Question

Project X has an expected cash outflow at time zero of 1,516 and has the following...

  1. Project X has an expected cash outflow at time zero of 1,516 and has the following projected cash inflows over the next six years:

Year

Amount

1

148

2

223

3

364

4

401

5

564

6

669

  1. The company's weighted average cost of capital is 12.8%. What is the net present value of this project? (Show your answer to the nearest dollar, and if negative, include a minus sign, e.g. -123 or 123)

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
If a project has a net present value equal to zero, then: Group of answer choices...
If a project has a net present value equal to zero, then: Group of answer choices the project earns a return exactly equal to the discount rate. the total of the cash inflows must equal the initial cost of the project. a decrease in the project's initial cost will cause the project to have a negative NPV. any delay in receiving the projected cash inflows will cause the project to have a positive NPV. the project's PI must be also...
What is the net present value of a project that has an initial cash outflow of...
What is the net present value of a project that has an initial cash outflow of $-11,400, at time 0, and the following cash flows for years 1-4? The required return is 10.0%. DO NOT USE DOLLAR SIGNS OR COMMAS IN YOUR ANSWER. ENTER YOUR ANSWER TO THE NEAREST DOLLAR (e.g. 1250). Year Cash Flows 1 $4,500 2 $4,350 3 $5,400 4 $7,250 Question 1 options: Answer Question 2 (1 point) A project has cash flows of -$163,500, $60,800, $62,300...
A project has the following cash flows: Year Cash Flow 0 $ 72,500 1 –51,500 2...
A project has the following cash flows: Year Cash Flow 0 $ 72,500 1 –51,500 2 –28,000 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return             % What is the NPV of this project if the required return is 6 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your...
If a project being considered has normal cash flows, with one outflow followed by a series...
If a project being considered has normal cash flows, with one outflow followed by a series of inflows, which of the following statements is CORRECT? A If a project's NPV is greater than zero, then its IRR must be less than the WACC. B If a project's NPV is greater than zero, then its IRR must be less than zero. C The higher the WACC used to calculate the NPV, the lower the calculated NPV will be. D A project's...
A project has the following cash flows: Year Cash Flow 0 $ 68,500 1 –44,500 2...
A project has the following cash flows: Year Cash Flow 0 $ 68,500 1 –44,500 2 –31,200 what is the net present value of this project if the required rate of return is 4 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
We are evaluating a project that costs $717,000, has a twelve-year life, and has no salvage...
We are evaluating a project that costs $717,000, has a twelve-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 154,000 units per year. Price per unit is $39, variable cost per unit is $25, and fixed costs are $722,019 per year. The tax rate is 38 percent, and we require a 18 percent return on this project. Requirement 1: Calculate the accounting break-even point.(Round your...
Hamilton Control Systems will invest $86,000 in a temporary project that will generate the following cash...
Hamilton Control Systems will invest $86,000 in a temporary project that will generate the following cash inflows: Year Cash Flow 1 $23,000 2 35,000 3 60,000 The firm will also be required to spend $11,000 to close the project at the end of the three years. a. Compute the net present value if the cost of capital is 8 percent. (Do not round intermediate calculations. Round the final answer to the nearest whole dollar. Negative answer should be indicated by...
If you assume that a project being considered has normal cash flows, with one outflow followed...
If you assume that a project being considered has normal cash flows, with one outflow followed by a series of inflows, which statement would be correct? Question 11 options: a) The lower the cost of capital used to calculate a project's NPV, the lower the calculated NPV will be. b) If a project's NPV is less than zero, then its IRR must be less than the cost of capital. c) A project’s NPV is found by compounding the cash inflows...
A project has the following cash flows: Year Cash Flow 0 –$ 16,600 1 7,300 2...
A project has the following cash flows: Year Cash Flow 0 –$ 16,600 1 7,300 2 8,600 3 7,100 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) What is the NPV at a discount rate of 12 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) What is the NPV at a discount rate...
A project has the following cash flows: Year Cash Flow 0 –$ 15,400 1 6,100 2...
A project has the following cash flows: Year Cash Flow 0 –$ 15,400 1 6,100 2 7,400 3 5,900 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ 4,000 What is the NPV at a discount rate of 8 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ 1,276.06 What is...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT