Question

The energy efficiency project described in Problem 10-23 has a first cost of $150,000, a life...

The energy efficiency project described in Problem 10-23 has a first cost of $150,000, a life of 10 years, and no salvage value. Assume that the interest rate is 8%. a) What is the equivalent uniform annual worth for the expected annual savings? b) Compute the equivalent uniform annual worth for the pessimistic, most likely, and optimistic estimates of the annual savings. What is the expected value of the equivalent uniform annual worth? c) Do the answers to (a) and (b) match? Why or why not? (Problem #23: Annual savings due to an energy project have a most likely value of $30,000. The high estimate of $40,000 has a probability of .25 and the low estimate of $20,000 has a probability of .35.)

Homework Answers

Answer #1

a. EUAB for the expected savings= 40000*0.25 + 20000*0.35 + 30000*(1-0.25-0.35)

= $29000

EAC of the capital investment = Capital cost *(A/P,8%,10 years)

= 150000* 0.149

= $22350

Annual worth= EUAB-EUAC

29000- 22350 = $6650

b.1. Annual worth for the pessimist= EUAB for pessimist- Capital cost

= 20,000- 22350 = $ - 2350

2. Annual worth for optimist= EUAB of optimist- Capital cost

= 40000- 22350 = $17650

3. Annual worth of most likely case= 30000- 22350 = $7650

Expected value= -2350*0.35+ 17650*0.25+ 7650*0.4

= $6650

c) Answers are same due to the presence and consideration of probabilities. In the first case we first calculated the expected value after considering probabilities. In the second we first computed the present worth and then multiplied with probabilities to arrive at the same value.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
An energy efficiency project with a first cost of $150,000, life of 10 years, and with...
An energy efficiency project with a first cost of $150,000, life of 10 years, and with no salvage value has a most likely value of $30,000. The high estimate of 40,000 has a probability of 0.2, and the low estimate of $20,000 has a probability of 0.3. Assume that interest rates are 8%. What is the present worth based on the probabilities given?
An energy efficiency project with a first cost of $150,000, life of 10 years, and with...
An energy efficiency project with a first cost of $150,000, life of 10 years, and with no salvage value has a most likely value of $30,000. The high estimate of 40,000 has a probability of 0.2, and the low estimate of $20,000 has a probability of 0.3. Assume that interest rates are 8%. What is the present worth based on the probabilities given?
The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most...
The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most likely (ML), and pessimistic(PS) estimates are given. If the interest rate is 20%, what is the expected NPV? Parameter Pessimistic Most Likely Optimistic Fist cost 150000 100000 80000 Annual benefit 25000 45000 50000 Project life 5 7 9
A project is being considered that has the first cost of $12,500, creates $5,000 in annual...
A project is being considered that has the first cost of $12,500, creates $5,000 in annual cost savings, requires $3,000 in annual operating costs and has a salvage value of $2,000 after a project life of 3 years with 10% annual interest. Calculate the projects Annual equivalent worth. Please show all work.
A project activity has an optimistic time estimate of three days, a most likely time estimate...
A project activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is: 7 7.5 8 8.5 10
1/ A retrofit project is estimated to cost $150,000. The energy savings are expected to last...
1/ A retrofit project is estimated to cost $150,000. The energy savings are expected to last 25 years, but will need a minor upgrade of $10,000 at year 15. The retrofit is expected to save 100 MWh per year. Assuming a discount rate of 6%, and an electricity cost of $0.12/kWh: a/ What is the net-present value of the system ? b/ What is the equivalent cost of the saved energy?
If a project has an expected time of completion Te of 45 weeks with a standard...
If a project has an expected time of completion Te of 45 weeks with a standard deviation of 7 weeks, what is the probability of completing it (a) within one year (52 weeks)? (b) within 38 weeks. Please solve the problem using PERT , Optimistic time, most likely time, and pessimistic time. Using this formula : Te = (To + 4Tm + Tp) / 6
A project has the following tasks and duration estimates given. These three tasks are done in...
A project has the following tasks and duration estimates given. These three tasks are done in succession on a project. Task Optimistic Estimate Most Likely Estimate Pessimistic Estimate Alpha 30 days 40 days 50 days Beta 20 days 25 days 28 days Charlie 4 days 10 days 12 days Delta 25 days 30 days 50 days What is the expected duration for the project? (3 points) What is the variance for the project? (3 points) What is the standard deviation...
A project with a life of 10 has an initial fixed asset investment of $41,580, an...
A project with a life of 10 has an initial fixed asset investment of $41,580, an initial NWC investment of $3,960, and an annual OCF of –$63,360. The fixed asset is fully depreciated over the life of the project and has no salvage value.    If the required return is 15 percent, what is the project's equivalent annual cost, or EAC?
A project with a life of 10 has an initial fixed asset investment of $30,240, an...
A project with a life of 10 has an initial fixed asset investment of $30,240, an initial NWC investment of $2,880, and an annual OCF of –$46,080. The fixed asset is fully depreciated over the life of the project and has no salvage value.    If the required return is 20 percent, what is the project's equivalent annual cost, or EAC? Multiple Choice $-45,788.59 $-53,868.93 $-56,562.37 $-22,584.40 $-51,175.48