Question

The Hardware Warehouse is evaluating the safety stock policy for all its items, as identified by...

The Hardware Warehouse is evaluating the safety stock policy for all its items, as identified by the SKU code. For SKU M4389, the company always orders 80 units each time an order is placed. The daily demand is constant, at 5 units per day; the lead time is normally distributed, with a mean of three days and a standard deviation of two days. Holding cost is $3 per unit per year. A 95% service level is to be maintained.

1)  What is the total annual holding cost?

Use Excel QM to show answer

Homework Answers

Answer #1

Using QM, we get the following output:

Path: Go to QM tab on Excel ---> Alphabetical ----> Inventory ----> Reorder point/safety stock (with normal distribution)

Safety stock (SS) = 16.45

Total annual holding cost (THC) = (Q/2)*Ch + SS*Ch where

Q = order quantity = 80; Ch = holding cost/unit per year = $3; SS = 16.45

(80/2)*3 + (16.45*3) = $169.35

1). Total annual holding cost = 169.35

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units...
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units a week, and safety stock is 200 units. What is the average inventory if 10 weeks’ supply is ordered at one time? What is the order point? The standard deviation of demand during the lead time is 100 units. Calculate the safety stock required for the following service levels: 75%, 80%, 85%, 90%, 95%, and 99.99%. Calculate the change in safety stock required to...
Assuming that there is no safety stock and that the present stock level is 400 components,...
Assuming that there is no safety stock and that the present stock level is 400 components, when should the next order be placed? (Assume a 360-day year.) (1 mark) COVID-19 Ltd produces a specialized product; LOCKDOWN which has a constant monthly demand of 4000 units. The LOCKDOWN requires a component which COVID-19 Ltd purchases from a supplier at GHS10 per unit. The component requires a three-day lead time from the date of order to the date of delivery. The ordering...
Bed Bath & Microwaves has problems with its best-selling microwave—the SonicMicrowave. Hank, the owner, tells you...
Bed Bath & Microwaves has problems with its best-selling microwave—the SonicMicrowave. Hank, the owner, tells you that he always seems to have too many or too few of the SonicMicrowave. He has hired you to help determine how much and when to order. At the same time, the company is considering quotes from 2 different suppliers, and you will help compare suppliers. You estimated the following information from the detailed records that Hank kept on the microwave. You calculated the...
Southeastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices....
Southeastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices. The yearly demand for these connectors is 16,000 units. Southeastern estimates its annual holding cost for this item to be $25 per unit. The cost to place and process an order from the supplier is $70. The company operates 300 days per year, and the lead time to receive an order from the supplier is 2 working days. a. Find the economic order quantity....
Retailers Warehouse (RW) is an independent supplier of household items to department stores. RW attempts to...
Retailers Warehouse (RW) is an independent supplier of household items to department stores. RW attempts to stock enough items for a 90 percent service probability. A stainless steel knife set is one item it stocks. Demand (1,800 sets per year) is relatively stable over the entire year. Whenever new stock is ordered, a buyer must assure that numbers are correct for stock on hand and then phone in a new order. The total cost involved to place an order is...
You manage inventory for your company and use a continuous review inventory system to control reordering...
You manage inventory for your company and use a continuous review inventory system to control reordering items for stock. Your company is open for business 300 days per year. One of your most important items experiences demand of 20 units per day, normally distributed with a standard deviation of 3 units per day. You experience a lead time on orders from your supplier of six days with a standard deviation of two days. The unit price, regardless of order size,...
Jake, Inc. begins a review of ordering policies for its continuous review system by checking the...
Jake, Inc. begins a review of ordering policies for its continuous review system by checking the current policies for a sample of its A items. Following are the characteristics of one item: Demand (D) = 94 units/week (assume 52 weeks per year) Ordering and setup cost (S) = $720/order Holding cost (H) = $23/unit/year Lead time (L) = 3 weeks Standard deviation of weekly demand = 30 units Cycle-service level = 82 percent Develop the best policies for a periodic-review...
Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine...
Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost $30 Annual holding cost $100 per subassembly Daily production 40 subassemblies Annual usage 4,500 (50 weeks times ×5 days each times ×daily usage of 18 subassemblies) Lead time 12 days Safety stock 4 days' production 1.) Kanban container size = _____ units (round your response to the nearest whole...
Pauline Found​ Manufacturing, Inc., is moving to kanbans to support its telephone​ switching-board assembly lines. Determine...
Pauline Found​ Manufacturing, Inc., is moving to kanbans to support its telephone​ switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed.                                                                                                      Setup cost ​$30   Annual holding cost ​$120 per subassembly   Daily production 20 subassemblies   Annual usage 4,000 ​(50 weeks x 5 days each x daily usage of 16 ​subassemblies) Lead time 12 days Safety stock 3 ​days' production Kanban container size​ = units ​(round your response to the nearest whole​ number). Number...
Pauline Found​ Manufacturing, Inc., is moving to kanbans to support its telephone​ switching-board assembly lines. Determine...
Pauline Found​ Manufacturing, Inc., is moving to kanbans to support its telephone​ switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed.                                                                                                      Setup cost ​$30   Annual holding cost ​$110 per subassembly   Daily production 25 subassemblies   Annual usage 4,500 ​(50 weeks x 5 days each x daily usage of 18 ​subassemblies)     Lead time 10 days Safety stock 4 ​days' production Kanban container size​ =    units ​(round your response to the nearest whole​ number)....
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT