Question

Using everything you know about capital budgeting, if the two projects are mutually exclusive, which project...

Using everything you know about capital budgeting, if the two projects are mutually exclusive, which project or projects should the firm undertake? Explain in full. The answer must be complete. Substantiate with numbers.

Homework Answers

Answer #1

Capital budgeting is the decision making technique where initial cash outflow and cash inflow are compared to come to an conclusion about the project. In case of two mutually exclusive project one should be chosen which have higher Net present value. In case where the NPV is same for both/all the project then this situation is indifferent, any project can be selected.

Net present value = Present value of cash inflow - Initial cash outflow

For example there are two project A and B. Project A has NPV of $ 25000 and Project B has NPV of $ 32000 so in this case project B should be choosen as it has higher NPV.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $17,000, and its expected cash flows would...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $17,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $30,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Explain. Which project would you recommend? Explain.
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project A -$500 $45 $45 $45 $220 $220 Project B -$600 $300 $300 $50 $50 $50 Which project would you recommend? Select the correct answer. I. Neither A or B, since each project's NPV < 0. II. Both Projects A and B, since both projects have NPV's > 0. III. Both Projects A and...
Capital budgeting criteria: mutually exclusive projects. Project S costs $17,000 and its expected cash flow would...
Capital budgeting criteria: mutually exclusive projects. Project S costs $17,000 and its expected cash flow would be $5,000 per year 5 years. Mutually exclusive Project L costs $30,000 and its expected cash flow would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Explain. **Show Work**
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$400 $65 $65 $65 $210 $210 Project 2 -$400 $300 $300 $55 $55 $55 Which project would you recommend? Select the correct answer. I. Both Projects 1 and 2, since both projects have NPV's > 0. II. Project 2, since the NPV2 > NPV1. III. Neither A or B, since each project's...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$500 $45 $45 $45 $160 $160 Project 2 -$450 $300 $300 $60 $60 $60 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 1, since the NPV1 > NPV2. c. Both Projects 1 and 2, since both...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$350 $40 $40 $40 $215 $215 Project 2 -$650 $200 $200 $70 $70 $70 Which project would you recommend? Select the correct answer. a. Project 1, since the NPV1 > NPV2. b. Both Projects 1 and 2, since both projects have IRR's > 0. c. Project 2, since the NPV2 > NPV1....
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$250 $75 $75 $75 $170 $170 Project 2 -$700 $200 $200 $50 $50 $50 Which project would you recommend? Select the correct answer. a. Neither Project 1 nor 2, since each project's NPV < 0. b. Both Projects 1 and 2, since both projects have NPV's > 0. c. Project 1, since...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$250 $50 $50 $50 $175 $175 Project 2 -$700 $350 $350 $80 $80 $80 Which project would you recommend? Select the correct answer. a. Project 2, since the NPV2 > NPV1. b. Project 1, since the NPV1 > NPV2. c. Both Projects 1 and 2, since both projects have NPV's > 0....
11-11 CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS $225 $225 $50 $49 Project S costs $15,000, and...
11-11 CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS $225 $225 $50 $49 Project S costs $15,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $37,500, and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Explain
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has...
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has an initial outlay of $10,000, an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an initial outlay of $15,000, an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, and the projects have different lives. If the projects are repeatable, then: You should do both...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT