Question

If cumulative PV = $100,000, cumulative EV = $98,000, and cumulative AC = $104,000, the project...

If cumulative PV = $100,000, cumulative EV = $98,000, and cumulative AC = $104,000, the project is:

Ahead of schedule.

Operating below project cost projections.

Likely to come in over budget at completion.

Likely to come in under budget at completion

Homework Answers

Answer #1

HI

We calculate Scheduling Performance Index (SPI) and Cost Performance Index(CPI) to check whether project is over or under budget or it is on time or not.

SPI = EV/PV = 98000/100000 = 0.98

If it is less than 1 that means project is behind schedule. So option 1 is wrong.

CPI = EV/AC=98000/104000 = 0.94

If it less than 1 that means project is over budget.

Hence out of the options. 3rd option is correct here.Likely to come in over budget at completion

Thanks

   

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Your project has a total budget of $10,000,000. At the end of week 26 of your...
Your project has a total budget of $10,000,000. At the end of week 26 of your project, you have the following values: Planned Value: $1,000,000 Earned Value: $750,000 Actual Cost: $1,250,000 Questions: What is your schedule variance? Is your project ahead of or behind schedule? What is your cost variance? Is your project over budget or under budget? Provide two estimates of the cost at completion for your project. Be sure to show your calculations.
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a...
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a philosophy that the project manager would be assigned during proposal preparation, assist in the preparation of the proposal, and take on the role of the project manager after contract award, assuming the company would be awarded the contract. Usually, contract go-ahead would take place within a week or two after contract award. That made project staffing relatively easy for most of the project managers....
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a...
Background Sarah’s project had now become more complex than she had anticipated. Sarah’s company had a philosophy that the project manager would be assigned during proposal preparation, assist in the preparation of the proposal, and take on the role of the project manager after contract award, assuming the company would be awarded the contract. Usually, contract go-ahead would take place within a week or two after contract award. That made project staffing relatively easy for most of the project managers....
Cook Contractors is a general construction company with a wide variety of projects. Budgeted and actual...
Cook Contractors is a general construction company with a wide variety of projects. Budgeted and actual (to date) results (in thousands of dollars) for a building project follow. Budget Actual    Month Cost %Complete Cost %Complete 0 $ 0 0.0 % $ 0 0.0 % 1 $ 820 2.8 % $ 1,010 2.5 % 2 $ 1,640 5.6 % $ 1,720 5.5 % 3 $ 2,460 8.4 % $ 2,390 7.2 % 4 $ 3,280 11.2 % $ 3,300 10.9 %...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Ivy Terrace The third property was Ivy Terrace, a 75-unit garden apartment project under construction near...
Ivy Terrace The third property was Ivy Terrace, a 75-unit garden apartment project under construction near Arlington, Virginia. There was a building moratorium in parts of the county because of inadequate public facilities, preventing much short-term competition. The property was for sale for $11.2 million, but the broker was certain it could be purchased for $11 million. A 10-year, $7 million mortgage at a 4.25% interest rate had been arranged. The loan had a 30-year amortization period. The land was...
CAPITAL BUDGETING PROJECT NEWMAN ENTERPRISES, Inc. is a multinational conglomerate corporation providing a wide range of...
CAPITAL BUDGETING PROJECT NEWMAN ENTERPRISES, Inc. is a multinational conglomerate corporation providing a wide range of goods and services to its customers. As part of its budgeting process for the next year, it has three mutually exclusive projects under consideration, and it might decide which project should receive the investment funds for this year. As part of the financial analysis team, it is up to you to determine the appropriate valuation of each project. However, before you can determine the...
ou are a Consultant for the professional service firm, BUSI 2083 LLP. Your firm specializes in...
ou are a Consultant for the professional service firm, BUSI 2083 LLP. Your firm specializes in providing a wide variety of internal business solutions for different clients. One of the partners in your practice is impressed with the work you have completed to date and would like to give you additional responsibility. She has asked you to take the lead on this engagement with the hope that a successful outcome may lead to your promotion to Senior Consultant. You take...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT