV=Present value of inflows-Present value of outflows

=21282.91-10,000

=$11282.91(Approx)

L:

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=13750/1.16+13750/1.16^2+13750/1.16^3+13750/1.16^4+13750/1.16^5

=45021.54

NPV=Present value of inflows-Present value of outflows

=45021.54-50,000

=-4978.46(Approx)(Negative)

Hence S must be chosen having positive and higher NPV.

Hence the correct option is:

b. Project S, since the NPVS > NPVL.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project S requires an initial outlay at t = 0 of $12,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $45,000, and its expected cash flows would be $13,150 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Neither Project...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $28,500, and its expected cash flows would be $13,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $12,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's...
Project R requires an initial outlay at t = 0 of $14,000, and its expected cash...
Project R requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $32,500, and its expected cash flows would be $13,050 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 9%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places. = % Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay...
Project S costs $19,000 and its expected cash flows would be $6,500 per year for 5...
Project S costs $19,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $32,000 and its expected cash flows would be $8,850 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0 . c. Both Projects S and...
Project S costs $14,000 and its expected cash flows would be $6,500 per year for 5...
Project S costs $14,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $37,500 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0. c. Neither Project S nor L, since each project's NPV...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $15,000 and its expected cash flows would...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $15,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $45,000 and its expected cash flows would be $9,900 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have NPV's > 0....
Project S costs $12,000 and its expected cash flows would be $5,500 per year for 5...
Project S costs $12,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $26,000 and its expected cash flows would be $11,500 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Project S, since the NPVS > NPVL. c. Neither Project S nor L,...
Project S costs $13,000 and its expected cash flows would be $5,000 per year for 5...
Project S costs $13,000 and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $34,500 and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have NPV's > 0. c. Both Projects S and L,...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT