Question

Problem Two You are considering two mutually exclusive projects with the following cash flows: Project C/F0...

Problem Two You are considering two mutually exclusive projects with the following cash flows:

Project C/F0 C/F1 C/F2 C/F3 C/F4 C/F5 C/F6

A $(41,215) $12,500 $14,000 $16,500 $18,000 $20,000 N/A

B $(46,775) $15,000 $15,000 $15,000 $15,000 $15,000 $15,000

A) Assuming that the discount rate for project A is 16% and the discount rate for B is 15%, then given that these are mutually exclusive projects, which project would you take and why?

B) If you are one of the management teams, when making a capital budgeting decision, how would you explain why the WACC is different for project A than for project B?

Homework Answers

Answer #1

B. Primarily reason for a different WACC of project A than project B is that it could be having a different set of capital structure of debt and equity. Lower the WACC, higher will be the valuations of the company and vice versa. Lower WACC also widens the scope of the company by allowing it to accept low return projects and still create value. But In present case as we see initial cost of project A is lower and it's giving a increasing NPV in time where as in project B the initial cost is higher and the cash flow is fixed even though it's creating almost same cash flow with a minor difference.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Problem Two You are considering two mutually exclusive projects with the following cash flows: (Please show...
Problem Two You are considering two mutually exclusive projects with the following cash flows: (Please show calculations) Project C/F0 C/F1 C/F2 C/F3 C/F4 C/F5 C/F6 A $(41,215) $12,500 $14,000 $16,500 $18,000 $20,000 N/A B $(46,775) $15,000 $15,000 $15,000 $15,000 $15,000 $15,000 A)Assuming that the discount rate for project A is 16% and the discount rate for B is 15%, then given that these are mutually exclusive projects, which project would you take and why? B) If you are one of...
The following are the net cash flows for a project under consideration: F0 = - $100,000...
The following are the net cash flows for a project under consideration: F0 = - $100,000 F1 = - $2,000 F2 = - $77,200 F3 = - $3,920 F4 = $232,848      a) Find all valid rates of return for this project      b) For what range of MARR should this project be accepted using FW as the figure of merit?
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 -$50,000 -$50,000 1    15,000 0 2    15,000 0 3    15,000 0 4    15,000 0 5    15,000 99,000 If the required rate of return on these projects is 10 percent, which would be chosen and why?
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $15,000 and its expected cash flows would...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $15,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $45,000 and its expected cash flows would be $9,900 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have NPV's > 0....
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $17,000, and its expected cash flows would...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $17,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $30,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Explain. Which project would you recommend? Explain.
Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would...
Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $40,500 and its expected cash flows would be $10,800 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. I. Both Projects S and L, since both projects have NPV's > 0. II. Project L, since the NPVL > NPVS....
You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you...
You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent? Year Project A Project B 0 -$80,000 -$80,000 1 31,000 0 2 31,000 0 3 31,000 0 A.) accept A at 8.5 percent and B at 13 percent B.) accept B at 8.5 percent and A at 13 percent C.) Accept B at 8.5% and neither at 13...
Consider the following two mutually exclusive projects: Year Project A Project B 0 -180,000 -18,000 1...
Consider the following two mutually exclusive projects: Year Project A Project B 0 -180,000 -18,000 1 60,000 15,000 2 100,000 15,000 3 150,000 12,000 Calculate the internal rate of return, and net present value. Assume a discount rate of 15%. Which project should be selected?
(Capital Budgeting Criteria: Mutually Exclusive Projects) Project S costs $17,000 and its expected cash flows would...
(Capital Budgeting Criteria: Mutually Exclusive Projects) Project S costs $17,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $28,500 and its expected cash flows would be $11,250 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have IRR's > 0....
10.  Problem 11.11 (Capital Budgeting Criteria: Mutually Exclusive Projects) eBook Project S costs $18,000 and its expected...
10.  Problem 11.11 (Capital Budgeting Criteria: Mutually Exclusive Projects) eBook Project S costs $18,000 and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $39,500 and its expected cash flows would be $7,900 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have...