Question

A project that provides annual cash flows of $21,000 for 6 years costs $61,000 today. 1)...

A project that provides annual cash flows of $21,000 for 6 years costs $61,000 today.
1) If the required return is 14 percent, what is the NPV for this project?
A) $18.595.82
B) $20,662.02
C) $22,728.22
D) $23,761.32
E) $24,794.42

2) Determine the IRR for this project.
A) 25.70%
B) 23.13%
C) 28.27%
D) 30.84%
E) 29.55%

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
34. A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today....
34. A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a. If the required return is 10 percent, what is the NPV for this project? a. If the required return is 10 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $11,300 for 9 years costs $60,209 today. a....
A project that provides annual cash flows of $11,300 for 9 years costs $60,209 today. a. If the required return is 16 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $12,800 for 12 years costs $87,215 today.   ...
A project that provides annual cash flows of $12,800 for 12 years costs $87,215 today.    a. If the required return is 13 percent, what is the NPV for this project?    b. Determine the IRR for this project.
A project that provides annual cash flows of $2,900 for 10 years costs $15,300 today. Required:...
A project that provides annual cash flows of $2,900 for 10 years costs $15,300 today. Required: (a) If the required return is 8 percent, what is the NPV for this project? (b) Determine the IRR for this project.
A project that provides annual cash flows of $20,500 for 7 years costs $82,000 today. a....
A project that provides annual cash flows of $20,500 for 7 years costs $82,000 today. a. If the required return is 10 percent, what is the NPV for this project? Determine the IRR for this project.
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today. What...
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today. What is the NPV for the project if the required return is 7 percent? What is the NPV for the project if the required return is 19 percent? At what discount rate would you be indifferent between accepting the project and rejecting it?
A project that provides annual cash flows of $17,300 for nine years costs $79,000 today. THREE...
A project that provides annual cash flows of $17,300 for nine years costs $79,000 today. THREE QUESTIONS: What is the NPV for the project if the required return is 8 percent What is the NPV for the project if the required return is 20 percent At what discount rate would you be indifferent between accepting the project and rejecting it ?
A project that provides annual cash flows of $13,738 for eight years costs $84,486 today. What...
A project that provides annual cash flows of $13,738 for eight years costs $84,486 today. What is the NPV for the project if the required return is 7 percent? (Negative amount should be indicated by a minus sign. Round your answer to the nearest dollar. (e.g., 32.16)
A project that provides annual cash flows of $2,700 for nine years costs $8,800 today. Requirement...
A project that provides annual cash flows of $2,700 for nine years costs $8,800 today. Requirement 1: At a required return of 9 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)   NPV   $    Requirement 2: At a required return of 28 percent, what is the NPV of the project? Use the IRR function. (Do not round intermediate calculations. A negative amount should be indicated by a...
A project that provides annual cash flows of $11,700 for nine years costs $63,000 today. What...
A project that provides annual cash flows of $11,700 for nine years costs $63,000 today. What is the NPV for the project if the required return is 8 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) At a required return of 8 percent, should the firm accept this project? Accept Reject What is the NPV for the project if the required return is 20 percent? (A negative answer should be indicated by...