Question

Blossom Corp. management is investigating two computer systems. The Alpha 8300 costs $3,324,225 and will generate...

Blossom Corp. management is investigating two computer systems. The Alpha 8300 costs $3,324,225 and will generate cost savings of $1,213,225 in each of the next five years. The Beta 2100 system costs $4,000,500 and will produce cost savings of $1,115,750 in the first three years and then $2 million for the next two years. The company’s discount rate for similar projects is 14 percent.

What is the NPV of each system? (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to 0 decimal places, e.g. 1,525.)

NPV of Alpha system $
NPV of Beta system $



Which one should be chosen based on the NPV?

Blossom should chose the ____ system.

A. Beta 2100

B. Alpha 8300

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Champlain Corp. management is investigating two computer systems. The Alpha 8300 costs $2,761,825 and will generate...
Champlain Corp. management is investigating two computer systems. The Alpha 8300 costs $2,761,825 and will generate cost savings of $1,186,025 in each of the next five years. The Beta 2100 system costs $4,207,500 and will produce cost savings of $1,217,750 in the first three years and then $2 million for the next two years. If the company’s discount rate for similar projects is 14 percent: What is the NPV for the two systems? (Enter negative amounts using negative sign, e.g....
Blossom Corp. management is investigating two computer systems. The Alpha 8300 costs $2,785,525 and will generate...
Blossom Corp. management is investigating two computer systems. The Alpha 8300 costs $2,785,525 and will generate cost savings of $1,495,025 in each of the next five years. The Beta 2100 system costs $3,841,500 and will produce cost savings of $1,120,750 in the first three years and then $2 million for the next two years. The company’s discount rate for similar projects is 14 percent. What is the NPV of each system? NPV of Alpha system NPV of Beta system
Emporia Mills management is evaluating two alternative heating systems. Costs and projected energy savings are given...
Emporia Mills management is evaluating two alternative heating systems. Costs and projected energy savings are given in the following table. The firm uses 12.27 percent to discount such project cash flows. Year System 100 System 200 0 $-2,053,200 $-1,741,800 1 314,410 701,900 2 520,830 460,300 3 529,940 614,300 4 656,200 314,000 What is the NPV of the systems? (Enter negative amounts using negative sign e.g. -45.25. Do not round discount factors. Round answers to 0 decimal places, e.g. 5,275.) NPV...
Please answer both parts of this question. Carla Vista Corp. management is planning to spend $650,000...
Please answer both parts of this question. Carla Vista Corp. management is planning to spend $650,000 on a new marketing campaign. They believe that this action will result in additional cash flows of $313,000 each year for three years. If the discount rate is 17.5 percent, what is the NPV on this project? (Enter negative amounts using negative sign e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to 0 decimal places, e.g. 1,525.) Oriole,...
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,292,224 -$1,321,796 1 238,000 384,000 2 329,000 384,000 3 430,000 384,000 4 504,000 384,000 5 800,000 384,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to...
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,304,168 -$1,325,262 1 264,000 379,000 2 365,000 379,000 3 445,000 379,000 4 539,000 379,000 5 739,000 379,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to...
Cullumber Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive,...
Cullumber Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 9 percent discount rate for their production systems. Year System 1 System 2 0 -$15,100 -$42,300 1 15,100 30,800 2 15,100 30,800 3 15,100 30,800 What are the payback periods for production systems 1 and 2? (Round answers to 2 decimal places,...
Crescent Industries management is planning to replace some existing machinery in its plant. The cost of...
Crescent Industries management is planning to replace some existing machinery in its plant. The cost of the new equipment and the resulting cash flows are shown in the accompanying table. If the firm uses an 18 percent discount rate for projects like this. Year Cash Flow 0 -$3,379,600 1 $788,310 2 $898,600 3 $1,137,500 4 $1,212,360 5 $1,602,800 What is the NPV of this project? (Enter negative amounts using negative sign e.g. -45.25. Do not round discount factors. Round other...
Wildhorse Industries management is planning to replace some existing machinery in its plant. The cost of...
Wildhorse Industries management is planning to replace some existing machinery in its plant. The cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses an 18 percent discount rate for projects like this. Should management go ahead with the project? Year Cash Flow 0 -$3,485,400 1 871,710 2 896,700 3 1,104,400 4 1,340,360 5 1,450,600 What is the NPV of this project? (Enter negative amounts using negative sign e.g. -45.25. Do...
Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System...
Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System A costs $200,000, has a four-year life, and requires $65,000 in pretax annual operating costs. System B costs $282,000, has a six-year life, and requires $59,000 in pretax annual operating costs. Both systems are to be depreciated straight-line to zero over their lives and will have zero salvage value. Whichever system is chosen, it will not be replaced when it wears out. The tax...