Question

1)      Given the following project data sheet:      Year 1 Year 2 Year 3 Year 4...

1)      Given the following project data sheet:

    

Year 1

Year 2

Year 3

Year 4

Investment at time 0

$ 2000

0

0

0

Revenue

1700

1450

1250

1000

Expense

1000

920

840

760

   Determine after federal income tax the present value if the interest rate of 15 % and inflation    rate 10 %, use mid year continues method .

Homework Answers

Answer #1

Discount rate = (Interest rate - inflation rate) / (1 + inflation rate) = (0.15-0.1)/(1+0.1) = 0.04545 = 4.54%

For Mid year Discounting, half year is taken as 1 year.

Enterprise Value (EV) = FCF1 / (1+r)^(0.5) + FCF2 / (1+r)^1.5 + ..... + FCFn / (1+r)^(n-0.5)

r = discount rate

FCF = Free cash flow

n = number of years

Assumption - Tax rate = 35%

Discount rate 0.045455
Year 0 1 2 3 4 Total
Investment at time 0 -2000 0 0 0
Revenue 1700 1450 1250 1000
Expense -1000 -920 -840 -760
Net Profit -2000 700 530 410 240
Tax -245 -185.5 -143.5 -84
Total -2000 455 344.5 266.5 156
PV -2000      445.00      322.28      238.47      133.52 (860.73)

Present Value (PV) after federal income tax = -860.73

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Example : Project A Project B year 1 6000 2000 Year 2 0 3000 Year 3...
Example : Project A Project B year 1 6000 2000 Year 2 0 3000 Year 3 2500 3000 Year 4 2500 3000 (a) If the discount rate is 8%, what is the present value of project A? (b) If the discount rate is 8%, what is the future value of project A in year 4? No financial calculator, could you please provide normal formula calculate with details?
An investment promises the following cash flow stream: Year 0 Year 1 Year 2 Year 3...
An investment promises the following cash flow stream: Year 0 Year 1 Year 2 Year 3 Year 4 Cashflow 1000 2000 3000 5000 The discount rate is 5%. What is the maximum price that you are willing to pay for this investment now?
Given are the following data for year 1: Revenue = $150 million; Variable cost = $40...
Given are the following data for year 1: Revenue = $150 million; Variable cost = $40 million; Fixed cost = $20 million; Depreciation = $10 million; Interest expense = $15 million; capital Investment = $25 million; change in working capital = $5 million. Corporate tax rate is 30%. Calculate the free cash flow to firm (FCFF) for year 1: A. $36 million. B. $56 million. C. $26 million. D. $66 million.
You are considering the following project. What is the NPV of the project? Project life: 3...
You are considering the following project. What is the NPV of the project? Project life: 3 years Equipment:      Cost: $18,000      Economic life: 3 years      Salvage value: $4,000 Initial investment in net working capital: $2,000 Revenue: $13,000 in year 1, with a nominal growth rate of 5% per year Fixed cost: $3,000 in year 1 Variable cost: 30% of revenue Corporate tax rate (T): 40% WACC for the project: 10% This project does not create incidental effect.
Year 0 Year 1 Year 2 Year 3 Year 4 TOTAL Project A $ (200,000.00) $...
Year 0 Year 1 Year 2 Year 3 Year 4 TOTAL Project A $ (200,000.00) $ 25,000.00 $ 50,000.00 $    75,000.00 $ 100,000.00 $ 250,000.00 Project B $ (200,000.00) $ 50,000.00 $ 75,000.00 $    50,000.00 $    75,000.00 $ 250,000.00 Project C $ (200,000.00) $ 75,000.00 $ 75,000.00 $    50,000.00 $    50,000.00 $ 250,000.00 1. You have $200,000 to invest in the above three projects with corresponding cash flows. The discount rate is 8%. Of the three projects, which, according to...
QUESTION 3 (10 Pelosi Company is considering a project with the following information. The initial investment...
QUESTION 3 (10 Pelosi Company is considering a project with the following information. The initial investment of the project costs the company $15,000 now (outflow at t0). The real interest rate (r) is 15% and the expect inflation rate (h) is 10%. All cash flows in Year 1 and Year 2 occur at the end of the year. Year Nominal Cash Flow Real Cash Flow 1 $11,000 real CF1 = ? 2 $24,200 real CF2 = ? Using Fisher equation,...
Year 0 Year 1 Year 2 Year 3 Year 4 Totals: Project A $ (200,000.00) $...
Year 0 Year 1 Year 2 Year 3 Year 4 Totals: Project A $ (200,000.00) $ 25,000.00 $ 50,000.00 $    75,000.00 $ 100,000.00 $ 250,000.00 Project B $ (200,000.00) $ 50,000.00 $ 75,000.00 $    50,000.00 $    75,000.00 $ 250,000.00 Project C $ (200,000.00) $ 75,000.00 $ 75,000.00 $    50,000.00 $    50,000.00 $ 250,000.00 1. If I decide to borrow my 200K required investment at a rate of 10%, which project would be the best option? A. Project A B. Project...
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4...
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Discount Rate (%) Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A -90 40 50 60 --- 3.0 B -90 30 30 30 30 3.0 (a) The internal rate of return (IRR) for project A is %. (round to two decimals) (b) The internal rate of return (IRR) for project B is %. (round to two decimals) (c) The NPV for project...
Given the following data, calculate the net present value for this capital budgeting project: Annual operating...
Given the following data, calculate the net present value for this capital budgeting project: Annual operating cash flow = $198,500 Fixed asset investment = $649,000 Working capital investment = $38,000 Project life=4 years; Depreciation method=SLD to zero Market salvage value=$187,000; Cost of capital=14%; Tax rate=35%
You are considering the following project. What is the NPV of the project? Project life: 3...
You are considering the following project. What is the NPV of the project? Project life: 3 years Equipment:      Cost: $18,000      Economic life: 3 years      Salvage value: $4,000 Initial investment in net working capital: $2,000 Revenue: $13,000 in year 1, with a nominal growth rate of 5% per year Fixed cost: $3,000 in year 1 Variable cost: 30% of revenue Corporate tax rate (T): 40% WACC for the project: 10% This project does not create incidental effect. Select...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT