Question

The following are the cash flows of two projects: Year Project A Project B 0 $...

The following are the cash flows of two projects: Year Project A Project B 0 $ (350 ) $ (350 ) 1 180 250 2 180 250 3 180 250 4 180 a. Calculate the NPV for both projects if the opportunity cost of capital is 16%. (Do not round intermediate calculations. Round your answers to 2 decimal places.)

Homework Answers

Answer #1

NPV = Total PV of cash inflows – Initial investment

Computation NPV in tabular format:               

Project A

Project B

Year

Computation of PV Factor

PV factor @ 16 % (F)

Cash Flow CA

PV (CA x F)

Cash Flow CB

PV (CB x F)

0

1/(1+0.16)^0

1

($350)

($350)

($350)

($350)

1

1/(1+0.16)^1

0.862068965517241

$180

$155.1724137931

$250

$215.5172413793

2

1/(1+0.16)^2

0.743162901307967

$180

$133.7693222354

$250

$185.7907253270

3

1/(1+0.16)^3

0.640657673541351

$180

$115.3183812374

$250

$160.1644183853

4

1/(1+0.16)^4

0.552291097880475

$180

$99.4123976185

NPV

$153.6725148845

$211.4723850916

NPV of Project A is $ 153.67 and that of Project B is $ 211.47

*There is no cash flow given in year 4 for Project B.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (210 ) $ (210 ) 1 90 110 2 90 110 3 90 110 4 90 a. Calculate the NPV for both projects if the opportunity cost of capital is 17%. (Do not round intermediate calculations. Round your answers to 2 decimal places.)
The following are the cash flows of two independent projects: Year Project A Project B 0...
The following are the cash flows of two independent projects: Year Project A Project B 0 $ (230 ) $ (230 ) 1 110 130 2 110 130 3 110 130 4 110 a. If the opportunity cost of capital is 11%, calculate the NPV for both projects. (Do not round intermediate calculations. Round your answers to 2 decimal places.) b. Which of these projects is worth pursuing? Project A Project B Both Neither
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (210 ) $ (210 ) 1 90 110 2 90 110 3 90 110 4 90 If the opportunity cost of capital is 12%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) project A: project B:
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (390 ) $ (390 ) 1 220 290 2 220 290 3 220 290 4 220 a. Calculate the NPV for both projects if the opportunity cost of capital is 17%. Project A: Project B:
Here are the cash-flow forecasts for two mutually exclusive projects: Cash Flows (dollars) Year Project A...
Here are the cash-flow forecasts for two mutually exclusive projects: Cash Flows (dollars) Year Project A Project B 0 − 120 − 120 1 50 69 2 70 69 3 90 69 a-1. What is the NPV of each project if the opportunity cost of capital is 2%? (Do not round intermediate calculations. Round your answers to 2 decimal places.) a-2. Which project would you choose? b-1. What is the NPV of each project if the opportunity cost of capital...
Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 0 1...
Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 0 1 2 3 4 A − 6,300 + 1,325 + 1,325 + 3,650 0 B − 2,300 0 + 2,300 + 2,650 + 3,650 C − 6,300 + 1,325 + 1,325 + 3,650 + 5,650 a. What is the payback period on each of the projects? b. If you use a cutoff period of 2 years, which projects would you accept? Project A Project B...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$40,000...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$40,000       –$180,000       1 25,000       15,000       2 22,000       45,000       3 20,000       50,000       4 15,000       275,000       The required return on these investments is 11 percent. Required: (a) What is the payback period for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).) Payback period   Project A years     Project B years  ...
Consider the following projects: Cash Flows ($) Project C0 C1 D –10,900 21,800 E –20,900 36,575...
Consider the following projects: Cash Flows ($) Project C0 C1 D –10,900 21,800 E –20,900 36,575 Assume that the projects are mutually exclusive and that the opportunity cost of capital is 8%. a. Calculate the profitability index for each project. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project Profitability Index D E b-1. Calculate the profitability-index using the incremental cash flows. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Profitability-index b-2....
Consider the following projects: Cash Flows ($) Project C0 C1 D –11,300 22,600 E –21,300 37,275...
Consider the following projects: Cash Flows ($) Project C0 C1 D –11,300 22,600 E –21,300 37,275 Assume that the projects are mutually exclusive and that the opportunity cost of capital is 9%. a. Calculate the profitability index for each project. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project Profitability Index D E b-1. Calculate the profitability-index using the incremental cash flows. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Profitability-index b-2....
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 11 percent. Year Dry Prepreg Solvent Prepreg 0 –$ 1,740,000 –$ 770,000 1 1,104,000 395,000 2 908,000 640,000 3 754,000 398,000    a. What is the payback period for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)     b. What is the NPV for both projects? (Do not round intermediate...