Question

Answer Question 1-3 Project A has the following projected cash flows: Year           Cash Flow 0                -11,23

Answer Question 1-3

Project A has the following projected cash flows:

Year           Cash Flow

0                -11,235

1                4,400

2                4,400

3                4,400

4                4,400

5                7,400

Q1) The NPV of the above project is $_____. Assume a discount rate of 6%.

a)9541

b)20776

c)17623

d)6388

Q2) The IRR for the above project is __ %.

a)21.09

b)26.76

c)33.95

d)31.25

Q3)Which of the following statement is correct?

a)If the discount rate increases, the IRR will decrease.

b)If the discount rate increases, the NPV will stay the same.

c)If the discount rate decreases, the IRR will turn negative.

d)If the discount rate decreases, the NPV will increase.

Homework Answers

Answer #1

1)

NPV = present value of cash inflows - present value of cash outflows

NPV = -11,235 + 4,400 / (1 + 0.06)1 + 4,400 / (1 + 0.06)2 + 4,400 / (1 + 0.06)3 + 4,400 / (1 + 0.06)4 + 7,400 / (1 + 0.06)5

NPV = $9541

2)

IRR is the rate of return hat makes NPV equal to 0.

NPV = -11,235 + 4,400 / (1 + R)1 + 4,400 / (1 + R)2 + 4,400 / (1 + R)3 + 4,400 / (1 + R)4 + 7,400 / (1 + R)5

Using trial and error method, i.e., after trying various values for R, lets try R as 31.25%

NPV = -11,235 + 4,400 / (1 + 0.3125)1 + 4,400 / (1 + 0.3125)2 + 4,400 / (1 + 0.3125)3 + 4,400 / (1 + 0.3125)4 + 7,400 / (1 + 0.3125)5

NPV = 0

Therefore, IRR is 31.25%

3)

d)If the discount rate decreases, the NPV will increase.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Answer Q1-Q3 Assume that the discount rate of Project B is 15%. Given the following projected...
Answer Q1-Q3 Assume that the discount rate of Project B is 15%. Given the following projected cashflow: Time Cashflow DCF Year 0 -1500 ? Year 1 1000 869.57 Year 2 800 604.91 Year 3 700 460.26 Year 4 500 285.88 Q1: The PBP of the project is __ a)1.625 b)2.125 c)1.535 d)1.5 Q2) The DPBP of the project is __ . a)1.75 b)2.58 c)3.04 d)2.06 Q3) Which of the following statement is correct? a)If the discount rate increases, the PBP...
A project has the following projected cash flows Year 0- R280,000( investment) Year 1 R70,000 Year...
A project has the following projected cash flows Year 0- R280,000( investment) Year 1 R70,000 Year 2 R100,000 Year 3 R130,000 a) Assuming a discount rate of 10% what is the Net Present Value (NPV) of this project over the 3 year period? b) Based on your answer above, should the project be recommended for acceptance? c) would your answer to b above change if the discount rate was 5%? Why? d) what do you understand by the term nominal...
Consider a project with an initial outflow at time 0 and positive cash flows in all...
Consider a project with an initial outflow at time 0 and positive cash flows in all subsequent years. As the discount rate increases, the _____________. A.  IRR remains constant while the NPV increases. B.  IRR decreases while the NPV remains constant. C.  IRR increases while the NPV remains constant. D.  IRR remains constant while the NPV decreases. E.  IRR decreases while the NPV decreases.
Q1.) What is the payback period for the following set of cash flows? Year Cashflow 0...
Q1.) What is the payback period for the following set of cash flows? Year Cashflow 0 -$3900 1 1500 2 1400 3 1800 4 1800 Q2.) An investment project costs $14,400 and has annual cash flows of $4,200 for six years. What is the discounted payback period if the discount rate is 5 percent? Q3.)A project has projected cash flows of –$28,800, $10,400, $13,100, $15,000, $12,100 and –$8,600 for years 0 to 5, respectively. Should this project be accepted based...
Company ABC is considering a project with the following projected cash flows (in thousands): Year 0:...
Company ABC is considering a project with the following projected cash flows (in thousands): Year 0: -$60 Year 1: 10 Year 2: 20 Year 3: 30 Year 4: 40 Year 5: -$25 a. Assuming a 10% hurdle rate, the NPV for the project is b. Assuming a 10% hurdle rate, the IRR for company ABC project is: c. Based on the NPV calculation (10% hurdle rate) , should company ABC undertake the project d. Based on the IRR calculation (10%...
A stand-alone capital project has the following projected cash flows: Year 0 1 2 3 Cash...
A stand-alone capital project has the following projected cash flows: Year 0 1 2 3 Cash flow ($4,000) $1,500 $1,200 $2,395 If the firm's cost of capital is 14%, which of the following statements is true? a.the IRR is greater than the cost of capital and the project should be undertaken b.the project should be rejected because the IRR is 12%, which is less than the project's cost of capital c.the IRR is less than 12% and the project should...
Assuming a project having the following cash flows: Year 0 1 2 3 4 Cash flow...
Assuming a project having the following cash flows: Year 0 1 2 3 4 Cash flow -6000 500 -500 5000 3000 What is the NPV of this project if the discount rate is 5%? Report the answer with 2 numbers after decimal place What is the IRR of this project? Report the answer in percentage term with 2 numbers after decimal place such as 12.43%. What discount rate will make NPV of this project equals to -494.258 Report the answer...
For the following set of cash flows,    Year Cash Flow 0 –$9,700            1 4,100...
For the following set of cash flows,    Year Cash Flow 0 –$9,700            1 4,100            2 3,400            3 4,400               a. What is the NPV at a discount rate of 0 percent? 2,200.00 $2,266.00 $2,310.00 $2,090.00 $2,134.00    b. What is the NPV at a discount rate of 15 percent? $-670.82 $-690.95 $-704.36 $-637.28 $-650.70    c. What is the NPV at a discount rate of 23 percent? $-1,754.84 $-1,807.48 $-1,842.58 $-1,667.10 $-1,702.19 d. What is...
A project has the following cash flows: Year Cash Flow 0 –$ 15,400 1 6,100 2...
A project has the following cash flows: Year Cash Flow 0 –$ 15,400 1 6,100 2 7,400 3 5,900 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ 4,000 What is the NPV at a discount rate of 8 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ 1,276.06 What is...
Lepton Industries has a project with the following projected cash​ flows: Initial cost: $470,000 Cash flow...
Lepton Industries has a project with the following projected cash​ flows: Initial cost: $470,000 Cash flow year one: $120,000 Cash flow year two: $300,000 Cash flow year three: $193,000 Cash flow year four: $120,000 a. Using a discount rate of 11% for this project and the NPV​ model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 14%? c. Should the company accept or reject it...