Your division is considering two projects with the following cash flows (in millions):
0 | 1 | 2 | 3 |
Project A | -$27 | $13 | $17 | $8 |
Project B | -$25 | $14 | $11 | $2 |
What are the projects' NPVs assuming the WACC is 5%? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to two decimal places.
Project A: $ million
Project B: $ million
What are the projects' NPVs assuming the WACC is 10%? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to two decimal places.
Project A: $ million
Project B: $ million
What are the projects' NPVs assuming the WACC is 15%? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to two decimal places.
Project A: $ million
Project B: $ million
What are the projects' IRRs assuming the WACC is 5%? Do not round intermediate calculations. Round your answer to two decimal places.
Project A: %
Project B: %
What are the projects' IRRs assuming the WACC is 10%? Do not round intermediate calculations. Round your answer to two decimal places.
Project A: %
Project B: %
What are the projects' IRRs assuming the WACC is 15%? Do not round intermediate calculations. Round your answer to two decimal places.
Project A: %
Project B: %
If the WACC was 5% and A and B were mutually exclusive, which project would you choose? (Hint: The crossover rate is 90.37%.)
-Select-Project AProject BNeither A nor BItem 13
If the WACC was 10% and A and B were mutually exclusive, which project would you choose? (Hint: The crossover rate is 90.37%.)
-Select-Project AProject BNeither A nor BItem 14
If the WACC was 15% and A and B were mutually exclusive, which project would you choose? (Hint: The crossover rate is 90.37%.)
-Select-Project AProject BNeither A nor BItem 15
1.
=NPV(5%,{-27;13;17;8})*(1+5%)=7.71115430299103
2.
=NPV(5%,{-25;14;11;2})*(1+5%)=0.0383327934348328
3.
=NPV(10%,{-27;13;17;8})*(1+10%)=4.87828700225394
4.
=NPV(10%,{-25;14;11;2})*(1+10%)=-1.67918858001503
5.
=NPV(15%,{-27;13;17;8})*(1+15%)=2.41892002958823
6.
=NPV(15%,{-25;14;11;2})*(1+15%)=-3.19347415139311
7.
=IRR({-27;13;17;8})=20.6723919032408%
8.
=IRR({-25;14;11;2})=5.10476830994324%
9.
=IRR({-27;13;17;8})=20.6723919032408%
10.
=IRR({-25;14;11;2})=5.10476830994324%
11.
=IRR({-27;13;17;8})=20.6723919032408%
12.
=IRR({-25;14;11;2})=5.10476830994324%
13.
Project A
14.
Project A
15.
Project A