PLEASE PAY ATTENTION TO THIS QUESTION.. I AM STUCK BETWEEN A AND C.
Question 21
An independent project should be accepted if it
produces a net present value that is greater than the equivalent IRR. |
||
produces a profitability index greater than or equal to zero. |
||
has an IRR greater than zero. |
||
produces a net present value that is greater than zero. |
Question 14
The APR of not taking advantage of the 1/10, net 90 terms offered by a supplier is
18.18%. |
||
4.55%. |
||
7.27%. |
||
10.39%. |
21. Option d is correct option produces a net present value that
is greater than zero. because if NPV is greater than 0 then it
increases value of the firm.
Option a is incorrect because for a project to be accepted cost of
capital should be less than IRR.
Option b is incorrect because profitability index should be more
than 1 for a project to be accepted.
Option c is incorrect because IRR should be greater than cost of
capital and not zero for project to be accepted.
22. APR cost of Trade discount = Discount/(100 -discount) * 360/(
days of credit - discount period )
=1%/(100-1%) * 360/(90 - 10) = 1/99 * 365/80 = 4.55%
Option b is correct option
Get Answers For Free
Most questions answered within 1 hours.