Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results:
Economic Scenario Probability of Outcome
NPV
Recession 0.05 ($42 million)
Below average 0.20 (24 million)
Average 0.50 12 million
Above average 0.20 14 million
Boom 0.05 38 million
Calculate the project's expected NPV, standard deviation, and
coefficient of variation. Enter your answers for the project's
expected NPV and standard deviation in millions. For example, an
answer of $13,000,000 should be entered as 13. Do not round
intermediate calculations. Round your answers to two decimal
places.
E(NPV):
million
σNPV:
million
CV: