Crane Corp. management is evaluating two mutually exclusive
projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive
projects. The cost of capital is 15 percent. Costs and cash flows
for each project are given in the following table.
Year
Project 1
Project 2
0
-$1,292,224
-$1,321,796
1
238,000
384,000
2
329,000
384,000
3
430,000
384,000
4
504,000
384,000
5
800,000
384,000
Calculate NPV and IRR of two projects. (Enter negative
amounts using negative sign, e.g. -45.25. Do not round discount
factors. Round other intermediate calculations and final answer to...
Management of Crane Measures, Inc., is evaluating two
independent projects. The company uses a 12.62 percent...
Management of Crane Measures, Inc., is evaluating two
independent projects. The company uses a 12.62 percent discount
rate for such projects. The costs and cash flows for the projects
are shown in the following table. Year Project 1 Project 2 0 -
$8,066,549 - $11,655,500 1 3,003,590 2,165,830 2 1,608,490
3,783,590 3 1,465,800 2,820,680 4 1,061,800 4,040,500 5 1,153,880
4,449,580 6 1,708,040 7 1,266,990 a. What are the IRRs for the
projects? (Round final answer to 2 decimal places, e.g....
As the director of capital budgeting for Denver Corp., you are
evaluating two mutually exclusive projects...
As the director of capital budgeting for Denver Corp., you are
evaluating two mutually exclusive projects with the following net
cash flows:
Project
X Project
Z
Year Cash
Flow Cash
Flow
0 -$100,000 -$100,000
1 50,000 10,000
2 40,000 30,000
3 30,000 40,000
4 10,000 60,000
If Denver’s cost of capital is 15 percent, which project would you
choose?
Neither project.
Project X, since it has the higher IRR.
Project Z, since it has the higher NPV.
Project X, since it has the higher NPV.
Project Z, since it has the higher IRR....
Cullumber Crafts Corp. management is evaluating two independent
capital projects that will each cost the company...
Cullumber Crafts Corp. management is evaluating two independent
capital projects that will each cost the company $290,000. The two
projects will provide the following cash flows: Year Project A
Project B 1 $84,750 $66,000 2 103,450 99,000 3 24,235 137,250 4
129,655 98,110 Collapse question part (a1) What is the payback
period of both projects? (Round answers to 2 decimal places, e.g.
15.25.)
IRR: Mutually exclusive projects Ocean Pacific Restaurant is
evaluating two mutually exclusive projects for expanding the...
IRR: Mutually exclusive projects Ocean Pacific Restaurant is
evaluating two mutually exclusive projects for expanding the
restaurant's seating capacity. The relevant cash
flows for the projects are shown in the following table. The firm's
cost of capital is 4%.
Project X
Project Y
Initial Investment (CF)
980,000
363,000
Year
Cash inflows (CF)
1
150,000
110,000
2
170,000
98,000
3
220,000
93,000
4
270,000
82,000
5
340,000
67,000
a. calculate the IRR to the nearest whole percent for each of...
(Mutually exclusive projects and NPV) You have been assigned
the task of evaluating two mutually exclusive...
(Mutually exclusive projects and NPV) You have been assigned
the task of evaluating two mutually exclusive projects with the
following projected cash flows:
Year
Project A
Cash Flow
Project B
Cash Flow
0
$(90,000)
$(90,000)
1
32,000
0
2
32,000
0
3
32,000
0
4
32,000
0
5
32,000
240,000
If the appropriate discount rate on these projects is 9
percent, which would be chosen and why?
The NPV of Project A is $ _______. (Round to the nearest
cent.)
Consider the following two mutually exclusive
projects:
Year
Cash Flow (A)
Cash Flow (B)
0
–$...
Consider the following two mutually exclusive
projects:
Year
Cash Flow (A)
Cash Flow (B)
0
–$
424,000
–$
39,500
1
44,500
20,300
2
61,500
13,400
3
78,500
18,100
4
539,000
14,900
The required return on these investments is 11 percent.
a. What is the payback period for each project?
(Do not round intermediate calculations and round your
answers to 2 decimal places, e.g., 32.16.)
Payback period
Project A
years
Project B
years
b. What is the NPV for each...
Consider the following cash flows of two mutually exclusive
projects for A–Z Motorcars. Assume the discount...
Consider the following cash flows of two mutually exclusive
projects for A–Z Motorcars. Assume the discount rate for both
projects is 12 percent. Year AZM Mini-SUV AZF Full-SUV 0 –$ 525,000
–$ 875,000 1 335,000 365,000 2 210,000 450,000 3 165,000 305,000 a.
What is the payback period for each project? (Do not round
intermediate calculations and round your answers to 2 decimal
places, e.g., 32.16.) Payback period AZM Mini-SUV years AZF
Full-SUV years b. What is the NPV for...
Cullumber Incorporated management is considering investing in
two alternative production systems. The systems are mutually
exclusive,...
Cullumber Incorporated management is considering investing in
two alternative production systems. The systems are mutually
exclusive, and the cost of the new equipment and the resulting cash
flows are shown in the accompanying table. The firm uses a 9
percent discount rate for their production systems.
Year
System 1
System 2
0
-$15,100
-$42,300
1
15,100
30,800
2
15,100
30,800
3
15,100
30,800
What are the payback periods for production systems 1 and 2?
(Round answers to 2 decimal places,...
(Mutually exclusive projects and NPV) You have been assigned
the task of evaluating two mutually exclusive...
(Mutually exclusive projects and NPV) You have been assigned
the task of evaluating two mutually exclusive projects with the
following projected cash flows:
Year
Project A
Cash Flow
Project B
Cash Flow
0
$(102,000)
$(102,000)
1
30,000
00
2
30,000
00
3
30,000
00
4
30,000
00
5
30,000
210,000
If the appropriate discount rate on these projects is 11
percent, which would be chosen and why?
The NPV of Project B is $nothing.(Round to the nearest
cent.)