If cumulative PV = $100,000, cumulative EV = $98,000, and cumulative AC = $104,000, the project is:
Ahead of schedule. |
||
Operating below project cost projections. |
||
Likely to come in over budget at completion. |
||
Likely to come in under budget at completion |
HI
We calculate Scheduling Performance Index (SPI) and Cost Performance Index(CPI) to check whether project is over or under budget or it is on time or not.
SPI = EV/PV = 98000/100000 = 0.98
If it is less than 1 that means project is behind schedule. So option 1 is wrong.
CPI = EV/AC=98000/104000 = 0.94
If it less than 1 that means project is over budget.
Hence out of the options. 3rd option is correct here.Likely to come in over budget at completion
Thanks
Get Answers For Free
Most questions answered within 1 hours.