Question

Which of the following is NOT an advantage to NPV as a decision rule (assuming the...

Which of the following is NOT an advantage to NPV as a decision rule (assuming the correct discount rate is used)?

A) NPVs scale correctly.

B) NPVs are independent of financing.

C) NPVs achieve the best value per dollar invested for the firm.

D) NPV's are additive.

Homework Answers

Answer #1

NPV scale correctly cannot be used as an advantage. As it does not consider the life of the project. NPV is the diffeediff between present value if cash inflows and present value of cash outflows. It dies not consider the life of project. Suppose two projects having different lives may have similar NPV. And we would end up selecting the one with highest NPV. Hence, life of the project is an important critirea for selection of project which is not been taken into consideration while calculation NPV of the project. It tells us within how many years we will be able to receiver our initial cost.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following is not a net present value (NPV) decision rule? A        When choosing...
Which of the following is not a net present value (NPV) decision rule? A        When choosing among independent projects, select the one with the highest rate of return B        If an independent investment’s NPV is negative, reject the project C        If an independent investment’s NPV is positive, accept the project D        When choosing among mutually exclusive projects, select the one with the highest NPV
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
Which of the following statements about capital budgeting decision methods is most correct? NPV is superior...
Which of the following statements about capital budgeting decision methods is most correct? NPV is superior since it is the most conceptually correct method. IRR is superior since it measures the rate of return on a capital investment. PI is superior since it measures the present value benefit per dollar of capital invested. PB is superior since it is quick and easy to use and understand. None of the three methods is considered superior to the others.
Selecting the project(s) with the highest NPV(s) is not the correct decision rule when: Multiple Choice...
Selecting the project(s) with the highest NPV(s) is not the correct decision rule when: Multiple Choice a. there is capital rationing. b. there are mutually exclusive projects. c. projects are long-lived. d. projects are independent.
Which of the following statement is correct? Select one: a. All the answers are incorrect. b....
Which of the following statement is correct? Select one: a. All the answers are incorrect. b. A positive NPV means that the firm’s value will decrease if the project is adopted because the new project’s estimated return is lesst than the firm’s required rate of return. c. Reject the project if the IRR is greater than or equal to the required rate of return. d. Payback period is the discount rate that forces the NPV to equal zero. e. All...
1. Which of the following statements is correct? a. A project with conventional cash flows is...
1. Which of the following statements is correct? a. A project with conventional cash flows is one with an initial cash outflow followed by one or more cash inflows. b. The NPV method determines how much the future value of cash inflows exceeds the present value of costs. c. All the answers are correct. d. When two projects are independent, accepting one project implicitly eliminates the other. e. Conventional cash flow patterns could lead to conflicting decisions by NPV and...
) Which if the statements below describes the correct capital budgeting decision rule? a) Reject a...
) Which if the statements below describes the correct capital budgeting decision rule? a) Reject a project if the cost of capital exceeds the IRR. B) Reject a project if the cost of capital is less that the NPV. C) Accept a project if the NPV is greater than the IRR. D) Accept a project if the cost of capital is greater that the NPV.
Your firm is considering a project that has an NPV of $32,600, an IRR of 9.5...
Your firm is considering a project that has an NPV of $32,600, an IRR of 9.5 percent, and a payback period of 8.9 years. The required return is 9% and the required payback period is 9 years. Which one of the following statements correctly applies to this project? A) The net present value indicates accept while the internal rate of return indicates reject. B) The payback decision rule is sufficient in making the decision about the project. C) The payback...
Which one of the following statements about inflation is correct? A. The real rate of return...
Which one of the following statements about inflation is correct? A. The real rate of return accurately indicates how an investment opportunity will change the investor's purchasing power. B. The greater the inflation rate is, the stronger the purchasing power of a currency becomes. C. Deflation is highly desired because it immediately stimulates consumption in an economy. D. When the expected inflation increases, the nominal interest rates decline. Which of the following statements about capital budgeting tools are correct? I....
Which of the following statement is correct? a. A firm should never accept the independent projects...
Which of the following statement is correct? a. A firm should never accept the independent projects having NPVs greater than zero. b. All the answers are incorrect. c. Because the net present value method does not factor in the time value of money, nor the cash flows after the payback period, its usefulness is limited. d. Mutually exclusive projects are the projects that do not have the same task and therefore they do not compete with each other. e. The...