Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project M
Time: 0 1 2 3 4 5
Cash flow –$2,200 $590 $720 $760 $840 $340
NPV $
Should the project be accepted or rejected?
Project A | ||||||
Discount rate | 8.000% | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -2200 | 590 | 720 | 760 | 840 | 340 |
Discounting factor | 1.000 | 1.080 | 1.166 | 1.260 | 1.360 | 1.469 |
Discounted cash flows project | -2200.000 | 546.296 | 617.284 | 603.313 | 617.425 | 231.398 |
NPV = Sum of discounted cash flows | ||||||
NPV Project A = | 415.72 | |||||
Where | ||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||
Accept project as NPV is positive |
Get Answers For Free
Most questions answered within 1 hours.