Question

Briefly answer in Excel the questions that follow. An answer of 1-3 sentences for each question...

Briefly answer in Excel the questions that follow. An answer of 1-3 sentences for each question should suffice.

  1. You are considering two mutually exclusive projects. The NPV for project one is positive and higher than the NPV for project two, while the IRR for project two is higher than that for project one. Which project should the firm accept and why?

  1. When does a project result in only one IRR? If a project has more than one IRR, how can we use Excel to find the multiple IRRs?

  1. A diversified, low-risk firm is considering investing in a high-risk project in a new industry. Is it appropriate to use the firm’s WACC as the discount rate when evaluating this project? Why or why not?

  1. Briefly explain the benefits of a portfolio.

Homework Answers

Answer #1

Ans 1) Project with higher NPV will be selected because for project value add is more important higher the NPV better the project.

Ans 2) In case of more than one IRR one should use MIRR function in excel

Ans 3) No it is appropriate to use the WACC as the discount rate due to higher risk associated with the project thus one should use risk premium to evaluate the higher risk project in that way one can get the correct NPV so that there is no issue with the future prospect of the project. Higher risk lead to higher return but that also lead to higher value of WACC.

Ans 4) Portfolios are the combination of stocks thus one can mitigate the risk by creating the portfolio of stocks which are negatively correlated that lead to reduction is portfolio risk it also lead to higher return per unit of risk in comparision of individual stocks.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Briefly answer in Excel the questions that follow. An answer of 1-3 sentences for each question...
Briefly answer in Excel the questions that follow. An answer of 1-3 sentences for each question should suffice. a) You are considering two mutually exclusive projects. The NPV for project one is positive and higher than the NPV for project two, while the IRR for project two is higher than that for project one. Which project should the firm accept and why? b) When does a project result in only one IRR? If a project has more than one IRR,...
Briefly answer the questions that follow. You are considering two mutually exclusive projects. The NPV for...
Briefly answer the questions that follow. You are considering two mutually exclusive projects. The NPV for project one is positive and higher than the NPV for project two, while the IRR for project two is higher than that for project one. Which project should the firm accept and why? When does a project result in only one IRR? If a project has more than one IRR, how can we use Excel to find the multiple IRRs? A diversified, low-risk firm...
If your able to work out the problems instead of using excel since excel isnt accessible...
If your able to work out the problems instead of using excel since excel isnt accessible on the exam. Consider the following projects, for a firm using a discount rate of 10%. If the projects are mutually exclusive, which, if any, project(s) should the firm accept? Project                   NPV                                           IRR                                            PI E                               $200,000                                10.2%                                       1.04 F                               $(200,001)                            11%                                           .81 G                               $1                                                10%                                           1.01 H                              $(235,000)                            9%                                            .95 a.               E b.              F c.               H d.              F and H You are considering two...
A firm has the following investment alternatives. A firm has the following investment alternatives. Year    Project...
A firm has the following investment alternatives. A firm has the following investment alternatives. Year    Project A        Project B Cash Flow       Cash Flow               0        -$100,000        -$100,000   1            50,000              10,000   2            40,000              30,000   3            30,000              40,000   4            10,000              60,000 The firm's cost of capital is 7%. Project A and project B are mutually exclusive. Which investment(s) should the firm make? Project A because it has the higher IRR Project A because it has the higher NPV Neither because both have IRRs less than the cost of capital Project B...
Question text Which of the following statements is INCORRECT? Select one: a. When choosing between mutually...
Question text Which of the following statements is INCORRECT? Select one: a. When choosing between mutually exclusive projects, managers should accept all projects with IRRs greater than the weighted average cost of capital. b. For independent projects, the decision to accept or reject will always be the same using either the MIRR method or the NPV method. c. One of the disadvantages of choosing between mutually exclusive projects on the basis of discounted payback method is that you might choose...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both projects is 10%. The first project has an IRR of 22% and an NPV of $22,432. The second project has an IRR of 12% and an NPV of $24,456. Which project should you select? accept both projects since both are acceptable. pick the project with the shorter payback period. choose the project with the higher NPV. unable to determine due to insufficient information. choose...
QUESTION 20 For this and the next 3 questions. Consider the following MUTUALLY EXCLUSIVE projects. Cost...
QUESTION 20 For this and the next 3 questions. Consider the following MUTUALLY EXCLUSIVE projects. Cost of capital is 10%. Calculate IRR. Year Project A Project B 0 -40,000 -20,000 1 8,000 7,000 2 14,000 13,000 3 13,000 12,000 4 12,000 5 11,000 6 10,000 IRR (A) = 17.47%. IRR(B) = 25.20% IRR (A) = 17.77%. IRR(B) = 25.20% IRR (A) = 17.47%. IRR(B) = 20% None of the above is completely correct 1 points    QUESTION 21 Calculate NPV...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: Project...
Solve the problems below using well-formatted Excel solutions. Do not hardcode numbers in the formulas…..only use...
Solve the problems below using well-formatted Excel solutions. Do not hardcode numbers in the formulas…..only use cell references to the input data. I will change the input data in your problem to check alternate solutions. You will turn in a complete working Excel spreadsheet with your solution. 1. A firm is considering the two mutually exclusive investments projects. Project Alpha requires an initial outlay of $600 and will return $160 per year for the next seven years; Project Beta requires...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost of capital; answer the next 2 questions: year Project A Project B 0 -5000 -1000 1 2500 600 2 2500 600 3 2500 600 1)  Which project should be accepted, if any and why? A: Project B; it has a higher IRR and PI B: Neither project should be accepted, they both have negative NPVs C: Both project should be accepted; they have IRRs greater...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT